Guide

How to Bid a Construction Job:Invitations to Bid, Takeoffs, Subcontractor Quotes, Bonds and Bid Day

How to bid a construction job: the invitation to bid, quantity takeoff, subcontractor quotes and leveling, bid bonds and Miller Act thresholds, and bid day.

By Published Updated

14 min read

Knowing how to bid a construction job means turning an invitation to bid into a sealed number on the owner's form: read the documents and addenda, take off quantities, price self-performed labor and materials, level subcontractor quotes, add general conditions, overhead, fee and bond, then submit before the deadline with every addendum acknowledged.

A construction bid can be right in its arithmetic and still lose, or win at a loss, on its paperwork. A missed addendum can leave a bid nonresponsive; a subcontractor quote that excludes work another quote includes makes the low number look low; a bid that leaves out the bond premium wins a job at a price that cannot pay for the bond the contract requires. FieldRanger, which makes general contractor software that runs inside HubSpot, publishes this walkthrough as part of its pricing and quoting guides. It follows a bid in the order the work is done: the invitation and its documents, the bid or no-bid decision, the quantity takeoff, self-performed labor, subcontractor quotes and leveling, general conditions, overhead and fee, then bonds and the federal Miller Act thresholds. An office suite renovation in Philadelphia is then bid line by line, followed by bid day, estimates and quotes outside competitive bidding, a checklist and the software record.

Bid documents use five terms precisely. An invitation to bid, called an invitation for bids in federal contracting, is the owner's request for sealed prices against its drawings and specifications. A takeoff is the count and measurement of every quantity in those documents. General conditions are the job's own costs that belong to no single trade, such as supervision, dumpsters and the permit. Bid leveling adjusts subcontractor quotes for their exclusions so they can be compared on the same scope. A bid bond secures the bidder's promise to sign the contract and furnish the required bonds if awarded; a performance bond protects the owner if the contractor fails to finish, and a payment bond protects the subcontractors and suppliers who are owed money.

Invitation to bid: documents, addenda and the bid form

The bid package defines the job, and the bid prices only what the package describes. Federal sealed bidding states the principle directly: invitations "must describe the requirements of the Government clearly, accurately, and completely". Bids are submitted sealed and opened at the time and place stated, "Bids shall be evaluated without discussions", and the award goes to the responsible bidder whose conforming bid is most advantageous on price and price-related factors (FAR 14.101, FAC 2026-01, effective March 13, 2026). Private owners follow their own instructions to bidders, and the same elements appear in them.

A complete package holds the drawings, the specifications, the instructions to bidders, the bid form, the contract form, the bond requirements, any wage determination, and every addendum issued since. Addenda change the job after the documents were drawn, and acknowledging them is part of the bid. Under FAR 14.405(d), a failure to acknowledge an amendment is a minor informality only where the bid clearly indicates the amendment was received, such as by pricing an item the amendment added, or where the amendment has no effect or merely a negligible effect on price, quantity, quality or delivery (FAR 14.405). Outside those two cases, the omission is not a defect the contracting officer can waive.

Bid or no-bid decision

Each bid costs the estimator's time before it earns anything, so the decision to bid is made against the package rather than the job's appeal. The table sets out the questions and where each answer comes from.

Bid or no-bid questions and their sources
QuestionWhere the answer comes from
Does the scope fit the trades the company performs itself?The specification sections and the drawings
Can the crews start and finish in the contract time?The schedule in the bid documents against the company's own crew calendar, as in [construction crew scheduling](/blog/construction-crew-scheduling)
Will the surety bond a job of this size?The surety's limit for the company, or the SBA program limit of $9 million for non-federal contracts
Which wage rules apply?The wage determination in the package, for federal work covered by Davis-Bacon
Is there time to collect subcontractor quotes?The bid date against the subcontractors' own quoting time
Who else is bidding?The plan holders list, where the owner publishes one

Quantity takeoff from the drawings

A takeoff counts and measures every quantity the drawings and specifications call for, trade by trade, in the units the trade prices in: linear feet of partition, square feet of floor, each door and frame. Interior partitions in the sample below run 260 linear feet at 9 feet high, or 2,340 square feet of wall; drywall on both sides is 4,680 square feet, or 97.5 sheets of 4 by 12 feet before a waste allowance.

