Guide

General Contractor Pricing Guides:RSMeans, Craftsman and Xactimate Methods, Overhead and Profit Layers, Localization and a Denver Bid Built From a Cost Book

General contractor pricing guides compared by stated method: RSMeans, Craftsman and Xactimate, the overhead and profit each omits, and a sample Denver bid.

By Published Updated

12 min read

General contractor pricing guides are published cost databases: Gordian's RSMeans data, Craftsman's National Construction Estimator and Verisk's Xactimate price lists are three whose publishers state their methods. None includes the general contractor's own overhead and profit. A GC price is the guide's cost, adjusted to the company's labor and location, plus general conditions, contingency and markup.

A guide price goes wrong in a GC's hands in three ways. A line that already carries an installing contractor's markup gets the GC's markup again. A city factor is applied to labor the company already pays at its own rate. A national-average figure is bid with no contingency because the guide never included one. FieldRanger makes general contractor software that runs inside HubSpot, and this page is one of its pricing and quoting guides. It compares the three guides' stated methods, separates the overhead and profit layers, sets out the GC pricing methods, and localizes a cost book against a company's own payroll. A sample Denver bid built from the book follows, then the antipatterns and a checklist.

Four terms recur. A bare cost is the material, labor and equipment an installing contractor pays, with no markup. General conditions are the job's own overhead: supervision, permits, dumpsters, temporary facilities and cleanup. Overhead is company cost that belongs to no single job. Markup is profit and overhead stated as a percentage of cost; margin is the same amount as a percentage of price.

Three general contractor pricing guides and their stated methods

Each publisher states how its numbers are made. The statements below come from the publishers' own pages, read November 12, 2026.

Three general contractor pricing guides compared by the method each publisher states
GuideStated methodLocalizationOverhead and profit in the price
RSMeans data, GordianNational average costs, localized by a City Cost IndexIndex against a 30-city national average of 100Installing contractor's O&P in "Total Incl O&P"; GC's O&P excluded
National Construction Estimator 2026, CraftsmanCosts to a GC working with its own crews, compiled fall 2025Area modification factors by three-digit ZIP CodeNone on own-crew lines; subcontract lines include sub markup
Xactimate price lists, Verisk"Market price": the most common price recently submittedSeparate price lists for more than 460 areasNot stated in the methodology paper

RSMeans prices a national average and moves it with an index. Gordian describes the City Cost Index as comparing a standardized project's cost in one location with a national average of 30 major U.S. cities set at 100. Its model holds 66 materials, 21 trades and six pieces of equipment, with a base of July of the previous year (Gordian, City Cost Index, May 25, 2022). RSMeans defines bare costs as what "the installing contractor pays," and states that Total Cost including O&P "does not include the general contractor's overhead and profit" (RSMeans, what is construction estimating, May 23, 2025).

Craftsman prices the GC's own crews. Its 2026 edition "lists estimated construction costs to general contractors performing work with their own crews. Overhead and profit are not included." Costs were "compiled in the fall of 2025 and projected to early 2026." Its sources are contractors and subcontractors, architectural and engineering firms, suppliers, price services, completed project costs, and mail and phone surveys (Craftsman Book Company, 2026 National Construction Estimator preview, edited by Richard Pray, first printed September 2025). Sections marked "subcontract" are based on subcontractor quotes and include "typical subcontractor markup (about 30% on labor and 15% on material)."

Verisk reports what contractors charge in insurance repair. Its methodology paper describes a cluster analysis that selects "the most common price recently submitted," by definition a "market price." It reviews nearly 20,000 market surveys a month and publishes price lists for more than 460 areas, monthly, or every two weeks when demand surges (Verisk, Pricing Research Methodology, ©2023). Verisk states that it does not set prices from demographic data such as median income, and that "there is no way to be certain that any published price will be appropriate for a specific contractor."

