A punch list template is the closeout record of work still to be finished or corrected once a project is substantially complete: one line per item, with its location, the trade responsible, a photo, a due date and two sign-offs. Closing every line is the condition for releasing the retainage held back from each trade.

The field list is free and ungated, published with the free field service templates of FieldRanger, which makes field service software that runs inside HubSpot. The example fills it for a clinic fit-out in Ohio, where state law sets how fast retainage reaches subcontractors once the owner pays it.

Punch list template fields: header and item columns

The header identifies the project and the walk; the item columns repeat for each defect.

Punch list template fields and what goes in each
FieldWhat goes in it
ProjectProject name, address and contract number
Owner and general contractorOwner's name and representative; contractor's name and superintendent
Architect or owner's representativeThe person who verifies the list and may add to it
Walk date and attendeesDate of the inspection walk and everyone on it
Substantial completion dateThe date recorded on the certificate of substantial completion
List number and revisionPunch list number, revision letter and revision date
Completion deadlineThe date by which the contract requires every item closed
Item numberA sequential number that never changes, even when items close
LocationRoom number and name, grid line, elevation or exterior face
Item descriptionWhat is wrong and what finished looks like, in one sentence
Trade responsibleThe subcontractor or crew that owns the fix
PhotoReference to the photo taken at the walk, and the photo after the fix
Date logged and due dateWhen the item was found and when it must be closed
StatusOpen, ready for review, or closed
Contractor sign-offSuperintendent's initials and date when the trade reports the item fixed
VerificationArchitect's or owner's initials and date after the back-check
Back-chargeThe trade charged when another crew performs the fix, and the amount

The description states the finished condition, not the defect alone. "Grab bar loose" invites argument; "grab bar anchored to blocking, no movement under hand load" can be verified in one visit.

Filled punch list: physical therapy clinic tenant improvement in Dublin, Ohio

The project fits out a 4,100-square-foot suite as a physical therapy clinic, walked on November 10, 2026. The companies, people and amounts are illustrative; the statute and the AIA form are cited from their sources.

Filled punch list header (example project, illustrative entries)
FieldExample entry
ProjectExample Physical Therapy fit-out, Suite 200, 4800 Example Parkway, Dublin, OH 43017 · contract EB-2026-031
Owner and general contractorExample Physical Therapy LLC, Dr. Anita Shah · Example Builders LLC, superintendent Marco Diaz
Architect or owner's representativeExample Architects, Rachel Kim
Walk date and attendeesNovember 10, 2026 · Shah, Kim, Diaz, and foremen for electrical, mechanical and drywall
Substantial completion dateNovember 11, 2026
List number and revisionPL-01, revision B, November 25, 2026
Completion deadlineNovember 30, 2026, the owner's move-in date
Filled punch list items, revision B (illustrative)
No.LocationItem and finished conditionTradePhotoDueStatus and sign-off
1104 Treatment 1Cover plate installed on north-wall receptacleExample ElectricP-01, P-01ANov 17Closed · MD Nov 13 · RK Nov 25
2104 Treatment 1Three nail pops above door set, finished and painted to matchExample Drywall and PaintP-02, P-02ANov 18Closed · MD Nov 17 · RK Nov 25
3Corridor C1Paint touch-up beside corner guard, east wallExample Drywall and PaintP-03, P-03ANov 18Closed · MD Nov 17 · RK Nov 25
4110 GymRubber floor seam re-adhered flat for 14 inches at column C-3Example FlooringP-04, P-04ANov 20Closed · MD Nov 19 · RK Nov 25
5112 RestroomGrab bar anchored to blocking, no movement under hand loadExample Builders carpentryP-05, P-05ANov 17Closed · MD Nov 16 · RK Nov 25
6112 RestroomLavatory faucet stops dripping when closedExample PlumbingP-06, P-06ANov 17Closed · MD Nov 16 · RK Nov 25
7115 OfficeDoor closer adjusted so the door latches without slammingExample Builders carpentryP-07, P-07ANov 18Closed · MD Nov 18 · RK Nov 25
8101 ReceptionCountertop seam gap filled and color-matchedExample MillworkP-08, P-08ANov 20Closed · MD Nov 20 · RK Nov 25
9101 ReceptionStained ceiling tile at grid C-4 replaced after leak source foundExample Builders carpentryP-09, P-09ANov 20Closed · MD Nov 20 · RK Nov 25
10Roof above grid C-4Rooftop unit condensate line re-pitched and trapped; no water at grid C-4 after a 30-minute runExample MechanicalP-10, P-10ANov 20Closed · MD Dec 3 · RK Dec 4
11108 Treatment 5Supply diffuser aligned to ceiling gridExample MechanicalP-11, P-11ANov 18Closed · MD Nov 18 · RK Nov 25
12118 Break roomDishwasher secured to countertop underside with both bracketsExample Builders carpentryP-12, P-12ANov 17Closed · MD Nov 16 · RK Nov 25
13120 Electrical roomPanel directory typed and matching circuits as installedExample ElectricP-13, P-13ANov 20Closed · MD Nov 19 · RK Nov 25
14ThroughoutWindow sills, light lenses and diffuser faces cleanedExample Builders cleaning crewP-14Nov 24Closed · MD Nov 24 · RK Nov 25

Items 9 and 10 show why each line names one trade. The stained tile was a symptom of a roof-level leak, so the tile went to the carpenters and the leak to the mechanical subcontractor. Item 10 waited on a condensate trap until December 3; the November 25 back-check left it as the only open line.

