What Is Job Costing? Definition and Example
What is job costing: tracing labor, materials and overhead to one job and comparing actual cost with the estimate and price. A plumbing repipe costed by line.
Job costing is the method of recording the actual cost of each job on its own: labor hours at their rate, materials, vehicle and other direct costs, and a share of overhead, compared with the job's price and estimate. In field service the job is one work order or project, recorded on a job cost sheet.
OpenStax defines job order costing as an accounting system that traces the individual costs directly to a final job or service, and lists repair service providers among its users (OpenStax, Principles of Managerial Accounting, 4.1, February 14, 2019). The entry sits in the field service glossary of FieldRanger, which runs field service work inside HubSpot.
Job costing on a whole-house PEX repipe
In this illustration, a plumbing company repipes a two-bath house for $6,800 against an estimate of 32 labor hours; price, materials and overhead are illustrative. The median wage for plumbers was $30.67 an hour in May 2025 (BLS Occupational Outlook Handbook, modified October 29, 2026). At wages of 70.0 percent of compensation (BLS Employer Costs for Employee Compensation, June 2026), the loaded rate is $43.81 an hour. Mileage uses the IRS business rate of 76 cents from July 1, 2026 (IRS, Standard mileage rates, updated July 28, 2026).
| Cost line | Estimate | Actual | Difference |
|---|---|---|---|
| Labor hours | 32.0 | 38.5 | +6.5 |
| Labor at $43.81 an hour | $1,401.92 | $1,686.69 | +$284.77 |
| PEX, fittings and valves | $1,450.00 | $1,612.00 | +$162.00 |
| Drywall patch materials | $120.00 | $145.00 | +$25.00 |
| Vehicle, 4 trips × 22 miles × $0.76 | $66.88 | $66.88 | $0.00 |
| Overhead at $18.00 per labor hour | $576.00 | $693.00 | +$117.00 |
| Total job cost | $3,614.80 | $4,203.57 | +$588.77 |
| Price | $6,800.00 | $6,800.00 | |
| Job profit | $3,185.20 | $2,596.43 | −$588.77 |
| Job margin | 46.84% | 38.18% | −8.66 points |
The sheet locates the 8.66 points: $401.77 in the extra 6.5 hours and their overhead, and $187.00 in materials. With overhead applied, the job margin sits below the job's gross profit margin, defined in what is gross profit margin. In FieldRanger, time and materials are logged against each job, and revenue reports show margin by customer or service type.
Job costing, process costing and estimating
Job costing traces cost to one job and suits work in which every job differs. Process costing accounts for cost by production process or department, for continuous production of like units (OpenStax, 4.1). Estimating forecasts a job's cost before the work; job costing records what the job consumed, and the gap corrects the next estimate. Accounting texts call the same method job order costing (OpenStax, chapter 4).
Related cost terms
- What is net profit margin: the company-wide ratio after overhead, interest and tax.
- NTE meaning: a cap on a time-and-materials job, checked against the cost record.
Frequently asked questions
What is job costing?
Recording the actual labor, materials, other direct costs and applied overhead of each job separately, and comparing the total with the job's price and its estimate.
What is the difference between job costing and process costing?
Job costing traces cost to an individual job or service. Process costing accounts for cost by production process or department across continuous production of like units.
The next repipe on the same floor plan starts from 38.5 hours, not 32, because the job cost sheet recorded the difference. Plans for FieldRanger are listed per technician on pricing, and Start free trial runs 14 days without a card.