The three answer different questions. RSMeans answers what a task costs in an average market, adjusted to a city. Craftsman answers what a GC's own crew costs to do it. Xactimate answers what contractors in an area recently charged on repair estimates.

Overhead and profit layers in a guide price

A GC price stacks five layers, and a guide supplies only the first one or two. Reading which layers a line already holds is the core skill in using a pricing guide.

Layers of a general contractor price and which guide supplies them
LayerRSMeansCraftsmanAdded by the GC
Bare cost of material, labor and equipmentBare Costs columnsOwn-crew linesNo
Installing contractor's overhead and profitTotal Incl O&P columnSubcontract lines: about 30% labor, 15% materialNo: on self-performed work the GC's own markup covers it
General conditionsNot in unit lines; 5% to 15% for the GCNot includedYes
ContingencyNot included in national average costsNot includedYes
GC overhead and profitNot includedNot included; 20% of contract price suggested for residential GCsYes

RSMeans gives general conditions a range: 0% to 10% of Total Cost including O&P for the installing contractor, and 5% to 15% for the general or prime contractor (RSMeans). On contingency, RSMeans states that national average costs "do not include any allowances" for it, and recommends 15% to 20% on historic preservation projects regardless of drawing stage (RSMeans, estimating best practices, July 24, 2025).

The second row is where guide prices get marked up twice. A subcontract line in Craftsman, or a Total Incl O&P line in RSMeans, already pays an installing contractor's overhead and profit. For work a sub performs, that is correct, and the GC's markup goes on top. For work the GC's own crew performs, the GC is the installing contractor, and the bare line is the starting point.

General contractor pricing methods: markup, overhead rate and fee

General contractor pricing sets the last layer by one of four methods. Craftsman's own suggestion shows the first: a 20% gross profit on the contract price requires a 25% markup on costs. The full markup-to-margin conversion table is in contractor pricing.

Four methods for the GC's overhead and profit
MethodHow it is setWhere it fits
Percentage markup on costOne percentage on all costs, own and subcontractStipulated-sum bids from a guide
Overhead rate plus profitAnnual overhead ÷ annual direct cost, plus a profit percentageA company that knows its overhead to the dollar
Cost of the work plus a fee, with a guaranteed maximum priceFixed or percentage fee; contractor guarantees the maximumNegotiated work under AIA A102
Cost plus a fixed fee on federal workFee capped by regulationFederal cost-plus-fixed-fee contracts

An overhead rate recovers the company's real overhead rather than an assumed one. A sample firm with $210,000 of annual overhead on $1.5 million of annual direct cost carries a 14% overhead rate; a 10% profit on top gives a 25.4% markup ((1.14 × 1.10) − 1). The figures are sample inputs, and the method replaces a rounded guess with the company's own books.

A fee contract moves the risk. AIA describes A102–2017 as the agreement used when "the basis of payment to the contractor is the cost of the work plus a fee." Under it, "the only value guaranteed by the Contractor is the Guaranteed Maximum Price," and individual schedule-of-values lines may run over provided the GMP holds (AIA Contract Documents, A102–2017 summary).

Federal cost-plus-fixed-fee work has a ceiling. Under FAR 15.404-4(b)(4)(i), the fee on other cost-plus-fixed-fee contracts "shall not exceed 10 percent" of estimated cost excluding fee; experimental and research work allows 15%, and architect-engineer services 6% of construction cost (FAR 15.404-4, read November 12, 2026).

Localizing a guide: area factors and the company's own labor rate

A guide can be localized two ways, and Craftsman states which to use when. The area modification table applies when the company's labor rate is unknown. When it is known, Craftsman's procedure divides the company's loaded hourly cost by the book's to get a labor modification factor.

The book's numbers for a carpenter are explicit. Craftsman's 2026 hourly labor table lists a $32.08 base wage, $2.04 of taxable fringe benefits, a 29.17% tax and insurance rate worth $9.95, and $1.81 of non-taxable benefits, for $45.88 an hour; a building laborer totals $37.40. Denver's three-digit ZIP 802 carries area factors of +3% on material, +17% on labor and +1% on equipment, +9% in total.

