Free Construction Invoice Template:Every Field and a Filled Progress Billing Example

Construction invoice template with every field of a progress billing request: schedule of values, change orders, retainage and a filled pay application example.

Updated 8 min read

Download .xlsxExcel spreadsheet · 15 KB · Free, no sign-upFill it in online

A construction invoice template is the payment request a contractor submits at each billing stage: the contract sum and approved change orders, a schedule of values by trade, work completed this period and to date, materials stored, retainage, earlier payments and the amount due now. The example below fills every field for a commercial tenant improvement.

The field list is free and ungated, one of the free field service templates published by FieldRanger, which makes general contractor software that runs inside HubSpot. A job billed once at completion needs only the general invoice template. This template is for a project billed in stages. Its layout follows AIA Document G702, the Application and Certificate for Payment, and its G703 continuation sheet, which breaks the contract sum into portions of the work on a schedule of values (AIA Contract Documents, Summary: G703-1992 Continuation Sheet, checked November 2026).

Construction invoice template fields

Construction invoice template fields and what goes in each
PartFieldWhat goes in it
HeaderContractorBusiness name, contact details and contractor license number
HeaderOwnerThe party billed, with the billing address
HeaderProjectProject name and site address
HeaderContractContract type, number and date
HeaderApplication number and periodThe pay application's sequence number and the period it covers
HeaderApplication date and due dateThe date submitted and the payment date the contract sets
SummaryOriginal contract sumThe price in the signed contract
SummaryNet change by change ordersApproved additions less approved deductions
SummaryContract sum to dateOriginal contract sum plus the net change
SummaryTotal completed and stored to dateThe total of the schedule of values
SummaryRetainageThe percentage withheld under the contract, on completed work and stored materials
SummaryTotal earned less retainageCompleted and stored to date, less retainage
SummaryLess previous applicationsThe amounts certified on earlier applications
SummaryCurrent payment dueTotal earned less retainage, less previous applications
SummaryBalance to finish, including retainageContract sum to date less total earned less retainage
Schedule of valuesItem and descriptionEach portion of the work, by trade, and each change order
Schedule of valuesScheduled valueThe part of the contract sum assigned to that portion
Schedule of valuesPrevious applicationsWork on that line billed on earlier applications
Schedule of valuesThis periodWork on that line completed since the last application
Schedule of valuesMaterials storedMaterials delivered but not yet installed, for which payment is sought
Schedule of valuesTotal to date and percentPrevious plus this period plus stored, and that total divided by the scheduled value
Schedule of valuesBalance to finishScheduled value less the total to date
Change ordersChange order logNumber, description, approval date and amount of each change; pending changes listed and not billed
Sign-offCertificationThe contractor's signature on the application, and the architect's or owner's approval where the contract requires it
AttachmentsLien waiversThe waivers the contract requires with each payment

The AIA instructions for G703 set the arithmetic: total to date is previous plus this period plus stored, and percent is that total over the scheduled value (AIA Contract Documents, Instructions: G703-1992 Continuation Sheet, checked November 2026). Balance to finish is the scheduled value less the total. Change orders are listed separately, at the end of the schedule or on their own sheet.

Filled construction invoice example: pay application 3 for a dental office in Fresno, California

The example is the third monthly application on a private commercial project: a 3,200 square foot dental office in an existing building. The business, owner and figures are illustrative; the retainage and payment terms follow California law for private works.

Filled construction invoice template, header (example business, illustrative entries)
FieldExample entry
ContractorExample Construction Inc., 900 Example Avenue, Fresno, CA 93721 · 559-555-0134 · license 0000000 (example)
OwnerExample Dental Group LLC, 1200 Example Street, Suite 200, Fresno, CA 93720
ProjectTenant improvement, Suite 200, 1200 Example Street, Fresno · 3,200 sq ft dental office
ContractStipulated sum, contract 2026-07, dated August 3, 2026
Application number and periodApplication 3 · October 1 to October 31, 2026
Application date and due dateNovember 3, 2026 · due within 30 days, under the contract
CertificationSigned by the contractor; approved by the owner's project manager
Lien waiversConditional waiver for this payment; unconditional waiver for application 2
Filled construction invoice template, schedule of values (illustrative figures)
ItemDescriptionScheduled valuePreviousThis periodStoredTotal to date%Balance to finish
1General conditions$38,000$15,200$7,600$0$22,80060%$15,200
2Demolition$14,500$14,500$0$0$14,500100%$0
3Framing and drywall$72,000$43,200$21,600$0$64,80090%$7,200
4Doors, frames and hardware$21,500$0$4,300$9,800$14,10066%$7,400
5Acoustical ceilings$18,400$0$5,520$0$5,52030%$12,880
6Plumbing, including dental air and vacuum$46,000$18,400$13,800$0$32,20070%$13,800
7HVAC$52,000$20,800$15,600$0$36,40070%$15,600
8Electrical$61,000$24,400$18,300$0$42,70070%$18,300
9Flooring$24,600$0$0$0$00%$24,600
10Painting$12,800$0$3,840$0$3,84030%$8,960
11Casework$31,200$0$0$12,480$12,48040%$18,720
CO-1Floor boxes for two dental chairs$6,850$0$6,850$0$6,850100%$0
CO-2Delete the storage room ceiling−$1,400$0−$1,400$0−$1,400credit$0
Totals$397,450$136,500$96,010$22,280$254,79064%$142,660
Filled construction invoice template, application summary (illustrative figures)
LineAmount
Original contract sum$392,000.00
Net change by change orders$5,450.00
Contract sum to date$397,450.00
Total completed and stored to date$254,790.00
Retainage, 5% of completed work and stored materials$12,739.50
Total earned less retainage$242,050.50
Less previous applications$129,675.00
Current payment due$112,375.50
Balance to finish, including retainage$155,399.50
Filled construction invoice template, change order log (illustrative)
Change orderDescriptionStatusAmount
CO-1Floor boxes for two dental chairs, electrical and plumbingApproved September 18, 2026$6,850.00
CO-2Delete the ceiling in the storage roomApproved October 9, 2026−$1,400.00
CO-3Relocate the sterilization sinkPending; not billed$3,200.00

