Guide
Contractor Pricing:Cost-Plus, Flat-Rate and Value Methods, Cost per Billable Hour, Markup and Margin, Price Books and Supplier Pro Pricing
Contractor pricing explained: cost-plus, flat-rate and value methods, a sourced cost per billable hour, markup and margin, price books and supplier pro pricing.
Contractor pricing is the method a trade contractor uses to turn costs into the prices customers pay. Cost-plus pricing adds a markup to each job's actual costs; flat-rate pricing charges a fixed price per task from a price book; value pricing sets the price from what the result is worth to the customer. Each must recover labor and overhead.
Prices go wrong in a contractor business in three recognizable ways. A rate copied from a competitor or a published guide recovers someone else's costs; a margin target applied as a markup earns less than the target on every job; a flat-rate book written before a wage, mileage or insurance change keeps charging last year's cost. FieldRanger makes field service software that runs inside HubSpot, and this guide is one of its pricing and quoting guides. It covers the three pricing methods, a sourced cost per billable hour for an electrical contractor, the markup and margin conversion, price books, published pricing guides, supplier pro pricing, price review triggers, a checklist and the estimating record. The single quote, from site visit to signature, is covered in how to quote a job.
Four terms recur. A billable hour is an hour a technician spends on work a customer pays for. Overhead is cost that belongs to no single job: the office, insurance, software, rent and the owner's unbilled time. Markup is profit stated as a percentage of cost; margin is the same profit stated as a percentage of price. A price book is the contractor's list of repeatable tasks with a fixed price for each.
Contractor pricing strategies: cost-plus, flat-rate and value pricing
The three methods differ in who carries the risk of a job running long and in what the customer knows before work starts.
| Method | How the price is set | Who carries an overrun |
|---|---|---|
| Cost-plus (time and materials) | Actual hours and materials, plus a markup | The customer |
| Flat-rate | A fixed price per task from the price book | The contractor |
| Value pricing | The worth of the result to the customer, with cost as the floor | The contractor |
Cost-plus fits work whose scope cannot be seen before it starts: tracing a fault, opening a wall, repairing storm damage. The customer pays for what the work turns out to be and the contractor's margin holds, but the customer cannot know the total in advance. Flat-rate fits repeatable tasks, such as replacing a receptacle or a water heater, whose duration the contractor has measured on its own jobs. The customer sees the price before agreeing; the contractor keeps the gain when a task runs short and absorbs the loss when it runs long. Value pricing fits work whose worth to the customer far exceeds its cost, such as restoring power to a restaurant's walk-in cooler on a Friday evening, where the price follows the loss the customer avoids and cost sets only the floor.
A contractor can run more than one method: a flat-rate book for service calls and cost-plus terms for change orders on remodels sit comfortably in the same company, because the method follows the work, not the business.
Cost per billable hour for an electrical contractor
Every method rests on one number, what an hour of billable work costs the company, and the build below computes it from published figures for a sample three-electrician company.
The Bureau of Labor Statistics reports a median wage of $30.38 an hour for electricians in May 2025 (BLS Occupational Outlook Handbook, Electricians, modified August 27, 2026). Wages and salaries were 70.0 percent of private-industry compensation in June 2026, with benefits the remaining 30.0 percent (BLS Employer Costs for Employee Compensation, released September 9, 2026), so the loaded cost of the median electrician is $30.38 ÷ 0.700, or $43.40 an hour. An electrician paid for 2,080 hours who bills a sample 65 percent of them bills 1,352 hours, and each billable hour then carries $66.77 of loaded labor.
Vehicle cost uses the IRS business rate of 76 cents a mile from July 1, 2026 (IRS standard mileage rates, updated July 28, 2026). Insurance uses the figures Insureon publishes for electricians: $732 a year for general liability, $1,679 for workers' compensation and $1,198 for a business owner's policy (Insureon, electrician insurance cost, updated July 28, 2026). The office manager is costed at the BLS median for secretaries and administrative assistants, $48,310 a year in May 2025 (BLS), loaded the same way.
| Line | Calculation | Per billable hour |
|---|---|---|
| Loaded labor | $43.40 × 2,080 paid hours ÷ 1,352 billable hours | $66.77 |
| Vehicle | 18,000 sample miles × $0.76 = $13,680, ÷ 1,352 | $10.12 |
| Overhead | ($69,014.29 office manager loaded + $3,609.00 insurance + $30,000.00 sample rent, software and phones) ÷ 4,056 billable hours | $25.30 |
| Cost per billable hour | Sum | $102.19 |
| Hourly price at a 20% margin | $102.19 ÷ 0.80 | $127.74 |
| Hourly price at a 25% margin | $102.19 ÷ 0.75 | $136.25 |
The published wage range shows how far one company's number can sit from the median. BLS puts the lowest 10 percent of electricians below $42,640 a year and the highest 10 percent above $108,510. At 2,080 paid hours, a 0.700 wage share and a 65 percent billable share, loaded labor alone runs from $45.06 to $114.66 per billable hour across that range, before a mile is driven or an office is rented. A price taken from someone else's book describes someone else's payroll.
