Free Contractor Estimate Template:Every Field and a Filled Basement Finish Example
Contractor estimate template with license, scope by trade, allowances, exclusions, payment schedule and change-order fields, filled for a Pennsylvania basement.
A contractor estimate template is the priced scope a registered or licensed contractor gives a property owner, written so that the signed copy serves as the contract: the license number, the scope by trade, allowances, exclusions, the payment schedule and the change-order terms. The example below fills every field for a basement finish in Lancaster, Pennsylvania.
FieldRanger, which makes field service software that runs inside HubSpot, publishes this field list with its other free field service templates, and none of it is gated. The contractor version differs from a one-trade estimate for a legal reason: several states set what a home improvement contract must contain before it binds the owner.
Contractor estimate template: fields and entries
The table lists the template's fields; the free .xlsx download, with no sign-up, carries them on a Template sheet. Each row becomes a box or a numbered clause in a Word or Google Docs copy.
| Field | What goes in it |
|---|---|
| Contractor | Business name, street address and telephone number |
| License or registration number | The number the state or city issues to the contractor, printed on the estimate |
| Insurance | Liability carrier and coverage amounts at signing, where the state requires them |
| Estimate number, date and expiry | A unique number, the date of the transaction and the date the prices lapse |
| Owner and job site | Each owner who signs, with address and telephone, and the area of work |
| Basis of estimate | Site visit date, measurements and any drawings the prices rest on |
| Line items by trade | Trade, task, quantity, unit, unit price and line total |
| Subcontractors | Name, address, telephone and trade of each subcontractor known at signing |
| Allowances | Each item the owner selects later, its amount and what the amount buys |
| Time-and-materials work | Work priced by the hour, with its initial estimate and cap |
| Exclusions | Work outside the price, named one by one |
| Permits | Permits the contractor obtains, and whether fees are billed at cost |
| Contract price and sales tax | The total, and the state rule behind the tax entry |
| Schedule | Approximate start and completion dates |
| Deposit and payment schedule | The down payment, special-order materials on their own line, and each progress payment with the work it pays for |
| Change-order terms | How a change is written, priced, signed and dated before the work |
| Warranty | Workmanship warranty period and coverage |
| Cancellation notice | The owner's right to cancel, in the form the state or the FTC requires |
| Acceptance | Owner's and contractor's signatures, with dates |
The general estimate template prices one trade and stops at variance terms, a deposit and a signature. The contractor version adds subcontractors, allowances, a capped hourly line, payments tied to finished work and change-order terms.
Filled contractor estimate: basement finish in Lancaster, Pennsylvania
The example finishes 820 square feet of basement with a wet bar and a built-in bookcase. The contractor's crew does the carpentry; electrical and plumbing are subcontracted. The business, owners and prices are illustrative; the terms follow Pennsylvania's Home Improvement Consumer Protection Act.
| Field | Example entry |
|---|---|
| Contractor | Example Carpentry and Remodeling LLC, 210 Example Street, Lancaster, PA 17603 · 717-555-0134 |
| License or registration number | Pennsylvania home improvement contractor registration PA000000 (example) |
| Insurance | Example Mutual: $1,000,000 personal injury, $1,000,000 property damage (illustrative) |
| Estimate number, date and expiry | CE-2026-061 · November 12, 2026 · valid until December 11, 2026 |
| Owner and job site | Elena and Marcus Ortiz, 48 Example Avenue, Lancaster, PA 17601 · 717-555-0172 · unfinished basement |
| Basis of estimate | Measured November 6, 2026; layout sketch S-1 dated November 9, 2026 |
| Subcontractors | Example Electric LLC, 15 Example Road, Lancaster, PA 17602, 717-555-0150 · Example Plumbing Co., 77 Example Pike, Lititz, PA 17543, 717-555-0181 |
| Exclusions | Egress window and any sleeping room; waterproofing beyond the capped crack repair; heating ducts; moving stored contents |
| Permits | Building permit, obtained by the contractor, billed at cost |
| Schedule | Start about January 11, 2027 · completion about February 26, 2027 |
| Change-order terms | Written change order, dated, signed by both parties and priced, before any changed work; allowance differences settled the same way |
