Free Punch List Template:Every Field and a Filled Commercial Closeout Example
Punch list template for construction closeout: item, location, trade, photo, due date and sign-off, filled for an Ohio clinic, with retainage tied to closeout.
A punch list template is the closeout record of work still to be finished or corrected once a project is substantially complete: one line per item, with its location, the trade responsible, a photo, a due date and two sign-offs. Closing every line is the condition for releasing the retainage held back from each trade.
The field list is free and ungated, published with the free field service templates of FieldRanger, which makes field service software that runs inside HubSpot. The example fills it for a clinic fit-out in Ohio, where state law sets how fast retainage reaches subcontractors once the owner pays it.
Punch list template fields: header and item columns
The header identifies the project and the walk; the item columns repeat for each defect.
| Field | What goes in it |
|---|---|
| Project | Project name, address and contract number |
| Owner and general contractor | Owner's name and representative; contractor's name and superintendent |
| Architect or owner's representative | The person who verifies the list and may add to it |
| Walk date and attendees | Date of the inspection walk and everyone on it |
| Substantial completion date | The date recorded on the certificate of substantial completion |
| List number and revision | Punch list number, revision letter and revision date |
| Completion deadline | The date by which the contract requires every item closed |
| Item number | A sequential number that never changes, even when items close |
| Location | Room number and name, grid line, elevation or exterior face |
| Item description | What is wrong and what finished looks like, in one sentence |
| Trade responsible | The subcontractor or crew that owns the fix |
| Photo | Reference to the photo taken at the walk, and the photo after the fix |
| Date logged and due date | When the item was found and when it must be closed |
| Status | Open, ready for review, or closed |
| Contractor sign-off | Superintendent's initials and date when the trade reports the item fixed |
| Verification | Architect's or owner's initials and date after the back-check |
| Back-charge | The trade charged when another crew performs the fix, and the amount |
The description states the finished condition, not the defect alone. "Grab bar loose" invites argument; "grab bar anchored to blocking, no movement under hand load" can be verified in one visit.
Filled punch list: physical therapy clinic tenant improvement in Dublin, Ohio
The project fits out a 4,100-square-foot suite as a physical therapy clinic, walked on November 10, 2026. The companies, people and amounts are illustrative; the statute and the AIA form are cited from their sources.
| Field | Example entry |
|---|---|
| Project | Example Physical Therapy fit-out, Suite 200, 4800 Example Parkway, Dublin, OH 43017 · contract EB-2026-031 |
| Owner and general contractor | Example Physical Therapy LLC, Dr. Anita Shah · Example Builders LLC, superintendent Marco Diaz |
| Architect or owner's representative | Example Architects, Rachel Kim |
| Walk date and attendees | November 10, 2026 · Shah, Kim, Diaz, and foremen for electrical, mechanical and drywall |
| Substantial completion date | November 11, 2026 |
| List number and revision | PL-01, revision B, November 25, 2026 |
| Completion deadline | November 30, 2026, the owner's move-in date |
| No. | Location | Item and finished condition | Trade | Photo | Due | Status and sign-off |
|---|---|---|---|---|---|---|
| 1 | 104 Treatment 1 | Cover plate installed on north-wall receptacle | Example Electric | P-01, P-01A | Nov 17 | Closed · MD Nov 13 · RK Nov 25 |
| 2 | 104 Treatment 1 | Three nail pops above door set, finished and painted to match | Example Drywall and Paint | P-02, P-02A | Nov 18 | Closed · MD Nov 17 · RK Nov 25 |
| 3 | Corridor C1 | Paint touch-up beside corner guard, east wall | Example Drywall and Paint | P-03, P-03A | Nov 18 | Closed · MD Nov 17 · RK Nov 25 |