Applications 1 and 2 billed $136,500.00 of work, certified at 95 percent: $129,675.00. The schedule of values began as the trade lines of the construction estimate template, with markup spread across them. The original contract sum is the fixed price accepted on a construction quote template and written into the contract.

Retainage, payment timing and change orders in California

California caps retention on private works at 5 percent: SB 61, signed on July 14, 2025, added Civil Code section 8811 (Senator Dave Cortese, SB 61 signing release, July 14, 2025). The cap limits retention to 5 percent of each payment and of the contract price, for contracts entered into on or after January 1, 2026 (Stoel Rives, New California Law Limits Retention on Private Construction Projects to 5%, September 22, 2025). Residential projects that are not mixed-use and do not exceed four stories are exempt. The example contract is dated August 3, 2026, so 5 percent is the ceiling.

Payment timing comes from older sections of the same code. The owner of a private work must pay a progress payment within 30 days after the direct contractor demands it under the contract, unless they agree otherwise in writing (California Senate Judiciary Committee, analysis of SB 61, hearing of April 8, 2025, describing Civil Code section 8800). In a good-faith dispute the owner may withhold up to 150 percent of the disputed amount, and a late payment carries a penalty of 2 percent per month. Withheld retention is due within 45 days after completion, and a direct contractor must pay a subcontractor's share within 10 days of receiving it.

A change order enters the contract sum once it is signed. AIA Document G701 records an agreed change in the work, the contract sum and the contract time, signed by the owner, architect and contractor (AIA Contract Documents, Summary: G701-2017 Change Order, checked November 2026). CO-3 stays in the log, outside the contract sum, until it is executed.

Construction invoice instructions: field by field

  1. Number the application in sequence and state the period it covers.
  2. Enter the original contract sum, then each change order approved since the contract, with deductions as negative amounts.
  3. On each line of the schedule of values, carry the previous total forward, enter the work completed this period, and enter materials stored but not installed.
  4. Total each line, and compute its percentage and balance to finish.
  5. Carry the schedule total to the summary, and apply retainage at the contract rate, within the state's cap.
  6. Subtract the previous applications to reach the current payment due.
  7. Sign the application, attach the lien waivers the contract requires, and send it on the date the contract sets.
  8. Confirm that the scheduled values sum to the contract sum to date, that no line exceeds 100 percent, and that the previous column matches the total of the last application.

Construction billing software and the pay application

A spreadsheet pay application is rebuilt each month. Its previous column is copied from the last file, so one copying error carries into every later application.

FieldRanger generates the invoice from the completed work order. Progress billing and retainage are not built, so a general contractor billing monthly against a schedule of values needs construction billing software, or the AIA progress billing template for the AIA forms. FieldRanger fits jobs billed at completion, such as service calls and small projects, and a deposit invoice can go out before the job, with the balance invoiced on completion. The estimate is built from the HubSpot deal or in FieldRanger, a won deal becomes a job with its context carried over, and job status shows on the deal record. The contractor invoicing software page sets out the FieldRanger invoice and its limits.

Fill it in here, or download the spreadsheet

The form below is the same template: totals calculate as you type, with the spreadsheet's own formulas, and your entries stay in this browser. Download it filled in, print it or save it as a PDF, or take the blank file.

Frequently asked questions

What should a construction invoice include?

The contract and application details, the original contract sum, approved change orders, a schedule of values with work completed this period and to date, stored materials, retainage, previous applications, the current payment due and the balance to finish.

What is retainage on a construction invoice?

A percentage of each payment the owner withholds until the project is complete. In California, retention on private works contracts entered into on or after January 1, 2026 may not exceed 5 percent, with an exemption for residential projects of four stories or fewer that are not mixed-use.

How is retainage calculated on a pay application?

Multiply the total completed and stored to date by the retainage rate. In the example, 5 percent of $254,790.00 is $12,739.50.

What is a schedule of values?

A breakdown of the contract sum into portions of the work, each with a scheduled value, against which each application bills a percentage complete.

How long does an owner have to pay a contractor in California?

On a private work, 30 days after the contractor demands a progress payment under the contract, unless the parties agree otherwise in writing. Late amounts carry a penalty of 2 percent per month.

Application 3 and the bills still to come

After application 3, the Fresno project has $155,399.50 left to bill, including the $12,739.50 of retainage due within 45 days after completion. Each later document, from the change order to the final invoice, has an entry in the free field service templates hub, and pricing lists FieldRanger's per-technician plans, where Start free trial gives 14 days without a card.