| Warranty | Workmanship, one year from completion |
| Cancellation notice | Three-business-day rescission notice attached; registration hotline 1-888-520-6680 printed |
| Acceptance | Owners' and contractor's signatures and dates |
| Trade and task | Quantity | Unit | Unit price | Line total |
|---|---|---|---|---|
| General conditions: protection, dumpster, cleanup | 5 | week | $640.00 | $3,200.00 |
| Carpentry: frame walls, 2 x 4 on treated plate | 156 | linear ft | $31.00 | $4,836.00 |
| Insulation: 2-inch rigid foam on foundation walls | 920 | sq ft | $3.40 | $3,128.00 |
| Electrical, subcontractor quote: 3 circuits, 16 receptacles, 14 recessed lights, alarms | 1 | lot | $7,150.00 | $7,150.00 |
| Plumbing, subcontractor quote: wet bar sink | 1 | lot | $2,380.00 | $2,380.00 |
| Drywall: hang, tape and finish | 2,450 | sq ft | $3.10 | $7,595.00 |
| Carpentry: prehung interior doors | 4 | each | $440.00 | $1,760.00 |
| Carpentry: paint-grade base and casing | 290 | linear ft | $7.25 | $2,102.50 |
| Carpentry: site-built bookcase, 8 ft | 1 | each | $3,850.00 | $3,850.00 |
| Carpentry: install bar cabinets | 1 | lot | $980.00 | $980.00 |
| Paint: walls, ceiling and trim | 1 | lot | $3,600.00 | $3,600.00 |
| Flooring installation, labor only | 820 | sq ft | $3.25 | $2,665.00 |
| Trade subtotal | $43,246.50 |
| Line | Basis | Amount |
|---|---|---|
| Trade subtotal | Line items above | $43,246.50 |
| Allowance: luxury vinyl plank | 880 sq ft, owners' choice, delivered | $3,300.00 |
| Allowance: bar sink and faucet | Owners' choice, delivered | $650.00 |
| Allowance: three pendant lights | Owners' choice, delivered | $540.00 |
| Special-order materials: bar cabinets | Made to measure, not returnable | $3,240.00 |
| Building permit | At cost | $620.00 |
| Contract price | No sales tax charged | $51,596.50 |
| Time-and-materials, outside the price | Seal foundation crack: initial estimate $1,200.00, capped at $1,320.00 without a written change order | Up to $1,320.00 |
| Total potential cost | $52,916.50 |
| Payment | Work finished before it is due | Amount |
|---|---|---|
| Down payment | Contract signed; three-day rescission period ended | $8,000.00 |
| Special-order materials | Same date, separate line | $3,240.00 |
| Progress payment 1 | Framing, insulation and rough-in inspected | $12,000.00 |
| Progress payment 2 | Drywall finished | $11,000.00 |
| Progress payment 3 | Doors, trim, bookcase, cabinets and paint | $11,000.00 |
| Final payment | Flooring, final inspection, punch list | $6,356.50 |
| Total | $51,596.50 |
The crack repair is billed at actual cost, up to its cap, with the next progress payment. Each payment goes out on a contractor invoice template that quotes CE-2026-061, so the bill names the same work as the estimate.
Pennsylvania home improvement contract rules in the example
Pennsylvania's Home Improvement Consumer Protection Act states that no home improvement contract "shall be valid or enforceable against an owner" unless it meets section 7(a) (Act 132 of 2008, 73 P.S. § 517.1 et seq., checked November 2026). That section requires the registration number, approximate start and completion dates, the down payment and special-order materials on separate lines, every subcontractor known at signing, and liability coverage of at least $50,000 each for personal injury and property damage. Specifications "cannot be changed without a written change order signed by the owner and the contractor". The contract must also carry the Attorney General's toll-free number and a rescission notice: three business days from signing, "regardless of where the contract was signed". The Attorney General's contractor FAQ adds that contractors "must include their registration number in their advertisements, contracts, estimates and proposals", and gives the toll-free number as 1-888-520-6680 (Pennsylvania Office of Attorney General, Contractor FAQ, checked November 2026).
Section 9 caps deposits on contracts above $5,000 at one-third of the price, or one-third plus special-order materials designated in the contract: items that are not stock and cannot be returned for a refund or credit. One-third of $51,596.50 is $17,198.83, so the $8,000 down payment fits.
The crack repair follows the Act's time-and-materials rule: an initial cost estimate, a limit of 10 percent above it, the total potential cost in dollars, and a signed change order for anything beyond.
The tax entry is empty because Pennsylvania's business guidance says contractors are not required to collect sales tax on construction activities (Pennsylvania Business One-Stop Hub, checked November 2026). Other states set different deposit limits; the construction estimate template applies California's. This page is not legal advice.
