Roofing Work Order Template:Tear-Off, Deck, Flashing, Install and Disposal Lines, OSHA Fall Protection Fields and a Centennial, Colorado Reroof
Roofing work order template with tear-off, deck, flashing, install and disposal lines, OSHA fall protection fields and Centennial, Colorado permit holds.
A roofing work order template is the instruction sheet for one day on one roof: the permit and inspection holds, squares and pitch by slope, the tear-off, deck, flashing, installation and disposal tasks in order, the fall protection system for each slope, required photos, approved changes and the sign-off. The example fills day 1 of a reroof in Centennial, Colorado.
The field list is one of the free field service templates kept by FieldRanger, the roofing contractor software that runs inside HubSpot. A reroof that takes two days gets two work orders, one per day, each with its own task list and sign-off. The price comes from the roofing estimate template, and the roofing invoice template bills the squares the work orders record.
Roofing work order fields: permit, roof data, fall protection, tasks and sign-off
The table lists the template's fields, offered as a free .xlsx download with no sign-up. Office fields are filled before the day; field entries are made on the roof.
| Field | Filled by | What goes in it |
|---|---|---|
| Work order number and day | Office | A number from one sequence, the estimate number, and "day 1 of 2" |
| Customer and access | Office | Name, phone, address, vehicles to move, dumpster location |
| Permit and inspections | Office | Permit number, the inspections required, and which may be done by photo |
| Roof data | Office | Squares by slope, pitch by slope, existing layers, deck type, eave height |
| Slope class | Office | Low-slope (4 in 12 or less) or steep (over 4 in 12), for each slope |
| Fall protection by slope | Office | The system for each slope, anchor points and rating, and who checks them |
| Tasks in order | Office | Numbered lines, from tear-off and deck repair through flashing, shingles and ridge |
| Materials staged | Office | Products and quantities delivered for this day, with any allowance such as replacement sheets |
| Hold points | Office | Steps that stop work until something happens, such as an inspection before shingles |
| Photos required | Office | Each slope at the deck, each replaced sheet, flashing before shingles, finished roof |
| Disposal | Office | Dumpster size and placement, protection under the wheels, haul ticket, magnet sweep |
| Task status | Field | Done, not done or changed, with the time, for each task |
| Change log | Field | The finding, the estimate's unit price, the added amount, and the customer's approval with time and method |
| Fall protection check | Field | Time the anchors, lifelines and harnesses were checked, and by whom |
| Daily sign-off | Field | Foreman's name, roof dried in, site clean, time out |
| Customer sign-off | Field | On the last day: walk-through, signature and date |
The slope class field ties the roof data to the fall protection field. One roof can carry two systems, as in the example: fall arrest on the steep main roof, a safety monitor on the low-slope porch.
Filled roofing work order: day 1 of a reroof in Centennial, Colorado
The house has a steep main roof, a low-slope rear porch roof and a brick chimney. Day 1 runs from tear-off to dry-in; day 2, on its own work order, from shingles to final sweep. The business, customer, quantities and prices are sample entries. The fall protection and permit fields follow the federal regulation and the city page cited after the tables.
| Field | Sample entry |
|---|---|
| Work order number and day | RW-2026-0617 · estimate RFE-2026-0598 · Monday, November 16, 2026 · day 1 of 2 (day 2 is RW-2026-0618) |
| Customer and access | Nadia Ferris · 720-555-0136 · 7400 Example Circle, Centennial, CO 80122 · cars out by 7:00 AM · dumpster on the driveway apron |
| Permit and inspections | City of Centennial reroof permit 0000-00000 (sample) · mid-roof inspection before shingles, by photo · final inspection after day 2 |
| Roof data | 26 squares: main roof 23.5, two slopes at 6 in 12 · porch 2.5 at 3 in 12 · one layer over 7/16-inch OSB · eaves 10 to 11 ft above grade |
| Slope class | Main roof: steep · porch: low-slope, 14 ft wide |
| Fall protection by slope | Main roof: personal fall arrest, two ridge anchors fastened into rafters, manufacturer-rated (sample), full-body harness, rope grab and lifeline rigged for under 6 ft of free fall · porch: safety monitoring system, monitor named |
| Materials staged | Ice barrier 6 rolls · synthetic underlayment 8 rolls · drip edge 290 lin ft · step flashing 1 bundle · pipe boots 3 · 3 sheets of 7/16-inch OSB as the estimate's allowance |
