Guide
How to Estimate a Roofing Job:Measuring Squares, IKO Pitch Factors, Waste Allowance, Tear-Off Layers, Materials Takeoff, Crew Labor and Metal Roof Bids
How to estimate a roofing job: measuring squares, IKO pitch factors, waste, tear-off layers, a materials takeoff, crew labor at BLS wages and metal roof bids.
How to estimate a roofing job, in order: measure each roof plane, convert its area to squares of 100 square feet with a pitch factor, add a waste allowance, count the layers to tear off, take off shingles, starter, ridge cap and drip edge from the manufacturer's coverage figures, then price crew hours, disposal, overhead and margin.
An estimate built any other way is short in places that only show up on the roof. Plan area used without a pitch factor under-orders a steep roof by the same share on every line. A second layer of shingles is found at tear-off, after the price was signed. Ridge cap is ordered by the square when it is sold by the linear foot. This page is one of FieldRanger's pricing and quoting guides, written for the owners and estimators who use the roofing contractor software page. It covers measurement, IKO's pitch factor tables, waste and duplicated areas, the re-roof code on tear-off layers, a materials takeoff, crew labor at published wages, overhead and margin, and metal roof bids, then estimates one sample reroof with the arithmetic shown.
Four terms carry the method. A square is 100 square feet of roof surface. Slope, which roofers also call pitch, is the rise in inches per foot of horizontal run, written as 8:12 or "8 inches". A pitch factor, which IKO calls the area/rake factor, converts horizontal area or length into actual sloped area or length. A waste allowance is the material ordered above the measured area for cutting at rakes, hips, valleys and starter courses.
Roofing estimate, roofing bid and roofing quote
The three words name documents built from the same takeoff. An estimate states the expected price for a defined scope and may change if the scope changes, such as a rotten deck found under the shingles. A bid is the price offered in competition, against a written specification where a property manager or general contractor issues one; how to bid a roofing job is therefore a question of matching that specification line by line, and public bid forms, deposits and prevailing wage are covered in how to bid a job. A quote is a fixed offer, valid for a stated period, that becomes the contract price on signature; how to quote a roofing job adds a validity date and allowances for anything hidden.
The general method behind all three, with overhead recovery and validity terms, is in how to quote a job. The fields a roofing estimate carries, filled for a two-layer tear-off, are in the roofing estimate template. This page is the method that produces the numbers for those fields.
Roof measurements from the ground, plans or aerial reports
A roof does not have to be walked to be measured. IKO, a shingle manufacturer, describes estimating "the projected horizontal areas of the roof", which "can be made from the plans, from the ground or from inside the attic", then converting them to true areas with the roof slope (IKO, Estimating How Much Roofing Is Required, checked November 13, 2026).
The horizontal projection is the roof seen from above. Each plane is a rectangle, triangle or trapezoid, measured at the eaves and across the building including overhangs. IKO's method then adds back areas the projection hides: where an upper roof's eaves overhang a lower roof, "such duplicated areas should be added to the total horizontal area". Slope can be read from the ground with a pitch card or a carpenter's folding rule held at arm's length, using IKO's conversion of rule readings to slope.
Aerial measurement reports, bought per address from measurement vendors, deliver the same quantities: plane areas, slopes and the lengths of eaves, rakes, ridges, hips and valleys. A report is checked against one ground measurement before it is used, because a single mis-traced plane carries into every line of the takeoff.
Pitch factors from IKO's area and rake table
IKO's Table 1 gives the factor that converts horizontal area, and horizontal rake length, into actual sloped measure. Table 2 gives a separate factor for hips and valleys, which run diagonally across two slopes.
| Slope (inches per foot) | Area/rake factor | Hip/valley factor |
|---|---|---|
| 4 | 1.054 | 1.452 |
| 5 | 1.083 | 1.474 |
| 6 | 1.118 | 1.500 |
| 7 | 1.157 | 1.524 |
| 8 | 1.202 | 1.564 |
| 9 | 1.250 | 1.600 |
| 10 | 1.302 | 1.642 |
| 11 | 1.356 | 1.684 |
| 12 | 1.414 | 1.732 |
The factor grows with slope. At 4:12 the true area is 5.4 percent above plan area; at 12:12 it is 41.4 percent above. Planes of different slope are converted separately and only then added, as IKO's own figures for a 9-inch and a 6-inch roof show: 1,302 square feet × 1.250 = 1,627.5 and 643 × 1.118 = 718.8.
