Template
Fence Estimate Template:Linear Feet, Post Spacing, Gates, Materials, Permit, 811 Locate and HOA Approval
Fence estimate template with linear feet, post spacing, gates, materials by type, permit, 811 locate and HOA approval lines, filled for Van Buren, Arkansas.
A fence estimate template is the priced scope of a fence job: the fence line in linear feet, posts and their spacing, gates, materials by type, removal, the permit, the 811 utility locate, HOA approval, exclusions, the price and the terms. The example prices a 6-foot cedar privacy fence with two gates in Van Buren, Arkansas.
The field list is one of the free field service templates kept by FieldRanger, the fencing software that runs inside HubSpot. The general estimate template covers any trade. This page adds the rows a fence needs before a post hole is dug: the survey line, the easements, the locate ticket and the association's approval.
Fence estimate fields: fence line, posts, gates, materials and approvals
| Field | What goes in it |
|---|---|
| Contractor | Business name, address, telephone, and the liability insurer and limit |
| Estimate number, date and expiry | A unique number, the issue date and the date the price lapses |
| Customer and property | Name, address, subdivision and lot, and the homeowners association, if any |
| Survey and property line | The survey or plot plan used, whether the pins were found, and the setback from the line |
| Fence line | Each run with its length, the total in linear feet, the height and the style |
| Posts | Material and size, spacing, count by type (line, corner, end, gate), hole depth and footing |
| Rails and infill | Rails per section, and pickets, panels or fabric with the count and waste allowance |
| Gates | Width, count, frame, hinges, latch, drop rod, and the gate post size |
| Grade and obstacles | Slope along each run, stepped or racked sections, trees, rock and buried obstructions |
| Removal | Existing fence to remove, its length, and haul-off |
| Easements | Utility and drainage easements on the plot plan, and how the fence treats each |
| Permit | Issuing department, what the application needs, and the fee |
| Utility locate | The 811 ticket number, the date called, and the dates digging may start and must end |
| HOA approval | Application date, approval reference, and the style, height and color approved |
| Finished side | Which face points outward |
| Exclusions | Survey work, rock drilling, irrigation repair, stain or sealer unless listed |
| Price and options | Line items with the total, and options listed outside it |
| Terms and acceptance | Deposit, balance due, payment methods, signature and date |
Fence materials by type and the components each estimate lists
The materials rows change with the fence type, and so does the unit of the infill.
| Fence type | Posts | Framing | Infill | Gate hardware |
|---|---|---|---|---|
| Wood privacy | Pressure-treated or cedar posts rated for ground contact, set in concrete | Two or three rails per section | Pickets counted by width, plus a waste allowance | Steel frame kit or Z-brace, hinges, latch, drop rod |
| Vinyl | Vinyl posts, with a steel or aluminum insert at gates where the manufacturer specifies one | Routed rails sold with the panel | Panels counted per section, spacing set by the panel length | Gate kit matched to the panel line |
| Chain link | Terminal posts at ends, corners and gates; line posts between | Top rail, or a tension wire | Fabric by the roll, with tension bars and bands at each terminal | Gate frames, fork latch, drop rod |
| Aluminum or steel ornamental | Posts set in concrete or surface-mounted | Rails welded or bracketed to the panel | Panels counted per section | Self-closing hinges and latch where a pool barrier rule applies |
Filled fence estimate: 6-foot cedar privacy fence in Van Buren, Arkansas
The lot measures 80 by 130 feet, with a 10-foot utility easement along the rear lot line. The new fence replaces a 4-foot chain link fence and encloses the back yard from two returns set 10 feet behind the front of the house. The business, customers and prices are illustrative; the permit, easement and locate rows follow the Van Buren and Arkansas 811 sources cited below.
