How to Bid a Job:Bid Forms, Multi-Year Unit Prices, Bid Deposits, Prevailing Wage and Massachusetts Thresholds

How to bid a job for a public or commercial owner: bid forms, unit prices held for three years, 5% bid deposits, prevailing wage and Massachusetts thresholds.

By Published Updated

16 min read

How to bid a job for a commercial or public owner: read the invitation for bids, price every line on the owner's bid form from loaded labor, travel and overhead, hold unit prices for the full contract term, attach any bid deposit the invitation requires, apply the prevailing wage schedule where the law sets one, and deliver the sealed bid before the opening.

A bid differs from a quote in one respect that shapes the rest of the work: the owner writes the form, and the contractor fills it in. A residential quote describes the job in the contractor's own terms, as set out in how to quote a job. A bid answers the owner's description line by line, and a missing line or a changed term can disqualify it. This guide covers bids for public and commercial service work, using Massachusetts law as the named rule set, then sets out a priced sample, the trade variations for subcontractors, drywall, decks and retaining walls, and a checklist. The other trades' pricing methods sit in the pricing and quoting guides.

Four terms recur. An invitation for bids is the owner's solicitation: in Massachusetts law, the documents used to solicit bids, including documents attached or incorporated by reference (M.G.L. c. 30B, § 2, checked November 12, 2026). The bid form is the page of lines the bidder prices and signs. A bid deposit is security, such as a bid bond, that the bidder forfeits if it wins and then refuses to sign. A prevailing wage schedule is the list of minimum hourly rates a state sets for work on public projects.

Massachusetts procurement thresholds for services and construction

Massachusetts splits public purchasing by what is bought. Supplies and services, such as HVAC maintenance, cleaning or grounds care, fall under chapter 30B. Building construction falls under chapter 149, and other public works under chapter 30, section 39M. Each statute sets its own dollar tiers, and the tier sets the procedure a bidder meets.

Massachusetts procurement tiers by contract type (statutes checked November 12, 2026)
Contract amountSupplies and services (c. 30B)Public works construction (c. 30, § 39M)Building construction (c. 149, § 44A)
Under $10,000Sound business practicesSound business practicesSound business practices
$10,000 to $50,000Written quotations from at least 3 personsWritten responses from at least 3 persons, notice posted 2 weeksWritten responses from at least 3 persons, notice posted 2 weeks
Over $50,000Invitation for bids, sealed and publicly openedCompetitive bids publicly opened, 5% bid deposit$50,000 to $150,000 under § 39M; over $150,000 under §§ 44A to 44H

For services, section 4 has the procurement officer seek written quotations from not fewer than three persons who customarily provide the service, and award to the responsible person offering the needed quality at the lowest quotation (c. 30B, § 4). Above $50,000, or $100,000 for a school district, section 5 requires competitive sealed bidding (c. 30B, § 5). The notice runs at least once in a newspaper and on the COMMBUYS system no less than two weeks before bids are due, and stays posted for two weeks near the office. A contractor who wants public service work therefore registers on COMMBUYS, one of the two places each notice must appear.

The construction side runs on separate statutes. Section 44A sends building contracts from $50,000 to $150,000 to the chapter 30, section 39M procedure, and those above $150,000 to sections 44A to 44H (c. 149, § 44A). The same town can therefore bid its boiler maintenance under one statute and its boiler replacement under another, with different deposit and wage rules.

Bid form lines: unit prices, hourly rates and estimated quantities

The invitation for bids must state the time and date for receipt, the delivery address, the purchase description, the evaluation criteria and all contractual terms (c. 30B, § 5). The bid form converts that description into lines. A service bid form carries three kinds of line.

  • Unit prices. A price per visit, per unit serviced or per square foot, multiplied by a quantity the owner states.
  • Hourly rates. A rate for work the owner cannot quantify in advance, such as repairs, applied to an estimated number of hours.
  • Lump sums. A single price for a defined task, such as a start-up inspection.

Section 12 requires a multi-year solicitation to state the quantity required and whether it is an actual amount or an estimate (c. 30B, § 12). An estimated quantity is the owner's forecast, not a promise of work. A bidder who spreads fixed costs across an estimated 150 repair hours recovers less of them if the owner calls for 60.

Responsive and responsible bidders

Two tests stand between the lowest price and the award. A responsive bidder has submitted a bid that conforms in all respects to the invitation. A responsible bidder has the capability to perform the contract fully, with the integrity and reliability that assure good-faith performance (c. 30B, § 2). The award goes to the lowest bidder who passes both (c. 30B, § 5).

Responsiveness is a property of the document. A bid that adds a fuel surcharge, changes the payment terms or skips a line no longer conforms to the invitation, whatever its price. Responsibility is a property of the company: its staff, licenses, equipment and record. Questions about either are put to the procurement officer in writing, before the deadline the invitation sets for them.

Mistakes have their own rule. Where the mistake and the intended bid are both clearly evident on the face of the document, the procurement officer corrects it and the bidder may not withdraw. Where the mistake is evident but the intended bid is not, the bidder may withdraw (c. 30B, § 5). A unit price that does not multiply out to the extended total is the classic case, so each extension is checked before the envelope is sealed.