The takeoff has two uses. For self-performed work it becomes the materials order and the labor hours. For subcontracted work it becomes the scope sheet sent with each request for a quote, so every subcontractor prices the same quantities and the leveling step has something to check against. A quantity left out of the takeoff is left out of every quote that relied on it.

Self-performed labor at a loaded rate

Self-performed work is priced as crew-hours at a loaded rate. The median wage was $29.12 an hour for carpenters (BLS Occupational Outlook Handbook, carpenters) and $22.44 for construction laborers and helpers (BLS, construction laborers and helpers) in May 2025, both pages modified August 27, 2026. Wages and salaries were 69.0% of total compensation for private industry construction, extraction, farming, fishing and forestry occupations in June 2026 (BLS Employer Costs for Employee Compensation, Table 4), so the loaded rates are $29.12 ÷ 0.690 = $42.20 for a carpenter and $22.44 ÷ 0.690 = $32.52 for a laborer.

The hours come from the company's own completed jobs, broken into the same units as the takeoff, so crew hours recorded against cost codes through a construction time tracking app feed the next bid directly. Federal work changes the wage. The Davis-Bacon and Related Acts cover contracts over $2,000 for construction, alteration or repair of public buildings or public works. Contractors and subcontractors on them pay laborers and mechanics at least the "locally prevailing wages and fringe benefits", from wage determinations published on SAM.gov, and prime contracts over $100,000 also require time and a half for hours over 40 in a workweek (U.S. Department of Labor, Wage and Hour Division, construction contracts, checked November 12, 2026). On a covered job, the wage determination replaces the BLS median in the loaded rate.

Subcontractor quotes and bid leveling

Subcontractor quotes are compared on scope before price. Each quote is read against the scope sheet, its exclusions are listed, and each missing item is given a plug: the estimator's own price for the work the quote leaves out. The leveled figure is the quote plus its plugs, and the lowest leveled figure, not the lowest quote, goes into the bid.

Sample leveling of two electrical quotes for the same scope sheet
ItemSubcontractor ASubcontractor B
Quoted price$31,900$34,600
Fire alarm device relocationExcluded; plug $3,100 (sample)Included
Addenda acknowledged1 and 21 and 2
Leveled price$35,000$34,600

Subcontractor B carries the electrical scope at $400 less once the exclusion is priced, although its quote was $2,700 higher. The leveling sheet also records each subcontractor's acknowledgment of addenda, its bonding where the owner requires subcontractor bonds, and its insurance, because a low quote from a subcontractor who cannot meet the contract's terms cannot be used.

General conditions, overhead and fee

General conditions are priced from the schedule: supervision for the number of weeks on site, dumpsters by the number of hauls, temporary protection, final cleaning and the building permit from the jurisdiction's schedule. Overhead is the company's share of its home office, recovered as a percentage of cost or as a rate per week of the job. The fee is the profit, set by the bidder for this job and this competition. A bid can lower its fee to win; it cannot lower general conditions without lowering the supervision or the cleanup the job needs.

Bid bonds, performance bonds and Miller Act thresholds

The federal rules state the bond thresholds in full. Under FAR 28.102-1, performance and payment bonds are required for any construction contract "exceeding $150,000". For contracts "greater than $35,000, but not greater than $150,000", the contracting officer selects two or more payment protections, giving particular consideration to an irrevocable letter of credit (FAR 28.102-1, FAC 2026-01, effective March 13, 2026). FAR 28.101-1 requires a bid guarantee "whenever a performance bond or a performance and payment bond is required" (FAR 28.101-1), and FAR 28.101-2 sets its amount: "at least 20 percent of the bid price but shall not exceed $3 million" (FAR 28.101-2).

A small contractor without a bonding line can apply through the SBA. Its Surety Bond Guarantee program covers bid, performance and payment bonds on contracts "Up to $9 million for non-federal contracts and up to $14 million for federal contracts". The performance and payment bond guarantee carries a fee of "0.6% of the contract price", and the SBA charges no fee on a bid bond guarantee (SBA, surety bonds, checked November 12, 2026). The surety's own premium is separate and depends on the contractor and the contract. State and local owners publish their own bond requirements in their bid documents.