| 4 | 110 Gym | Rubber floor seam re-adhered flat for 14 inches at column C-3 | Example Flooring | P-04, P-04A | Nov 20 | Closed · MD Nov 19 · RK Nov 25 |
| 5 | 112 Restroom | Grab bar anchored to blocking, no movement under hand load | Example Builders carpentry | P-05, P-05A | Nov 17 | Closed · MD Nov 16 · RK Nov 25 |
| 6 | 112 Restroom | Lavatory faucet stops dripping when closed | Example Plumbing | P-06, P-06A | Nov 17 | Closed · MD Nov 16 · RK Nov 25 |
| 7 | 115 Office | Door closer adjusted so the door latches without slamming | Example Builders carpentry | P-07, P-07A | Nov 18 | Closed · MD Nov 18 · RK Nov 25 |
| 8 | 101 Reception | Countertop seam gap filled and color-matched | Example Millwork | P-08, P-08A | Nov 20 | Closed · MD Nov 20 · RK Nov 25 |
| 9 | 101 Reception | Stained ceiling tile at grid C-4 replaced after leak source found | Example Builders carpentry | P-09, P-09A | Nov 20 | Closed · MD Nov 20 · RK Nov 25 |
| 10 | Roof above grid C-4 | Rooftop unit condensate line re-pitched and trapped; no water at grid C-4 after a 30-minute run | Example Mechanical | P-10, P-10A | Nov 20 | Closed · MD Dec 3 · RK Dec 4 |
| 11 | 108 Treatment 5 | Supply diffuser aligned to ceiling grid | Example Mechanical | P-11, P-11A | Nov 18 | Closed · MD Nov 18 · RK Nov 25 |
| 12 | 118 Break room | Dishwasher secured to countertop underside with both brackets | Example Builders carpentry | P-12, P-12A | Nov 17 | Closed · MD Nov 16 · RK Nov 25 |
| 13 | 120 Electrical room | Panel directory typed and matching circuits as installed | Example Electric | P-13, P-13A | Nov 20 | Closed · MD Nov 19 · RK Nov 25 |
| 14 | Throughout | Window sills, light lenses and diffuser faces cleaned | Example Builders cleaning crew | P-14 | Nov 24 | Closed · MD Nov 24 · RK Nov 25 |
Items 9 and 10 show why each line names one trade. The stained tile was a symptom of a roof-level leak, so the tile went to the carpenters and the leak to the mechanical subcontractor. Item 10 waited on a condensate trap until December 3; the November 25 back-check left it as the only open line.
Substantial completion, the punch list and retainage
The punch list belongs to substantial completion. AIA's product page for Document G704, the Certificate of Substantial Completion, states that "the contractor prepares a punch list of items to be completed or corrected" and that "the architect verifies and may amend it" (AIA Contract Documents, G704, checked November 2026). The same page states that executing the form "triggers warranty periods and the release of retainage". Final completion follows when the last item closes.
Retainage is the share of each progress payment held back until the work is accepted. The example subcontracts hold 10 percent, an illustrative term.
| Subcontractor | Subcontract amount | Retainage held at 10% | Last punch item closed | Interest per day if paid late at 18% a year |
|---|---|---|---|---|
| Example Electric LLC | $62,400.00 | $6,240.00 | November 25 | $3.08 |
| Example Drywall and Paint Co. | $48,750.00 | $4,875.00 | November 25 | $2.40 |
| Example Mechanical LLC | $57,900.00 | $5,790.00 | December 4 | $2.86 |
| Example Flooring Inc. | $21,300.00 | $2,130.00 | November 25 | $1.05 |
| Example Plumbing Co. | $18,600.00 | $1,860.00 | November 25 | $0.92 |
| Example Millwork LLC | $14,200.00 | $1,420.00 | November 25 | $0.70 |
| Total | $223,150.00 | $22,315.00 |
The owner approved the work on December 4, after item 10's verification, and paid final retainage to the general contractor on December 18, 2026. That date sets every subcontractor's deadline.
Ohio prompt payment rules for retainage on the example
Ohio fixes the general contractor's side of the timeline. Under Ohio Revised Code 4113.61(A)(3), a contractor that receives final retainage from the owner pays each subcontractor its share within ten calendar days, provided the contractor has determined the work was satisfactorily performed and the owner has approved it (Ohio Revised Code 4113.61, effective September 29, 2011). A late payment accrues interest at 18 percent a year, starting on the eleventh day after the contractor received the owner's payment.