| Field | Example entry |
|---|---|
| Contractor | Example Fence Co. LLC, 700 Example Road, Van Buren, AR 72956 · 479-555-0124 · liability insurer and limit (example) |
| Estimate number, date and expiry | FE-2026-0391 · November 12, 2026 · valid until January 11, 2027 |
| Customer and property | Morgan and Lee Abara, 1806 Sample Lane, Van Buren, AR 72956 · Example Ridge subdivision, lot 14 · Example Ridge Homeowners Association |
| Survey and property line | 2019 plat survey from the closing file · all four pins found · fence set 6 in inside the side lot lines |
| Fence line | Left return 15 ft (4 ft walk gate, 11 ft fence) · left side 85 ft · rear 80 ft, on the easement line · right side 85 ft · right return 15 ft (12 ft drive gate, 3 ft fence) · total 280 lf, 264 lf of fence and 16 ft of gates · 6 ft, dog-ear privacy |
| Posts | 4x4 pressure-treated, ground-contact, 8 ft long, 8 ft on center maximum · 30 line, 4 corner, 2 walk gate · 6x6 pressure-treated for the drive gate, 2 · 38 posts · 4x4 holes 10 in by 30 in, 6x6 holes 12 in by 36 in, concrete footings |
| Rails and infill | 35 sections, three 2x4 rails each: 105 rails · 1x6 cedar dog-ear pickets, butted: 576 plus 5% waste, 605 |
| Gates | Walk gate 4 ft, steel frame kit, self-closing hinges, gravity latch · double drive gate 12 ft as two 6 ft leaves, steel frame kits, drop rod, on 6x6 posts |
| Grade and obstacles | Right side falls 2 ft toward the rear: stepped sections · one oak root zone at the left rear corner, post moved 2 ft |
| Removal | 4 ft chain link, 180 lf with posts, hauled off |
| Easements | Rear run set on the easement line, 10 ft inside the rear lot line · easement left unfenced: the 811 locate marked a buried telephone line in it |
| Permit | City of Van Buren Building Department fence permit · plot plan with easements, property lines, structures, existing and proposed fencing |
| Utility locate | Arkansas 811 ticket, called once the HOA approval and permit are in hand · number, call date and start-by date on the work order |
| HOA approval | Architectural application filed by the owners, November 13, 2026, with this estimate's drawing and material list · letter required before the locate |
| Finished side | Pickets on the outside face; rails face the yard |
| Exclusions | Boundary survey; rock below 30 in; irrigation line repair; stain or sealer |
| Terms and acceptance | 40% deposit at acceptance to order materials · balance on completion · check, card or bank transfer · owners' signatures and date |
| Line | Quantity | Unit price | Line total |
|---|---|---|---|
| Remove and haul off 4 ft chain link fence | 180 lf | $2.50 | $450.00 |
| 6 ft cedar privacy fence, three rails, 4x4 posts at 8 ft on center in concrete | 264 lf | $34.00 | $8,976.00 |
| Stepped sections on the right side run | 85 lf | $3.00 | $255.00 |
| Walk gate, 4 ft, with self-closing hinges and latch | 1 | $425.00 | $425.00 |
| Double drive gate, 12 ft, with 6x6 posts and drop rod | 1 | $1,150.00 | $1,150.00 |
| Plot plan and permit application, labor | 1 | $75.00 | $75.00 |
| Total, before the permit fee | $11,331.00 | ||
| City fence permit fee | 1 | At cost, from the city's schedule | Billed on the invoice |
| Option, outside the total: semi-transparent stain, both faces, after the wood dries | 264 lf | $3.25 | add $858.00 |
Posts, sections and pickets in the example
The counts follow from the run lengths and the spacing. Each run divides into sections of no more than 8 feet. The 85-foot sides take 11 sections and 10 line posts each, the 80-foot rear takes 10 sections and 9 line posts, and the 11-foot part of the left return takes 2 sections and 1 line post. The 3-foot panel beside the drive gate is one section with no line post. That gives 30 line posts, 35 sections, and 105 rails at three per section.
Pickets are counted by width. A 1x6 picket measures 5.5 inches across, so 264 feet of fence, 3,168 inches, takes 576 pickets butted edge to edge, and 5 percent for splits and cuts brings the order to 605. The gates carry their own pickets inside the gate kits.
Van Buren fence permit rows and easements
Van Buren requires a fence permit for all new fence construction and for replacement of existing fencing; a repair replacing less than 50 percent of the fence's linear length needs none. The application carries a plot plan showing easements, property lines, all existing structures and fencing, and the proposed fence (City of Van Buren Building Department, Fence Permit Requirements, checked November 2026). The same sheet sets the layout rules the estimate prices to:
- Fencing must be on private property, which is why the example sets its posts 6 inches inside the side lines.
- A front-yard fence may not exceed 48 inches and must be at least 10 feet from the street or public right-of-way, whichever is greater; no fence may sit in the 25-foot sight triangle.
- No fence may exceed 8 feet above the ground, and finish surfaces face outward from the property.
- A pool, pond or spa enclosure is at least 48 inches high, with no more than 2 inches between the bottom of the fence and the ground.