Office suite renovation in Philadelphia: a sample bid

The sample is a hypothetical bid for the interior renovation of a 3,000-square-foot office suite in an existing building in Philadelphia, invited by a private owner whose instructions require a 5% bid bond and performance and payment bonds. The general contractor performs demolition and carpentry itself and subcontracts the other trades. Crew-hours, material costs, subcontractor quotes, general conditions other than the permit, overhead, fee and the bond rate are sample inputs; the wages, the compensation ratio and the permit fee are published.

The building permit comes from Philadelphia's schedule for alterations in occupancies other than one- and two-family dwellings: $253 for the first 500 square feet plus $60 for each additional 100 square feet, effective October 1, 2026 (City of Philadelphia, construction permit fees). For 3,000 square feet that is $253 + 25 × $60 = $1,753. Trade permits are carried in the subcontractors' quotes.

Sample bid, interior renovation of a 3,000-square-foot office suite, Philadelphia (sample inputs, published rates)
LineBasisAmount
Demolition48 laborer-hours × $32.52$1,560.96
Carpentry: framing, doors, frames, hardware176 carpenter-hours × $42.20$7,427.20
Self-performed materialsSample supplier quotes$12,800.00
ElectricalLeveled quote, subcontractor B$34,600.00
HVACLeveled quote$27,900.00
PlumbingLeveled quote$11,800.00
Drywall and paintLeveled quote$29,400.00
Acoustical ceilingLeveled quote$8,950.00
FlooringLeveled quote$17,300.00
Fire sprinkler modificationsLeveled quote$6,200.00
General conditionsSupervision $14,000; 3 dumpsters × $650; protection and cleaning $2,400; final clean $1,200; permit $1,753$21,303.00
Direct costSum of the lines above$179,241.16
Overhead6% of direct cost$10,754.47
Fee5% of direct cost plus overhead$9,499.78
Subtotal before bond$199,495.41
Performance and payment bond premium2% of the bid price (sample rate)$4,071.33
Bid price$199,495.41 ÷ 0.98$203,566.74

The bond premium is charged on the contract price, which includes the premium, so the bid divides the subtotal by one minus the bond rate rather than adding 2% of the subtotal. The 5% bid bond is $10,178.34.

Two readings of the sample change how the estimator spends bid day. Subcontracted work is $136,150.00, or 66.9% of the bid price, while self-performed labor is $8,988.16, or 4.4%: the bid is decided far more by the leveling of quotes than by the carpenters' hours. The same job let by a federal agency would change three lines. Performance and payment bonds would be required because the price exceeds $150,000, the bid guarantee would be at least 20% of the bid price, or $40,713.35, and the laborers' and carpenters' wages would come from the Davis-Bacon wage determination instead of the BLS medians. If the bonds were guaranteed through the SBA program, its 0.6% fee would add $1,221.40.

Bid day: deadlines, late quotes and the final number

Bid day compresses the last subcontractor quotes, the final leveling and the delivery into a few hours, and the deadline does not move. Under FAR 14.304, a bid received after the exact time set for receipt is late, and a solicitation with no stated time closes at 4:30 p.m. local time on the due date; a late bid is considered only in narrow cases, such as an electronic bid that reached the government's initial point of entry by 5:00 p.m. one working day before the due date, while a late modification that makes an otherwise successful bid more favorable may be accepted (FAR 14.304). Private owners set their own rules in the instructions to bidders.

  1. Freeze the takeoff and the scope sheets the morning before, so late quotes are read against fixed quantities.
  2. Level each quote as it arrives and enter the leveled figure, with plugs for anything excluded.
  3. Plug any trade with no compliant quote at the estimator's own price, and mark it for follow-up.
  4. Recheck the bid form against the instructions: every line filled, every addendum acknowledged, every required attachment present.
  5. Compute the final number, including overhead, fee and the bond premium on the contract price.
  6. Sign the form, attach the bid bond, and seal the bid as the instructions require.
  7. Deliver or upload it with time to spare against the stated deadline, and keep proof of the time of receipt.
  8. Verify after the opening: record every bidder's price, compare the company's leveled trades with the winning number where the results are published, and note which trade decided the outcome.