Squares, waste allowance and duplicated eaves
True area divided by 100 gives squares of roof surface. The waste allowance is added to that figure, not to plan area. IKO's example assumes "a 10% waste allowance" and adds 235 square feet to 2,347.
Ten percent is IKO's figure for its example roof, not a rule for every roof. A plain gable has few cuts; a hip roof with valleys and dormers has many. A company that records squares ordered against squares installed on each completed job learns its own allowance by roof type, and that figure replaces any published one.
Duplicated areas are added before the factor is applied. In IKO's example, 4-inch overhangs at three places add about 11 square feet. The quantity is small; leaving it out on a complex roof with many overlapping eaves is a shortage at the end of the last day.
Tear-off layers and the re-roof code
The number of layers decides whether a new roof can go over the old one at all. The International Residential Code, as quoted in East Point, Georgia's re-roof guide, provides that new roof coverings "shall not be installed without first removing all existing roof coverings" where the existing roof is water-soaked or deteriorated, where it is slate, clay, cement or asbestos-cement tile, or "where the existing roof has two or more applications of any type of roof covering" (City of East Point, 2018 IRC Residential Re-Roof guide, section R908.3.1.1). The same guide answers "How many layers of roofing are allowed?" with "no more than two (2) layers are allowed upon completion of installation".
The layer count is therefore confirmed during the estimate, at a rake edge or a test cut, and written on the estimate. A one-layer roof can be recovered where the manufacturer's instructions allow; a two-layer roof is a full tear-off of both. Tear-off is priced per square per layer, and the dumpster is sized for the weight of every layer removed.
The guide also fixes a fastening requirement that changes the nail order on a tear-off: fasteners "must be long enough to penetrate through the total thickness of the roofing and a minimum of 3/4" into the decking material". Drip edge "is required around entire perimeter of roof", so eaves and rakes together set its length.
Materials takeoff from IKO product data
Each material is counted in its own unit, from the manufacturer's coverage figure for that product. The IKO lines below are an example; the takeoff uses the product actually specified.
| Material | Unit sold | Coverage | Counted from |
|---|---|---|---|
| Dynasty laminated shingles | Bundle | 33 1/3 sq ft; 20 shingles a bundle, 60 a square | Squares including waste |
| Leading Edge Plus starter | Bundle | 109 linear ft | Eaves, and rakes where the installation instructions call for starter |
| Hip and Ridge 12 cap shingles | Package | 29.53 linear ft | Ridges and hips, from true lengths |
| Drip edge | Piece | Linear ft as sold | Eaves plus true rake lengths |
Sources for the table: IKO Dynasty, IKO Leading Edge Plus and IKO Hip and Ridge. Dynasty's exposure is listed as 5 7/8 inches. IKO's hip and ridge page states that IKO Hip and Ridge 12 or Class 4 cap shingles, or an equivalent IKO-approved product, "are required for warranty coverage", so the cap line is not a place to substitute.
Underlayment, ice barrier, valley metal, pipe boots, step flashing and vents are counted the same way, from each roll's or piece's stated coverage and the lengths of the edges and penetrations they serve.
Crew labor at Atlanta roofer wages
Labor is priced as hours times a loaded wage. The hours per square come from the company's own records by task: tear-off per layer, installation by slope band, and flashing by penetration. In the Atlanta-Sandy Springs-Roswell metro, roofers earned a median of $23.61 an hour and $26.97 at the 75th percentile in BLS 2025 wage data (O\*NET OnLine, Georgia wages for 47-2181.00). The employer adds 6.2 percent Social Security and 1.45 percent Medicare (IRS Topic 751, updated November 9, 2026), and workers' compensation, which for roofing is priced by the insurer on the company's payroll.
Hours also set the calendar. A crew's hours per day divide into the job's total hours to give the number of days, and each day is scheduled, staffed and checked as a day of work.