Easements take their own row. No fencing is allowed in or over a platted drainage easement. A fence may cross a utility easement at 90 degrees through a gate or easily removable panels, with no posts in the 10 feet of easement, where the easement lies wholly on the owner's lot. Posts may go in the easement only if One Call located no utilities there. The owner then accepts removing the fence at the owner's expense if the utility needs access, by a notarized waiver filed with the application. The example's locate found a telephone line, so the rear run stops at the easement line.
Arkansas 811 locate rows before the first post hole
Every post hole is excavation. The Arkansas Underground Facilities Damage Prevention Act requires people to contact Arkansas 811 before any digging or demolition, and Arkansas 811's own list for homeowners begins with installing a mailbox or a fence. Utilities locate their lines within two full working days after the ticket is filed. Work starts within ten working days of the day the ticket was called in, and a job not finished within 20 working days needs a renewed ticket (Arkansas 811, checked November 2026).
The estimate turns those dates into a sequence. The ticket is called only once the permit and the HOA letter are in hand, so the ten-day start window is not spent waiting on approvals. The ticket number goes on the work order, and the crew photographs the paint marks before digging. A post that lands on a mark moves, and the section lengths on each side are adjusted, as they were for the post moved at the oak.
HOA approval line and the price expiry
An association's covenants can set the height, material, color and finished face of a fence, and its architectural committee reviews the plan before work starts. The example's drawing and material list are the attachments to the owners' application, and the approval line records the reference and the date. The 60-day price expiry is set to outlast the committee's review. The work order repeats the approved height, style and finished face, because a fence that differs from the approved drawing is outside the approval.
Fence estimate instructions from the survey to the signature
- Find the survey or plat, locate the pins, and mark the fence line with its setback from each property line.
- Mark every easement from the plat, and decide how the fence treats each one.
- Measure each run, each gate opening and the slope on each run.
- Count sections, posts by type, rails and infill from the run lengths and the spacing, and add the waste allowance.
- Price removal, the fence by the linear foot, each gate, the grade adjustments and the permit work, then write the permit, locate and HOA rows in the order each happens.
- Before sending, check that the runs add to the fence line total, that posts and sections reconcile run by run, and that every gate has two gate posts.
Estimating software and the signed fence estimate
In FieldRanger, the estimate is built from the HubSpot deal or contact record without leaving HubSpot, or built in FieldRanger and kept tied to the deal, and PandaDoc sends it for signature. The won deal becomes a job with its context carried over. Posts, pickets and concrete are checked out of a specific warehouse and logged against the job for job costing.
On site, a job-specific checklist holds the estimate's conditions: permit posted, HOA letter on file, 811 ticket entered, marks photographed. Before and after photos attach to the work order and sync to the customer's HubSpot record. The 40 percent deposit goes out as a deposit invoice at acceptance, the owners sign on completion, and the balance is invoiced from the completed work order. The estimating software page describes the estimate on the deal.
Post, section and picket counts come from the arithmetic above or a takeoff tool. Plans are priced per technician on pricing, and Start free trial gives 14 days with no card.
Fill it in here, or download the spreadsheet
The form below is the same template: totals calculate as you type, with the spreadsheet's own formulas, and your entries stay in this browser. Download it filled in, print it or save it as a PDF, or take the blank file.
Frequently asked questions
What should a fence estimate include?
The property and survey, each run with its length, height and style, posts by type with spacing, rails and infill, gates, grade, removal, easements, the permit, the 811 locate, HOA approval, the finished side, exclusions, the price and the terms.
How are fence posts counted on an estimate?
Divide each run into sections no longer than the post spacing, count one line post between each pair of sections, and add the corner, end and gate posts. In the example, 280 feet of fence line with two gates takes 38 posts.
Does a fence need a permit in Van Buren, Arkansas?
Yes, for a new fence or a replacement; a repair of less than 50 percent of the fence's length needs none. The application carries a plot plan with easements, property lines, structures and the proposed fence.
Is calling 811 required before installing a fence in Arkansas?
Yes. Arkansas law requires contacting Arkansas 811 before any digging, and its homeowner list names fence installation. Utilities locate within two full working days, and work starts within ten working days of the call.
Estimate FE-2026-0391 and the order of approvals
The Abaras' fence starts with paper in a fixed order: the HOA letter, then the city permit, then the 811 ticket, and only then 605 pickets on a truck. Tracking those three approvals as dated checklist items on one HubSpot deal is the part a demo walks through. The work order and invoice forms for the build sit in the free field service templates hub.
FieldRanger runs field service inside HubSpot
Estimates, scheduling and dispatch, a technician app and invoicing on the HubSpot records sales already keeps. Every plan starts with a free trial.
Book a demo