Substantial completion, the punch list and retainage

The punch list belongs to substantial completion. AIA's product page for Document G704, the Certificate of Substantial Completion, states that "the contractor prepares a punch list of items to be completed or corrected" and that "the architect verifies and may amend it" (AIA Contract Documents, G704, checked November 2026). The same page states that executing the form "triggers warranty periods and the release of retainage". Final completion follows when the last item closes.

Retainage is the share of each progress payment held back until the work is accepted. The example subcontracts hold 10 percent, an illustrative term.

Retainage held by subcontract on the example project (illustrative)
SubcontractorSubcontract amountRetainage held at 10%Last punch item closedInterest per day if paid late at 18% a year
Example Electric LLC$62,400.00$6,240.00November 25$3.08
Example Drywall and Paint Co.$48,750.00$4,875.00November 25$2.40
Example Mechanical LLC$57,900.00$5,790.00December 4$2.86
Example Flooring Inc.$21,300.00$2,130.00November 25$1.05
Example Plumbing Co.$18,600.00$1,860.00November 25$0.92
Example Millwork LLC$14,200.00$1,420.00November 25$0.70
Total$223,150.00$22,315.00

The owner approved the work on December 4, after item 10's verification, and paid final retainage to the general contractor on December 18, 2026. That date sets every subcontractor's deadline.

Ohio prompt payment rules for retainage on the example

Ohio fixes the general contractor's side of the timeline. Under Ohio Revised Code 4113.61(A)(3), a contractor that receives final retainage from the owner pays each subcontractor its share within ten calendar days, provided the contractor has determined the work was satisfactorily performed and the owner has approved it (Ohio Revised Code 4113.61, effective September 29, 2011). A late payment accrues interest at 18 percent a year, starting on the eleventh day after the contractor received the owner's payment.

On the example, the owner paid on December 18, so each share is due by Monday, December 28, 2026, and interest runs from December 29. For Example Electric, that is $3.08 a day on $6,240.00. The signed punch list is the evidence for both conditions: the superintendent's initials record the contractor's determination, and the architect's initials, given for the owner, record the approval.

The statute has limits. Division (C) excludes single-, two- and three-family detached houses. The section lets the contractor deduct contract retainage and withhold amounts needed to resolve disputed liens or claims. It sets the contractor's deadline, not the owner's, which the prime contract governs. This page is not legal advice.

Punch list instructions from the walk to the back-check

  1. Before the walk, have each trade complete its own list, so the walk finds what the trades missed rather than everything.
  2. Walk room by room in plan order, with the owner's representative and the architect, and number items as they are found.
  3. Photograph each item at the walk and record the photo reference on its line.
  4. Write each description as the finished condition, and assign one trade per line.
  5. Set due dates that end before the completion deadline, and send each trade its lines the same day.
  6. Price any item outside the contract scope as a change before the work, on the estimate template the project already uses.
  7. As trades report items fixed, have the superintendent check and initial each one, with an after photo.
  8. Hold a back-check walk with the architect, record verification initials and dates, and issue a revised list with the open items only.
  9. Confirm that every line has both sign-offs and two photos before requesting final retainage, then bill it on the final invoice template.

FieldRanger checklists, photos and the punch list

A paper punch list passes through a clipboard, a typed spreadsheet, an email to each trade and a marked-up back-check copy. Its photos sit on phones, apart from the lines they prove.

FieldRanger holds the same record on the job. Custom checklists carry job-specific items, so each punch line can sit on the work order as a checklist item. Before and after photos attach to the work order and sync to the customer's HubSpot record, and digital signatures capture sign-off on site as proof of completion. Job status shows to dispatchers and on the HubSpot deal, and job completions and notes are logged to the HubSpot timeline.

A fix reported by telephone carries no time or place. Clock-ins and clock-outs record where each worker was, with time logged against each job, so a reported fix can be checked against who was on site that day. The GPS time tracking app page covers located clock-ins. FieldRanger has no progress billing or retainage, so the retainage release stays in the contract documents and the accounting system.

Fill it in here, or download the spreadsheet

The form below is the same template: totals calculate as you type, with the spreadsheet's own formulas, and your entries stay in this browser. Download it filled in, print it or save it as a PDF, or take the blank file.

Frequently asked questions

What is a punch list in construction?

The list of work still to be finished or corrected when a project reaches substantial completion. Each line names the item, its location and the trade responsible, and the contractor and the owner's representative sign it off when it is fixed.

What should a punch list template include?

A header with the project, the parties, the walk date and the substantial completion date, then one line per item with a number, location, description of the finished condition, trade responsible, photo reference, due date, status and two sign-offs.

Who prepares the punch list?

AIA's description of Document G704 says the contractor prepares the list of items to be completed or corrected, and the architect verifies and may amend it.

When is retainage released after the punch list?

The prime contract sets when the owner releases it. In Ohio, once the general contractor receives final retainage, ORC 4113.61 gives it ten calendar days to pay each subcontractor's share, if the work was satisfactory and the owner approved it.

Is there a free punch list template?

Yes. The page offers a free .xlsx download with no sign-up: a Template sheet with the header fields and the item columns, and a Sample sheet with the filled Dublin clinic punch list.

Item 10 and the December 28 payment date

One condensate trap held the whole closeout: item 10 closed on December 3, the owner's approval followed on December 4, and the ten-day clock for six subcontractors started only when the retainage arrived on December 18. The work orders and invoices on either side of a closeout have their own free field service templates. FieldRanger is sold per technician, as set out on pricing; Start free trial lasts 14 days and asks for no card.