Markup and margin: a conversion table
A margin target is converted to the markup that produces it before it enters a price book: markup equals margin divided by one minus margin. The conversion holds at every price, so it can be printed once and kept beside the book.
| Target margin | Markup on cost | Price of $100.00 of cost |
|---|---|---|
| 10% | 11.1% | $111.11 |
| 15% | 17.6% | $117.65 |
| 20% | 25.0% | $125.00 |
| 25% | 33.3% | $133.33 |
| 30% | 42.9% | $142.86 |
| 35% | 53.8% | $153.85 |
| 40% | 66.7% | $166.67 |
| 50% | 100.0% | $200.00 |
A book that adds 20 percent to cost earns a 16.7 percent margin, not 20. The gap repeats on every line of the book and every job priced from it, so the conversion belongs in the book itself.
Contractor pricing book: flat-rate entries from task hours
A contractor pricing book lists each repeatable task with three inputs behind its price: the task hours from the company's own completed jobs, the parts at current cost, and the margin. The flat price is (task hours × cost per billable hour + parts) ÷ (1 − margin). Drive time and overhead already sit inside the cost per billable hour, so the book adds no separate trip charge unless the company chooses to show one.
| Task | Cost | Flat price |
|---|---|---|
| Replace a GFCI receptacle: 0.75 hours, $22.00 parts | $76.64 + $22.00 = $98.64 | $123.30 |
| Install a ceiling fan on an existing fan-rated box: 1.5 hours, $8.00 parts | $153.29 + $8.00 = $161.29 | $201.61 |
| Add a 20-amp circuit, run of 25 feet or less: 3.0 hours, $95.00 parts | $306.57 + $95.00 = $401.57 | $501.96 |
The flat-rate risk sits in the task hours. If the GFCI replacement takes 1.25 hours instead of 0.75, its cost becomes $149.74 against the book price of $123.30, a loss of $26.44 on the call; the same job priced at cost-plus would have billed $187.18. The book is only as good as the task hours behind it, and those come from time logged against each completed job and reviewed at least once a year.
Contractor pricing guides: published cost data and its limits
A contractor pricing guide is a published set of costs or prices for construction tasks. Free and paid guides both exist, and both describe a market rather than a company.
Free inputs come from federal sources: BLS publishes wages by occupation, including the percentile range above, and the IRS publishes the mileage rate. For federally funded construction, the Davis-Bacon Act requires contractors and subcontractors on contracts over $2,000 for the construction, alteration or repair, including painting and decorating, of public buildings or public works to pay laborers and mechanics no less than the locally prevailing wages and fringe benefits that the Department of Labor determines; the wage determinations are published on SAM.gov, which is open to the public (U.S. Department of Labor, Davis-Bacon and Related Acts, checked November 12, 2026). A free contractor pricing guide for labor on public work therefore already exists, county by county, in those determinations.
Paid guides sell unit costs. RSMeans describes its data as more than 92,000 unit line items of material, labor and equipment prices across more than 970 locations, with quarterly updates to its online product (RSMeans, checked November 12, 2026). A guide of that kind earns its cost on work the company has not priced before and as a check on a book against the market. It cannot stand in for the company's cost per billable hour, since the guide's labor rate is not the company's payroll and its productivity figures are not the company's crew. Guides for whole-project estimating are compared in general contractor pricing guides.
Supplier contractor pricing: pro accounts at paint and flooring suppliers
Supplier contractor pricing is a discount or program a supplier offers to trade accounts. It lowers the contractor's material cost; whether it lowers the customer's price depends on the pricing method.