Overhead, margin and the price per square
How to price a roofing job comes down to one build-up: direct cost of materials, labor, disposal and permit, plus a share of the company's overhead, plus margin. Overhead is recovered per job in proportion to the hours the job uses, so that the office, insurance, trucks and estimating time are paid for by the jobs that use them.
The price per square is a check on that build-up, not a way to make one. Two roofs of the same squares differ in layers, slope, access and penetrations, and a single rate per square averages those away. An estimate whose price per square falls far outside the company's recent jobs of the same type is read again line by line before it is sent.
Metal roofing bids: panels, trim and fasteners
How to bid a metal roofing job changes the unit of the takeoff. Panels are counted by coverage width along the eave and cut to the true rake length, not ordered by the square. ABC Metal Roofing lists its MasterRib panel with a coverage width of 36 inches, a 3/4-inch rib on 9-inch centers, a minimum slope of 3:12, an exposed fastening system and 29 or 26 gauge steel (ABC Metal Roofing, MasterRib, checked November 13, 2026).
Three rules follow for the bid:
- Panel count. Eave length divided by the 3-foot coverage, rounded up, for each plane.
- Panel length. The horizontal run times the IKO area/rake factor for the slope, plus the overhang the trim detail needs.
- Slope. Each plane is checked against the panel's minimum slope; a 3:12 panel cannot go on a 2:12 porch.
Trim is counted in linear feet by type: eave, rake or gable, ridge, sidewall and endwall. Fasteners follow the manufacturer's published pattern for the panel and the wind zone. The re-roof code matters here too: East Point's guide quotes R908.3.1 as allowing "complete and separate roofing systems, such as a standing-seam metal roof systems, that are designed to transmit the roof loads directly to the buildings structural system" without removal of the existing covering. An exposed-fastener panel screwed through the old shingles is not that system, so a two-layer roof under a metal bid is still a tear-off.
Sample estimate: a two-slope reroof in East Point, Georgia
The sample is a hypothetical one-story house with a main gable roof and a rear porch shed roof. Dimensions, slopes, the layer count and the hours per square are sample inputs, labelled as such; the factors, coverages, wage and tax rate come from the sources above.
| Line | Basis | Quantity |
|---|---|---|
| Main roof | Plan 30 × 44 ft with overhangs (sample) = 1,320 sq ft × 1.202 at 8:12 (sample) | 1,586.64 sq ft |
| Porch roof | Plan 10 × 24 ft (sample) = 240 sq ft × 1.054 at 4:12 (sample) | 252.96 sq ft |
| Roof area | 1,839.60 sq ft ÷ 100 | 18.40 squares |
| With 10% waste | 2,023.56 sq ft | 20.24 squares |
| Dynasty shingles | 2,023.56 ÷ 33 1/3 sq ft a bundle | 61 bundles |
| Eaves | 2 × 44 ft main + 24 ft porch | 112 linear ft |
| Rakes, true length | 4 × 15 ft × 1.202 + 2 × 10 ft × 1.054 | 93.20 linear ft |
| Starter | 112 ft eaves ÷ 109 ft a bundle (205.20 ft with rakes: also 2 bundles) | 2 bundles |
| Ridge cap | 44 ft ridge ÷ 29.53 ft a package | 2 packages |
| Drip edge | Eaves plus rakes | 205.20 linear ft |
| Existing layers | Confirmed at the north rake (sample) | 2: full tear-off required |
| Line | Basis | Amount |
|---|---|---|
| Tear-off hours | 18.40 squares × 2 layers × 1.0 hour a square a layer (sample) | 36.80 hours |
| Installation hours | 18.40 squares × 2.5 hours a square (sample) | 46.00 hours |
| Wages | 82.80 hours × $23.61 | $1,954.91 |
| Employer Social Security and Medicare | 7.65% × $1,954.91 | $149.55 |
| Labor cost | Wages plus payroll taxes | $2,104.46, or $114.37 a square |
| Crew days | 82.80 hours ÷ 32 hours a day for a crew of four (sample) | 2.6, scheduled as 3 days |
What the pitch factor is worth. Estimated from plan area, the same roof measures 1,560 square feet, 279.6 short of the true 1,839.6, or 15.2 percent. With waste, plan area orders 52 bundles instead of 61, and the 2.8 missing squares carry 7.0 installation hours, $177.91 of labor at the sample rate.