A Denver company's own payroll gives a different number. Denver-metro carpenters earn a median $31.21 an hour and construction laborers $23.44 (O*NET OnLine, BLS 2025 wage data; laborers). Wages were 69.5% of construction-industry compensation in June 2026 (BLS Employer Costs for Employee Compensation, Table 4, modified September 9, 2026). The loaded median carpenter therefore costs $31.21 ÷ 0.695 = $44.91 an hour.

One Denver carpenter-hour, localized two ways (published rates, read November 12, 2026)
MethodCalculationCost per hour
Book rate, unadjustedCraftsman hourly cost$45.88
Book rate with Denver area factor$45.88 × 1.17$53.68
Company payroll at the Denver median$31.21 ÷ 0.695$44.91
Labor modification factor$44.91 ÷ $45.880.979

The area factor prices the hour 19.5% above a company paying the Denver median. The factor describes a market, and the company's payroll describes the company; applying the factor to a crew whose wages are already known prices labor the company does not pay.

Sample bid: Denver basement finish built from a cost book

The bid below is a sample for a hypothetical 800-square-foot basement finish in Denver. Labor rates and the methods are published figures. Manhours, the material quote, subcontract quotes, general conditions items other than supervision, contingency and markup are sample inputs.

Self-performed carpentry, framing, doors and trim, is priced from the company's own loaded rates at the book's sample manhours. Subcontracted trades are priced from their quotes, which already carry each sub's overhead and profit. Supervision uses the Denver-metro median for first-line supervisors of construction trades, $40.10 an hour (O*NET OnLine), loaded to $57.70.

Sample bid for an 800-square-foot basement finish in Denver (published rates; quantities, quotes and percentages are sample inputs)
LineCalculationAmount
Carpentry labor, own crew120 hours × $44.91$5,389.20
Laborer, own crew40 hours × $33.73$1,349.20
Materials for self-performed workSample supplier quote$7,400.00
Electrical subcontractSample quote$6,800.00
Plumbing subcontractSample quote$5,900.00
HVAC subcontractSample quote$2,600.00
Drywall hang and finish subcontractSample quote$8,400.00
Painting subcontractSample quote$3,900.00
Flooring subcontractSample quote$5,200.00
Cost of the workSum$46,938.40
Supervision30 hours × $57.70$1,731.00
Dumpster, permit and plan review, final cleaningSample $650 + $1,100 + $400$2,150.00
General conditionsSupervision plus items; 8.3% of the work$3,881.00
ContingencySample 5% of work and general conditions$2,540.97
Total costSum$53,360.37
GC markup25% of cost, Craftsman's 20% of price$13,340.09
Bid priceCost plus markup$66,700.46, or $83.38 per square foot

General conditions land at 8.3% of the work, inside the 5% to 15% RSMeans gives for a general contractor. The markup produces a 20.0% share of price, which is Craftsman's suggested figure for residential GCs. Had the same 160 hours been priced at the area-adjusted book rates, $53.68 and $43.76, labor would cost $8,192.00 instead of $6,738.40. After markup, the bid would rise by $1,817.00 for wages the company does not pay.

The same cost under a federal cost-plus-fixed-fee ceiling of 10% would carry a fee of $5,336.04, against $13,340.09 of markup here. The comparison shows the price of risk: a stipulated sum carries the overrun, and a capped fee does not.

Pricing guide antipatterns: double markup, double localization and missing contingency

Three errors recur when a GC prices from a guide, and each has a mechanism.