Carpentry estimate template and the cost estimate behind it
A carpentry estimate template is the contractor estimate with carpentry priced by unit: linear feet of framing, each door, linear feet of trim, each built-in. A cost estimate template is the office sheet behind those prices: crew hours at a cost rate, materials at cost, and the margin left. The owner sees the price and never the cost estimate.
| Carpentry line | Crew hours | Labor cost | Materials | Direct cost | Price | Gross margin |
|---|---|---|---|---|---|---|
| Framing, 156 linear ft | 48 | $2,592.00 | $1,690.00 | $4,282.00 | $4,836.00 | 11.5% |
| Prehung doors, 4 | 10 | $540.00 | $820.00 | $1,360.00 | $1,760.00 | 22.7% |
| Base and casing, 290 linear ft | 20 | $1,080.00 | $610.00 | $1,690.00 | $2,102.50 | 19.6% |
| Bookcase, 8 ft | 30 | $1,620.00 | $1,080.00 | $2,700.00 | $3,850.00 | 29.9% |
| Carpentry total | 108 | $5,832.00 | $4,200.00 | $10,032.00 | $12,548.50 | 20.1% |
Gross margin is price less direct cost, divided by price, before overhead. Framing earns 11.5 percent against 29.9 percent on the bookcase: the estimator raises the framing price or accepts the thin line to win the job. Afterwards, the crew's logged hours replace the 108 estimated ones.
Contractor estimate instructions in order of preparation
- Measure the site, photograph the conditions the price depends on, and date the visit.
- Write the scope trade by trade, in the order the crews will work.
- Price each line from the cost estimate or a dated subcontractor quote, and name each known subcontractor.
- Set an allowance for each unchosen item, and move work that cannot be priced until opened into a capped time-and-materials line.
- List exclusions, permits and the tax treatment for the state of the work.
- Total the contract price, then set the deposit within the state's limit, with special-order materials on their own line.
- Tie each progress payment to finished, inspected work, and write the change-order terms, warranty and cancellation notice.
- Confirm that the payments add to the contract price, that the deposit is under the cap, and that every subcontractor in the line items appears in the subcontractor row.
Estimating software after the signed contractor estimate
On paper, the Lancaster figures are copied three times after signature, into the schedule, the change orders and the invoices, while the crew hours sit on timesheets apart from the cost estimate they would correct.
In FieldRanger, the estimate is built from the HubSpot deal or contact record without leaving HubSpot, or in FieldRanger, tied to the HubSpot deal it belongs to; either way it writes the HubSpot deal's line items and amount, and it goes out for signature through PandaDoc. The won deal becomes a job with its context carried over, and the deal record shows the job's status. A deposit invoice goes out before the work starts, with the balance invoiced on completion. Technicians clock in and out with time logged against each job, the invoice is generated from the completed work order, and revenue reports show margin by customer or service type. The estimating software page covers the estimate itself. FieldRanger has no progress billing or retainage, so a remodeler billing against a schedule of values needs construction billing software beside it. A seven-week remodel also runs as one job per day, because multi-day jobs are not built.
Fill it in here, or download the spreadsheet
The form below is the same template: totals calculate as you type, with the spreadsheet's own formulas, and your entries stay in this browser. Download it filled in, print it or save it as a PDF, or take the blank file.
Frequently asked questions
What should a contractor estimate include?
The license or registration number, the owner and job site, line items by trade, subcontractors, allowances, exclusions, permits, the price and tax treatment, the schedule, the deposit and payment schedule, change-order terms, the warranty, the cancellation notice and signatures.
Is there a free contractor estimate template?
Yes. The page offers a free .xlsx download with no sign-up: a Template sheet with every field and the line items, and a Sample sheet with the Lancaster estimate.
What is the difference between a contractor estimate and a cost estimate?
A contractor estimate states the price the owner signs. A cost estimate is the contractor's internal sheet behind it: crew hours at a cost rate, materials at cost and the margin on each line.
How much of a deposit can a contractor take in Pennsylvania?
On a home improvement contract above $5,000, no more than one-third of the price, or one-third plus special-order materials designated in the contract, under section 9 of the Home Improvement Consumer Protection Act.
Is a signed contractor estimate a binding contract?
It can be, once it holds the scope, price, payment terms and both signatures. In Pennsylvania it binds the owner only if it also carries the section 7(a) items, such as the registration number and rescission notice.
The Lancaster basement from signature to final payment
Estimate CE-2026-061 governs what follows it: the change order that settles the flooring allowance once the Ortizes choose a plank, the crack repair billed against its $1,320.00 cap, and four payments, each drawn from the free field service templates. Per-technician prices for FieldRanger are listed on pricing; a 14-day Start free trial asks for no card.