What the layer count is worth. Had the estimate assumed one layer, the second layer's 18.40 tear-off hours, $467.65 of labor with payroll taxes, would have been absorbed by the company, and the dumpster would have been ordered for half the weight.
Material, disposal and permit lines are priced from the supplier's written quote, the hauler's rate and East Point's permit fee on the day of the estimate. The retail pages that publish shingle prices could not be read for this guide on November 13, 2026, so no material price appears in the sample.
Roofing estimate checklist
- Every plane is measured in plan, with overhangs, and its slope recorded.
- Duplicated eaves are added before the pitch factor is applied.
- Each plane's area is converted with the factor for its own slope, then totalled.
- The waste allowance is the company's recorded figure for the roof type, or a stated assumption.
- The layer count is confirmed at a rake edge or test cut and written on the estimate.
- Shingles are counted in bundles, starter and cap in linear feet, drip edge around the whole perimeter.
- Hours per square come from completed jobs, by task, and are priced at a loaded wage.
- Overhead and margin are added to direct cost, and the price per square is compared with recent jobs.
- Metal bids count panels by coverage width and true rake length, and check each plane's minimum slope.
- Verify on completion: compare bundles ordered with bundles installed and hours estimated with hours clocked, and update the allowance and the rates.
Roof estimates, crew days and invoices in FieldRanger
FieldRanger keeps the estimate on the HubSpot records the lead arrived on. An estimate can be built from the HubSpot deal or contact record without leaving HubSpot, or in FieldRanger and tied to the HubSpot deal it belongs to, and estimates and agreements go out for signature through PandaDoc. A won HubSpot deal becomes a job with its context carried over. Photos taken on the job sync to the customer's HubSpot record, and materials tracking logs what each job used for job costing.
Each day of a roof is its own job in FieldRanger, assigned to a technician, since multi-day jobs are not built; the sample's three days are three dated jobs. The assigned technician clocks in and out with time logged against each job, which is the record that sets hours per square on the next estimate. The invoice is generated from the completed work order, and revenue reports show job revenue and margin by service type. Progress billing and retainage are not built, and there is no weather feed. How leads reach the estimate stage is covered in roofing leads, the licensing and budget of a new company in how to start a roofing business, and the estimate record itself on the estimating software page. Plans are on pricing, where Start free trial runs 14 days with no card.
Frequently asked questions
How to estimate a roofing job?
Measure each plane in plan, convert to true area with the pitch factor for its slope, divide by 100 for squares, add a waste allowance, confirm the layers to tear off, take off materials from the manufacturer's coverage figures, and price hours at a loaded wage plus disposal, permit, overhead and margin.
How to bid a roofing job?
Build the same takeoff as an estimate, then match the bid specification line by line: the products named, the layers to remove, the underlayment and flashing details, and the schedule. A bid priced from a different scope than the specification is not comparable with the others.
How to price a roofing job?
Add direct cost of materials, labor, disposal and permit, then a share of overhead in proportion to the job's hours, then margin. The price per square is a check against recent jobs of the same type, not the method.
How to quote a roofing job?
A quote is a fixed price for a stated scope with a validity date. It carries the layer count, the allowances for hidden conditions such as deck replacement, and the date after which material prices are re-checked.
How to bid a metal roofing job?
Count panels by coverage width along each eave, cut them to the true rake length from the pitch factor, check every plane against the panel's minimum slope, and count trim in linear feet by type. ABC Metal Roofing's MasterRib, for example, covers 36 inches and needs at least 3:12.
What pitch factor applies to an 8:12 roof?
IKO's area/rake table gives 1.202 for an 8-inch slope, so 1,320 square feet of plan area is 1,586.64 square feet of roof; its hip and valley factor for the same slope is 1.564.
The East Point sample turns on two readings taken before any price was written: a slope of 8:12, worth nine bundles, and a second layer at the north rake, worth $467.65 of tear-off labor.