Progress Billing:Schedule of Values, AIA G702 and G703 Lines, Florida Retainage Caps and a Sample Pay Application
Progress billing explained: the schedule of values, AIA G702 and G703 lines, Florida's 5% public retainage cap and a sample pay application for an HVAC job.
Progress billing is invoicing a long job in installments, each for the share of the contract completed since the last one. The contract price is divided into a schedule of values; each period the contractor bills the percentage complete on every line, the owner withholds an agreed retainage, and payments already made are subtracted from the total earned.
Progress billing goes wrong in the arithmetic between the lines. A schedule of values that loads the early lines bills more than the work is worth and is cut back when the architect certifies a lower amount. Retainage withheld at a rate the contract never stated, or above the statutory cap on public work, sits unpaid until closeout. A stored delivery billed as installed work is caught on the site walk and delays the whole application. FieldRanger files this guide among its invoicing and getting paid guides. It compares progress billing with the other invoice types, then covers the schedule of values, the AIA G702 and G703 forms line by line, retainage and Florida's public caps, retainage release, and over- and underbilling. A sample pay application for a county HVAC replacement, a checklist and the gap in FieldRanger's invoicing follow.
Three terms run through every application. A schedule of values is the contract price broken into lines of work, each with a dollar value, that totals the contract sum. Retainage is the share of each progress payment the owner holds back until the work is complete. A pay application is the contractor's request for one period's payment, on AIA forms or the owner's own format, which the architect or owner certifies before paying.
Progress billing compared with deposits, milestones and time-and-materials invoices
Progress billing is one of four ways a field business can invoice a job, and each fits a different kind of work.
| Method | What each invoice charges | Fits |
|---|---|---|
| Deposit and balance | A fixed share before work, the rest on completion | Short installs and replacements |
| Milestone billing | A fixed amount when a named event occurs, such as rough-in passed | Jobs with a few clear stages |
| Progress billing | The percentage complete on each schedule-of-values line, less retainage and prior payments | Commercial and public contracts over weeks or months |
| Time and materials | Hours worked and materials used in the period | Repairs and work without a fixed price |
Progress billing differs from milestone billing in what triggers the invoice. A milestone invoice is due when an event happens, whatever the cost incurred; a progress invoice is due at the end of each period, whatever events have happened, for the value of work put in place. The contract names which method applies.
The schedule of values
The schedule of values is agreed before the first application, and every application is measured against it. AIA's own summary describes the continuation sheet as breaking "the contract sum into portions of the work" according to "a schedule of values prepared by the contractor" (AIA Contract Documents help center, G702-1992 summary, checked November 12, 2026).
A usable schedule follows the way the work is measured on site. Equipment is a line by unit or by delivery, ductwork by floor or zone, controls by point list, and startup and closeout as their own lines, so that each period's percentage can be checked by someone walking the job. Lines named "labor" and "materials" for the whole project cannot be checked that way, and an architect has nothing to verify a 40% claim against.
AIA G702 and G703: the application and its continuation sheet
AIA publishes the standard forms for progress billing. Its sample of G702 states: "Use G702 when a contractor needs to formally apply for a progress payment and the architect needs to certify the amount due" (AIA Contract Documents, G702 sample, checked November 12, 2026). The forms require the contractor to show "the total dollar amount of the work completed and stored to date", "the amount of retainage (if any)", "the total of previous payments", "a summary of change orders" and "the amount of current payment requested", and they are designed for a project "where a Contractor has a direct Agreement with the Owner" (AIA summary, above).
The procedure is set in AIA's instructions. The contractor completes G703, carries its totals to G702, signs G702, "have it notarized, and submit it, together with G703, to the Architect"; the architect may certify a different amount under Sections 9.5 and 9.6 of A201, and then initials every changed figure on both forms (AIA help center, G702-1992 instructions, checked November 12, 2026). AIA lists G702 and G703 at $59.99 each for one-time use (aiacontracts.com, G702, checked November 12, 2026).