Sherwin-Williams' PRO+ pricing page lists 15 percent off paint supplies and 20 percent off paint supplies in case quantities, with free scheduled delivery (Sherwin-Williams, PRO+ Pricing, checked November 12, 2026). Floor & Decor's Pro page describes PRO Premier Rewards points on eligible purchases, Pro-specific pricing through its Bid Room for projects of $10,000 or more, and tax-exempt purchasing for qualified Pros; it does not describe a separate everyday Pro discount (Floor & Decor, Pro, checked November 12, 2026). Program terms change on the supplier's schedule, so the account terms behind each material price are recorded with the price.
The method decides who keeps the discount: on $400 of supplies at list, a 15 percent discount brings the cost to $340. Under cost-plus with a 25 percent markup on the price paid, the customer's price falls from $500 to $425 and the contractor's profit from $100 to $85. Under a flat-rate book priced from list cost, the customer pays the same and the contractor keeps the $60. A cost-plus contract therefore states whether cost means list price or price paid.
Price review triggers: wage, mileage, insurance and supplier changes
A price book is reviewed when an input changes, not on the anniversary of its writing. Four inputs move on their own schedules, and the first is set by the government: the IRS business mileage rate went from 70 cents in 2025 to 72.5 cents for January to June 2026 and 76 cents from July 1, 2026 (IRS). Wages move with each hire and each raise, insurance changes at renewal, and supplier programs change on the supplier's own page.
The mileage change alone shows the size of the effect: in the sample, 18,000 miles a year cost $12,600 at the 2025 rate and $13,680 at the July 2026 rate, an increase of $1,080 per electrician, or $0.80 per billable hour across 1,352 hours. A book reviewed every second year carries that gap on every hour it prices until the next review.
Contractor pricing checklist
- Compute the cost per billable hour from payroll, vehicle miles, insurance and overhead for the last twelve months.
- Measure each technician's billable share from time logged against jobs.
- Assign a method to each kind of work: flat-rate for measured repeatable tasks, cost-plus for hidden scope, value pricing where the result is worth far more than its cost.
- Convert the margin target to a markup with the table above before entering any price.
- Set flat-rate task hours from completed jobs, not from a published guide.
- State in each cost-plus contract whether cost means list price or price paid.
- Record the supplier program behind each material price.
- Reprice when the mileage rate, a wage, an insurance premium or a supplier program changes.
- Verify each quarter: margin by task from completed jobs against the margin the book assumed.
Contractor pricing guide software and estimates in FieldRanger
Software applies the book; the numbers in it still come from the company's own records. In FieldRanger, an estimate is built from the HubSpot deal or contact record without leaving HubSpot, or in FieldRanger and kept tied to the HubSpot deal it belongs to, and PandaDoc sends estimates and agreements for signature. A won deal becomes a job with its context carried over.
Technicians clock in and out with time logged against each job, which is the source of task hours for a flat-rate book. The invoice is generated from the completed work order, QuickBooks syncs invoices and payments, and Stripe takes payment in the field. Revenue reports show job revenue and margin by customer or service type, which is the quarterly check in the checklist above. The estimating software page shows the estimate. Pricing lists the plans; Start free trial runs 14 days without a card.
Frequently asked questions
What is contractor pricing?
The method a contractor uses to turn its costs into customer prices: cost-plus, flat-rate from a price book, or value pricing. Each method has to recover loaded labor, vehicle cost and overhead per billable hour before any margin.
Does Floor & Decor have contractor pricing?
Floor & Decor's Pro page, checked in November 2026, describes Pro-specific pricing through its Bid Room for projects of $10,000 or more, PRO Premier Rewards points and tax-exempt purchasing for qualified Pros. It does not describe a separate everyday Pro discount.
Does Sherwin-Williams have contractor pricing?
Its PRO+ pricing page, checked in November 2026, lists 15% off paint supplies and 20% off paint supplies in case quantities for PRO+ accounts.
Is a free contractor pricing guide accurate for a local job?
A published guide describes market costs, not one company's payroll or crew productivity. Across the BLS wage range for electricians, loaded labor alone runs from $45.06 to $114.66 per billable hour, so a guide price checks a book and cannot replace it.
What markup gives a 20% margin?
A 25% markup. Markup equals margin divided by one minus margin, so a 30% margin needs a 42.9% markup and a 50% margin needs 100%.
Cost-plus or flat-rate pricing for service work?
Flat-rate fits repeatable tasks whose hours the company has measured; cost-plus fits work whose scope cannot be seen before it starts. The contractor carries an overrun under flat-rate, and the customer carries it under cost-plus.
A GFCI receptacle that takes half an hour longer than its book entry turns a $24.66 profit into a $26.44 loss, and no margin setting fixes that; current task hours do.