On the example, the owner paid on December 18, so each share is due by Monday, December 28, 2026, and interest runs from December 29. For Example Electric, that is $3.08 a day on $6,240.00. The signed punch list is the evidence for both conditions: the superintendent's initials record the contractor's determination, and the architect's initials, given for the owner, record the approval.
The statute has limits. Division (C) excludes single-, two- and three-family detached houses. The section lets the contractor deduct contract retainage and withhold amounts needed to resolve disputed liens or claims. It sets the contractor's deadline, not the owner's, which the prime contract governs. This page is not legal advice.
Punch list instructions from the walk to the back-check
- Before the walk, have each trade complete its own list, so the walk finds what the trades missed rather than everything.
- Walk room by room in plan order, with the owner's representative and the architect, and number items as they are found.
- Photograph each item at the walk and record the photo reference on its line.
- Write each description as the finished condition, and assign one trade per line.
- Set due dates that end before the completion deadline, and send each trade its lines the same day.
- Price any item outside the contract scope as a change before the work, on the estimate template the project already uses.
- As trades report items fixed, have the superintendent check and initial each one, with an after photo.
- Hold a back-check walk with the architect, record verification initials and dates, and issue a revised list with the open items only.
- Confirm that every line has both sign-offs and two photos before requesting final retainage, then bill it on the final invoice template.
FieldRanger checklists, photos and the punch list
A paper punch list passes through a clipboard, a typed spreadsheet, an email to each trade and a marked-up back-check copy. Its photos sit on phones, apart from the lines they prove.
FieldRanger holds the same record on the job. Custom checklists carry job-specific items, so each punch line can sit on the work order as a checklist item. Before and after photos attach to the work order and sync to the customer's HubSpot record, and digital signatures capture sign-off on site as proof of completion. Job status shows to dispatchers and on the HubSpot deal, and job completions and notes are logged to the HubSpot timeline.
A fix reported by telephone carries no time or place. Clock-ins and clock-outs record where each worker was, with time logged against each job, so a reported fix can be checked against who was on site that day. The GPS time tracking app page covers located clock-ins. FieldRanger has no progress billing or retainage, so the retainage release stays in the contract documents and the accounting system.
Fill it in here, or download the spreadsheet
The form below is the same template: totals calculate as you type, with the spreadsheet's own formulas, and your entries stay in this browser. Download it filled in, print it or save it as a PDF, or take the blank file.
Frequently asked questions
What is a punch list in construction?
The list of work still to be finished or corrected when a project reaches substantial completion. Each line names the item, its location and the trade responsible, and the contractor and the owner's representative sign it off when it is fixed.
What should a punch list template include?
A header with the project, the parties, the walk date and the substantial completion date, then one line per item with a number, location, description of the finished condition, trade responsible, photo reference, due date, status and two sign-offs.
Who prepares the punch list?
AIA's description of Document G704 says the contractor prepares the list of items to be completed or corrected, and the architect verifies and may amend it.
When is retainage released after the punch list?
The prime contract sets when the owner releases it. In Ohio, once the general contractor receives final retainage, ORC 4113.61 gives it ten calendar days to pay each subcontractor's share, if the work was satisfactory and the owner approved it.
Is there a free punch list template?
Yes. The page offers a free .xlsx download with no sign-up: a Template sheet with the header fields and the item columns, and a Sample sheet with the filled Dublin clinic punch list.
Item 10 and the December 28 payment date
One condensate trap held the whole closeout: item 10 closed on December 3, the owner's approval followed on December 4, and the ten-day clock for six subcontractors started only when the retainage arrived on December 18. The work orders and invoices on either side of a closeout have their own free field service templates. FieldRanger is sold per technician, as set out on pricing; Start free trial lasts 14 days and asks for no card.