| Hold points | No shingles until the mid-roof photo inspection is passed · no one on the main roof before the 7:30 AM anchor check |
| Disposal | 30-yard dumpster on plywood under the wheels · haul ticket with weight · magnet sweep of lawn and driveway at day end |
| Seq | Task | Quantity | Protection | Photo or hold | Status |
|---|---|---|---|---|---|
| 1 | Install anchors, rig lifelines, name porch monitor, check harnesses | 2 anchors | Check at 7:30 AM by foreman | Photo of each anchor | Done 7:30 AM |
| 2 | Tear off shingles and felt to the deck, all slopes | 26 sq | Arrest on main · monitor on porch | Each slope at the deck | Done 11:15 AM |
| 3 | Replace delaminated OSB at the north eave | 3 sheets allowed | Arrest | Each sheet before cover | Changed: 5 sheets |
| 4 | Drip edge at eaves and rakes, all edges | 290 lin ft | Arrest · monitor | Done | |
| 5 | Ice barrier at eaves and in both valleys | 6 rolls | Arrest · monitor | Eaves before underlayment | Done |
| 6 | Synthetic underlayment on the remaining deck | 8 rolls | Arrest · monitor | Done | |
| 7 | Step flashing and counterflashing at the garage sidewall | 18 ft | Arrest | Before shingles | Done |
| 8 | Chimney: apron, step, counter and back pan flashing | 1 chimney | Arrest | Before shingles | Done |
| 9 | Pipe boots on three plumbing vents | 3 | Arrest | Done | |
| 10 | Submit mid-roof photo inspection; roof dried in | Hold for day 2 shingles | Submitted 4:20 PM | ||
| Change | 10:40 AM: 5 delaminated sheets against the 3-sheet allowance; 2 extra at $78.00 per sheet installed from the estimate, +$156.00; approved by Nadia Ferris by text at 10:55 AM with photos | Approved | |||
| Sign-off | Foreman T. Avila · dried in · dumpster 60 percent full · magnet sweep done · out 5:05 PM |
The change line is what the roofing invoice later bills: 5 sheets in total, 3 inside the price and 2 at the estimate's unit price, each photographed before it was covered.
OSHA fall protection fields: slope, system and anchorage
The fall protection fields come from 29 CFR 1926 Subpart M. A low-slope roof has a slope of 4 in 12 or less, and a steep roof more than 4 in 12. Roofing work covers hoisting, storing, applying and removing roofing materials, but not building the roof deck. Since January 1, 1998, a body belt may not be used for fall arrest (29 CFR 1926.500, via Cornell LII, checked November 2026).
Three paragraphs of section 1926.501 set the systems (29 CFR 1926.501, via Cornell LII, checked November 2026):
- Paragraph (b)(10), roofing work on low-slope roofs: each employee with unprotected sides and edges 6 feet or more above lower levels is protected by guardrail, safety net or personal fall arrest systems, or by a warning line combined with one of those or with a safety monitoring system. On roofs 50 feet or less in width, a safety monitoring system alone is permitted.
- Paragraph (b)(11), steep roofs: guardrail systems with toeboards, safety net systems or personal fall arrest systems, at the same 6-foot height.
- Paragraph (b)(13), residential construction: guardrail, safety net or personal fall arrest systems at 6 feet or more, unless another provision of paragraph (b) provides an alternative. Where the employer can demonstrate that these systems are infeasible or create a greater hazard, it develops and implements a fall protection plan meeting section 1926.502(k).
The example's choices map onto those paragraphs. The main roof is steep, with eaves above 6 feet, so it takes personal fall arrest. The porch is low-slope and 14 feet wide, under the 50-foot limit, so a safety monitor alone is permitted, and the work order names the monitor. A crew working under a written fall protection plan would attach the plan and its infeasibility finding.
The anchor and lifeline entries follow section 1926.502. An anchorage for fall arrest equipment supports at least 5,000 pounds per employee attached, or belongs to a complete system with a safety factor of at least two, supervised by a qualified person. The system is rigged so that an employee can neither free fall more than 6 feet nor contact any lower level (29 CFR 1926.502, via Cornell LII, checked November 2026). The anchor rating and the rigging length are therefore entries, not boxes to tick.
Centennial reroof permit and inspection fields
The City of Centennial's building division states its reroof rules on one page (City of Centennial, Residential Roof Repairs and Re-Roofing, checked November 2026). A repair under 100 square feet is a small repair and needs no permit; a repair over 100 square feet on any roof or combination of slopes is a major repair and needs one. Repairs that exceed 25% of the total roof area require a complete tear-off and reroof, and a roof replacement removes all existing layers of roof covering to the deck.