G702 line by line
G702's application section is arithmetic on G703's columns. The lines below are as printed on AIA's published sample of G702-1992.
| Line | Printed label | Source of the figure |
|---|---|---|
| 1 | Original contract sum | The signed contract |
| 2 | Net change by change orders | Approved change orders to date |
| 3 | Contract sum to date | Line 1 ± Line 2 |
| 4 | Total completed and stored to date | Column G on G703 |
| 5a | Retainage, % of completed work | Columns D + E on G703 |
| 5b | Retainage, % of stored material | Column F on G703 |
| 5 total | Total retainage | Lines 5a + 5b, or Column I of G703 |
| 6 | Total earned less retainage | Line 4 minus Line 5 total |
| 7 | Less previous certificates for payment | Line 6 from the prior certificate |
The current payment due is Line 6 less Line 7, and the balance to finish, including retainage, is Line 3 less Line 6. On G703, column D holds "the amount of completed Work covered by the previous application", column E the work completed this period, column F the "Materials Presently Stored for which payment is sought", and column G "the total of columns D, E and F" (AIA help center, G703-1992 instructions, checked November 12, 2026). Column I is "normally used only for contracts where variable retainage is permitted on a line-item basis"; where one rate applies to the whole contract, it can stay blank.
Retainage and Florida's 5% public retainage cap
Retainage is set by the contract and, on public work in some states, capped by statute. Florida is one example with a single, clear cap. For a state-level public entity, "a public entity may withhold from each progress payment" an amount "not exceeding 5 percent of the payment as retainage", and the section does not apply to construction services whose total cost in the contract is $200,000 or less (Florida Statutes 255.078, 2026 Florida Statutes). The same section permits a lower rate, a reduction on a schedule in the contract, or release of retainage at any point, and requires a contractor that receives retainage attributable to subcontractors or suppliers to "timely remit payment" of it to them.
Counties, cities and other local governmental entities follow a parallel section with the same cap: a local governmental entity "may withhold from each progress payment" an amount "not exceeding 5 percent of the payment as retainage", again excluding contracts of $200,000 or less (Florida Statutes 218.735, 2026 Florida Statutes). These caps bind public owners. A private contract in Florida sets its own rate, and the rate written in the contract is the one the pay application uses.
Retainage release and the punch list
Retainage is released when the work is accepted, and the release has its own procedure. Under section 218.735(7), a Florida local governmental entity and the contractor develop a list of items to complete within 30 calendar days after substantial completion on a project under $10 million, and within 30 to 45 days on a larger one. Within 20 business days after the list is created, the entity must pay the remaining balance, less 150% of the estimated cost to complete the listed items.
The 150% holdback is the number a contractor controls. A punch list estimated at $8,000 holds back $12,000 of the final payment; the same items finished before the list is written hold back nothing. Every open item on the list is therefore money held at one and a half times its estimated cost.
Overbilling, underbilling and front-loaded schedules
A progress billing is a claim about percentage complete, and it can be wrong in either direction. Overbilling bills more than the value of work in place: the contractor holds the owner's cash, and the next application has less to bill. Underbilling bills less than the work is worth: the contractor finances the owner's project from its own payroll and suppliers. A front-loaded schedule of values overbills by design, assigning high values to early lines such as mobilization so that the first applications collect more than the work justifies.
The certification step limits each one. An architect who walks the job compares each line's claimed percentage with what is installed, certifies a different amount under A201 Sections 9.5 and 9.6, and initials the changes. A contractor whose schedule follows site-measurable lines gives the architect fewer figures to change.
Sample pay application for a county HVAC replacement
The sample job is hypothetical: a mechanical contractor replacing four rooftop units on a Florida county building under a $480,000 contract, billing monthly with 5% retainage, the cap in section 218.735(8). The schedule of values and the period's progress are sample inputs; the retainage rate and the line structure come from the statute and AIA's form. This is the second application. The first billed mobilization in full and 20% of the ductwork.
| Line of work | Scheduled value | D: previous | E: this period | F: stored | G: total | % |
|---|---|---|---|---|---|---|
| Mobilization and submittals | $24,000 | $24,000 | $0 | $0 | $24,000 | 100% |
| Rooftop units, four | $216,000 | $0 | $108,000 | $108,000 | $216,000 | 100% |
| Ductwork | $96,000 | $19,200 | $38,400 | $0 | $57,600 | 60% |
| Controls | $60,000 | $0 | $12,000 | $0 | $12,000 | 20% |
| Startup, testing and balancing | $48,000 | $0 | $0 | $0 | $0 | 0% |
| Closeout and training | $36,000 | $0 | $0 | $0 | $0 | 0% |
| Total | $480,000 | $43,200 | $158,400 | $108,000 | $309,600 | 64.5% |
Two rooftop units were set this period and two were delivered and stored on site, so the line shows its full value as completed and stored although half the units are not yet installed. When the stored pair is set, AIA's instructions move their value out of column F and into column E: "only as materials are incorporated into the Project is their value deducted from this column".