Double markup happens when a line with an installing contractor's O&P is used for self-performed work. Pricing the sample's own-crew labor from a subcontract-style line would add the book's 30% sub markup on labor, $2,021.52, and the GC's 25% would then raise the bid by $2,526.90 above the bare-cost version. The fix is to start own-crew work from bare costs, or from Craftsman's own-crew lines, and to keep sub-inclusive lines for subcontracted scope.

Double localization happens when a known payroll rate is entered and the area factor is then applied to the total. The labor is localized twice. Craftsman's procedure is one or the other: a labor modification factor when the rate is known, an area factor when it is not.

Missing contingency happens because national averages carry none. RSMeans states that its national average costs include no contingency allowance. A bid built from a guide with no contingency line is priced for a job with no surprises.

General contractor pricing checklist

  1. Name the guide, edition and date behind every unit price in the estimate.
  2. Mark each line as bare cost, installing contractor O&P included, or subcontract quote.
  3. Price self-performed work from bare costs at the company's loaded labor rate.
  4. Apply an area factor only to lines whose labor rate is not already the company's own.
  5. Add general conditions as their own lines, and compare the total with the 5% to 15% range.
  6. Add a contingency line, sized to the drawings' completeness and the building's age.
  7. Choose the markup method: percentage, overhead rate plus profit, or fee.
  8. Convert the target margin to a markup before applying it.
  9. Verify at closeout: actual hours and costs by line against the estimate, and update the labor factor.

Estimates, job hours and margin by job in FieldRanger

FieldRanger holds the estimate on the same HubSpot records as the sales pipeline. An estimate is built from the HubSpot deal or contact record without leaving HubSpot, or in FieldRanger and kept tied to the HubSpot deal it belongs to. PandaDoc sends estimates and agreements for signature, and a won deal becomes a job with its context carried over. The estimating software page shows the estimate, and the construction estimate template lays out the lines this guide separates.

Technicians clock in and out with time logged against each job, which gives the actual hours the closeout step compares with the estimate. The invoice is generated from the completed work order, QuickBooks syncs invoices and payments, and revenue reports show job revenue and margin by customer or service type. Two things a GC expects are not built. FieldRanger has no progress billing or retainage, so pay applications are prepared outside it. It has no multi-day jobs: each day of a project is its own job. Bid notices, prequalification and owner relationships are covered in general contractor marketing, and channel budgets in the general contractor marketing plan. Plans are on pricing, and Start free trial runs 14 days with no card.

Frequently asked questions

What are general contractor pricing guides?

Published construction cost databases, such as Gordian's RSMeans data, Craftsman's National Construction Estimator and Verisk's Xactimate price lists. Each states its own method, and none includes the general contractor's overhead and profit.

Does RSMeans include overhead and profit?

RSMeans' Total Incl O&P column includes the installing contractor's overhead and profit, and its bare cost columns include none. RSMeans states that neither includes the general contractor's overhead and profit.

What markup does the National Construction Estimator suggest for a general contractor?

Craftsman's 2026 edition suggests 20% of the contract price for general contractors on residential construction, which requires a 25% markup on cost. Its own-crew lines include no overhead or profit.

Is a general contractor pricing guide accurate for a local bid?

A guide describes a market. In the Denver sample, the book's carpenter rate with the area factor came to $53.68 an hour against $44.91 for a company paying the Denver median, so a guide checks a bid and the company's own costs set it.

What is general contractor pricing on a cost-plus contract?

The owner pays the cost of the work plus a fee. Under AIA A102 the contractor also commits to a guaranteed maximum price, and on federal cost-plus-fixed-fee contracts the fee may not exceed 10% of estimated cost.

How much contingency belongs in a bid priced from a guide?

RSMeans states its national average costs include no contingency, and recommends 15% to 20% on historic preservation work. The sample bid carried 5% on a new basement finish, a sample figure.

One carpenter-hour cost $44.91 on the sample company's payroll and $53.68 in the area-adjusted book, and across 160 hours of carpentry and labor that gap moved the Denver bid by $1,817.00, more than the job's entire supervision line.