The page also sets the inspections and two code items. Every reroof permit requires a mid-roof inspection, and the mid-roof and final inspections may be done by photo; in person, the permit holder provides roof access and sets up the ladder. Ice barrier is required on all roofs, and drip edge on all edges. Reroofs meet the 2021 International Residential Code, with repairs under section R908.
Each rule has a row. The permit field records the photo option, and the photos field lists the deck and flashing shots the mid-roof inspection needs. The hold point keeps shingles off until it passes; tasks 4 and 5 put drip edge on every edge and ice barrier on the eaves.
Roofing work order instructions from anchor check to dry-in
- Before the day, fill the office fields from the estimate and permit, including slope class and the system for each slope.
- On arrival, install and check anchors and lifelines, name any monitor, and record the check time before anyone goes up.
- Work the tasks in sequence, marking each done, not done or changed with its time.
- Photograph each slope at the deck and every replaced sheet before it is covered.
- Log any finding beyond an allowance with its unit price and amount, and take approval before covering it.
- Photograph flashing and submit the mid-roof photo inspection.
- Before leaving, confirm the roof is dried in and the yard swept, then sign off with the time.
- Check that the change log, the sheet count and the photos agree before the work order goes to invoicing.
Roofing estimate, work order and invoice on one reroof
The estimate prices squares, layers, code items and allowances. The work orders direct each day and record what the deck needed. The invoice bills the squares installed and the allowances used, and because the day 1 change log carries the estimate's unit price, the 2 extra sheets need no new pricing.
Work order software for roofing jobs
A paper work order leaves its photos on a phone and its approvals in a text thread, for the office to reassemble.
In FieldRanger, job details, customer information and instructions reach the technician's phone on a digital work order, and job-specific checklists can hold the anchor and harness check. Before and after photos attach to the work order and sync to the customer's HubSpot record, so the five deck sheets sit with the customer's history. Job status is updated with one tap and is visible to dispatchers in real time; the customer signs on site as proof of completion, and the invoice is generated from the completed work order. The work order software page describes the work order.
The day-per-work-order layout matches how FieldRanger counts work. Each FieldRanger job is assigned to a technician, here the foreman, and each day is its own job, so the reroof is two jobs. There is no weather feed: a day lost to wind or snow is moved on the drag-and-drop calendar.
Fill it in here, or download the spreadsheet
The form below is the same template: totals calculate as you type, with the spreadsheet's own formulas, and your entries stay in this browser. Download it filled in, print it or save it as a PDF, or take the blank file.
Frequently asked questions
What goes on a roofing work order?
The work order and estimate numbers and the day, customer and access, permit and inspections, roof data and slope class, the fall protection system for each slope, tasks in order, materials, hold points, required photos, disposal, task status, a change log, the fall protection check and the sign-offs.
What fall protection does OSHA require for residential roofing?
Under 29 CFR 1926.501, employees 6 feet or more above lower levels are protected by guardrail, safety net or personal fall arrest systems. On low-slope roofs, warning lines and safety monitoring are allowed in combinations, and a safety monitor alone on roofs 50 feet wide or less. A fall protection plan is allowed only where the employer shows the systems are infeasible or more hazardous.
Does Centennial, Colorado require a permit to replace a roof?
Yes. The City of Centennial requires a permit for any roof repair over 100 square feet and for reroofs, requires a mid-roof inspection on every reroof permit, and allows the mid-roof and final inspections by photo.
Is there a free roofing work order template in PDF?
The download is a free .xlsx with no sign-up, not a PDF: a Template sheet with every field and the task lines, and a Sample sheet with the filled day 1 work order. Excel or Google Sheets saves it as a PDF, and the job takes one work order per day.
What is the difference between a roofing work order and a roofing estimate?
The estimate prices the reroof for the customer to accept. The work order directs one day of the job: tasks in order, fall protection, holds and photos, and it records what was found and approved, which the invoice then bills.
RW-2026-0617 at dry-in
Day 1 closed at 5:05 PM with 26 squares torn off, 5 sheets of OSB replaced and photographed, every edge under drip edge and the mid-roof photos submitted at 4:20 PM. RW-2026-0618 starts with the inspection result, and its first task stays on hold until the result is a pass. The day 2 work order and the invoice after it use forms from the free field service templates hub. Per-technician plans are on pricing, and Start free trial gives 14 days with no card, enough for several two-day reroofs scheduled as one job per day.