| G702 line | Calculation | Amount |
|---|---|---|
| 3. Contract sum to date | $480,000 + $0 in change orders | $480,000 |
| 4. Total completed and stored to date | Column G | $309,600 |
| 5a. Retainage on completed work | 5% × ($43,200 + $158,400) | $10,080 |
| 5b. Retainage on stored material | 5% × $108,000 | $5,400 |
| 6. Total earned less retainage | $309,600 − $15,480 | $294,120 |
| 7. Less previous certificates | 95% × $43,200 from application 1 | $41,040 |
| Current payment due | Line 6 − Line 7 | $253,080 |
| Balance to finish, including retainage | Line 3 − Line 6 | $185,880 |
The same application under a private contract at a sample 10% retainage would hold $30,960, twice the $15,480 the statute allows the county to hold. The difference, $15,480, is cash the contractor's payroll and equipment supplier wait for until closeout.
Progress billing checklist
- Read the contract for the billing period, the application date, the retainage rate on work and on stored material, and the certifying party.
- Build the schedule of values from site-measurable lines, and have it accepted before the first application.
- On public work, check the retainage rate against the state statute; in Florida, 5% for contracts above $200,000.
- Record each line's percentage complete from the site, with photographs of installed work and delivery tickets for stored material.
- Bill stored material in column F, separate from installed work, with proof of delivery and storage.
- Carry G703 totals to G702 and compute lines 3 to 7 before signing.
- Pass retainage attributable to subcontractors and suppliers to them when it is released.
- Write the punch list before substantial completion items are finished, and close each item to cut the holdback.
- Verify: recompute the current payment due from the certified figures, and match it to the payment received.
Invoicing in FieldRanger and the progress billing gap
FieldRanger does not do progress billing or retainage: it has no schedule of values, no G702 or G703 output and no retainage balance. A contractor that bills by pay application keeps those in its accounting system or in AIA's documents.
What FieldRanger does is per-job invoicing. An estimate can be built from the HubSpot deal or contact record, or in FieldRanger and kept tied to its HubSpot deal, and the invoice is generated from the completed work order, with invoice and payment sync to QuickBooks and payment in the field through Stripe. Each day of work is its own job in FieldRanger, and technicians clock in and out with time logged against each job, so labor by day and by job is on record for the site percentages in item 4. Revenue reports show job revenue and margin by customer or service type. The contractor invoicing software page covers invoicing from work orders, the invoice template sets out the fields of a single invoice, and plans are on pricing, with Start free trial for 14 days and no card.
Frequently asked questions
What is progress billing?
Invoicing a long job in installments, each for the percentage of every schedule-of-values line completed since the last one, less retainage and less payments already certified.
What is the difference between progress billing and milestone billing?
A milestone invoice is due when a named event happens, such as an inspection passed. A progress invoice is due at the end of each period for the value of work put in place, whatever events have happened.
What are AIA G702 and G703?
G702 is the application and certificate for payment, which the contractor signs and the architect certifies. G703 is the continuation sheet that breaks the contract sum into schedule-of-values lines, with columns for previous work, this period's work and stored material.
How much retainage can be held in Florida?
On public construction contracts above $200,000, Florida's state and local government sections cap retainage at 5% of each progress payment. Private contracts set their own rate.
When is retainage released?
At completion, under the contract. On Florida local government work, the entity pays the remaining balance within 20 business days after the punch list is created, holding back 150% of the estimated cost of the open items.
On the sample application, $253,080 is due and $15,480 stays with the county, a figure fixed by one rate in a statute and two columns of a continuation sheet. Progress billing is decided when the schedule of values is written: lines a walker can measure, retainage at the rate the contract and the statute allow, and stored material kept in its own column.