Construction estimates and quotes outside competitive bidding

Many construction prices are not bids. When one owner asks one contractor for a price, with no bid form and no competing bidders, the document is an estimate or a quote. Writing an estimate for a construction job uses the same takeoff and the same loaded rates, then states its allowances, the assumptions behind its quantities and how far the final cost may move. Writing a quote for a construction job fixes the price for a defined scope, valid until a date, with change terms for anything found later. The difference between the two is set out in quote vs estimate, and the method for a single priced job in how to quote a job. The construction estimate template lays out lines grouped by trade with allowances and a contingency.

Construction bid checklist

  1. The bid package is complete: drawings, specifications, instructions, bid form, contract form, bond requirements, wage determination and every addendum.
  2. The bid or no-bid questions are answered from the documents and the company's own calendar and bonding limit.
  3. The takeoff covers every trade, and each subcontractor received the same scope sheet.
  4. Self-performed hours come from completed jobs, priced at the loaded rate or at the wage determination where Davis-Bacon applies.
  5. Every subcontractor quote is leveled for exclusions, with plugs, and its addenda acknowledgments recorded.
  6. General conditions are priced from the schedule, and the permit from the jurisdiction's current fee schedule.
  7. The bond premium is computed on the contract price, and the bid bond meets the owner's percentage, or 20% on a federal job.
  8. The form is signed, sealed and delivered before the deadline, and the results are recorded after opening.

Bids, crews and job costs in FieldRanger

FieldRanger carries a won bid from the HubSpot deal into the job. An estimate is built from the HubSpot deal or contact record without leaving HubSpot, or built in FieldRanger and kept tied to the deal, and PandaDoc sends estimates and agreements for signature; the estimating software page shows both routes. When the deal is won, it becomes a job with its context carried over, and its crew is assigned on the drag-and-drop calendar, since one job can carry several technicians. Clock-ins and clock-outs record where each worker was, time is logged against each job, and materials used on each job are logged for job costing, so the hours and materials of the finished job can be set beside the bid. Invoices are generated from completed work orders, and revenue reports show job revenue and margin by customer or service type. The takeoff and the leveling sheet stay in the estimator's own tools, and FieldRanger holds the result.

Frequently asked questions

How to bid a construction job?

Read the invitation to bid and every addendum, take off quantities, price self-performed labor at a loaded rate and materials from supplier quotes, level subcontractor quotes for their exclusions, add general conditions, overhead, fee and the bond premium, then submit the signed form before the deadline.

How to bid on a construction job as a general contractor?

Send each subcontractor the same scope sheet from the takeoff, level the quotes that come back with plugs for excluded work, and carry the lowest leveled figure for each trade. Self-perform the trades the company does, price general conditions from the schedule, and meet the owner's bond requirements.

How to price a construction job?

Sum self-performed labor and materials, leveled subcontractor quotes and general conditions to get the direct cost, add overhead and fee, then add the bond premium computed on the contract price. In this guide's sample, a $179,241.16 direct cost becomes a $203,566.74 bid.

How to write an estimate for a construction job?

Use the same takeoff and loaded rates as a bid, then state the allowances, the assumptions behind the quantities and how far the final cost may move, with an expiry date. An estimate states the expected price; it does not fix it.

How to write a quote for a construction job?

Fix the price for a defined scope, list the exclusions, print an expiry date no later than the suppliers' price holds, and state how changes are priced and approved before work starts.

How much is a bid bond on a construction job?

The owner's instructions set it. On federal construction, FAR 28.101-2 sets the bid guarantee at no less than 20 percent of the bid price and no more than $3 million; the sample's private owner asks for 5%, or $10,178.34.

What happens to a late construction bid?

On a federal job it is late if it arrives after the exact time set for receipt, or after 4:30 p.m. local time when no time is stated, and it is considered only in the narrow cases FAR 14.304 lists. Private owners state their own rule in the instructions to bidders.

In the Philadelphia sample, seven subcontractor numbers carry two-thirds of a $203,566.74 bid, and one excluded fire alarm relocation was enough to reorder the electrical quotes. After award, construction crew scheduling takes over the weeks on site and general contractor software holds the job record; the plans, and Start free trial for 14 days without a card, are listed on pricing.