Unit prices held across a three-year term

Section 12 caps a contract at three years, including renewals and options, unless a majority vote authorizes longer. For a solicitation covering more than one year, the bidder gives a unit price for each service, and that unit price remains the same throughout the contract unless the solicitation and contract provide for price adjustment (c. 30B, § 12). The option to renew is the owner's alone: no exercise of an option is subject to the contractor's agreement. If funds are not appropriated for a later year, the procurement officer cancels the contract.

The consequence for pricing is direct. Wages rise during the term, but the price per visit does not. Private-industry wages and salaries rose 3.1% in the 12 months to September 2026 (BLS Employment Cost Index, released October 30, 2026). A unit price built on first-year cost loses margin in each later year, so the bid prices the term, not the first year. Where the invitation contains an adjustment clause, the clause's index and dates replace that calculation.

HVAC maintenance bid for a Massachusetts town: a sample

The sample is a three-year preventive maintenance contract for a town's heating and cooling equipment, bid under chapter 30B. The scope, hours, miles, overhead rate and margin are sample inputs; the wage, wage growth, loading and mileage rate are sourced. The scope covers 120 units across 14 buildings, each serviced quarterly, plus repair labor at an hourly rate against an estimated 150 hours a year.

The labor rate starts from the May 2025 median wage of $37.75 an hour for heating, air conditioning and refrigeration mechanics in the Boston-Cambridge-Newton area (BLS OEWS, area 14460). It is carried forward at the 3.1% annual wage growth above to the first contract year, two years later, and grown again for years two and three. Wages were 70.0% of private-industry compensation in June 2026 (BLS Employer Costs for Employee Compensation, released September 9, 2026), so each wage is divided by 0.70 to give the loaded rate. Mileage is costed at the IRS business rate of 76 cents a mile from July 1, 2026 (IRS standard mileage rates, updated July 28, 2026).

Sample HVAC maintenance bid for a Massachusetts town (sample scope and markups; sourced rates)
LineFigureBasis
Unit-visits a year480120 units × 4 quarterly visits, sample
Labor hours a year6421.25 hours a unit-visit plus 0.75 hours travel on each of 56 building visits, sample
Loaded rate, years 1 to 3$57.32, $59.10, $60.93$37.75 grown 3.1% a year, divided by 0.70
Average loaded rate$59.12Mean of the three years
Mileage a year$766.0856 building visits × 18 miles × $0.76
Direct cost per unit-visit$80.67(642 × $59.12 + $766.08) ÷ 480
Unit price per quarterly visit$107.56Direct cost × 1.20 overhead ÷ 0.90, for a 10% margin
Hourly rate for repairs$78.83$59.12 × 1.20 ÷ 0.90
Annual bid$63,453.30480 × $107.56 plus 150 × $78.83
Three-year bid$190,359.90Annual bid × 3

The annual amount exceeds $50,000, so the town buys the service through a sealed invitation for bids under section 5 rather than written quotations. Priced on the three-year average rate, the contract earns a 12.7% margin in year one, 10.0% in year two and 7.3% in year three. Priced on the first-year rate instead, the annual bid falls to $61,557.30, a $1,896.00 difference, and the margin falls to 10.0%, 7.3% and 4.4%. The lower bid gains its advantage at the opening by giving up the third year's margin, a loss the fixed unit price makes certain.

The repair line carries a separate risk. The 150 hours are the town's estimate under section 12, and overhead recovered through the hourly rate shrinks if the town calls for fewer. A bidder can test the price at half the estimated hours before committing to it.

Bid deposits and bonds on public construction

Section 5 of chapter 30B does not set a bid deposit amount for supplies and services, so any deposit on a service contract comes from the invitation's own terms. Public construction is different. A public works contract over $50,000 under chapter 30, section 39M carries a bid deposit of 5% of the value of the bid, in the form of a bid bond, cash, or a certified, treasurer's or cashier's check (c. 30, § 39M). The winning bidder then obtains the security bond required under chapter 149, section 29 within 10 days of notice of award.

Building contracts carry the same 5%. Under chapter 149, section 44B, every general bid and every sub-bid includes a bid deposit of five per cent of the value of the bid (c. 149, § 44B). On a $60,000 public works bid, that deposit is $3,000. A bid bond comes from a surety company, so it is arranged before bid week, not during it. The federal side of bonding, including Miller Act thresholds on federal work, is covered in how to bid a construction job.

Prevailing wage schedules in public bids

Massachusetts sets minimum wages for work on the construction of public works. The commissioner furnishes the awarding body with a schedule of rates, the awarding body incorporates it in the advertisement or call for bids by reference, and the schedule becomes part of the contract as the minimum rates (M.G.L. c. 149, § 27). A legible copy stays posted at the site for the life of the contract. Each year after award, the awarding body requests updated rates, and the general contractor obtains them annually.

The schedule changes the labor line of the bid. The bidder prices each worker classification at the scheduled rate or higher, not at its own payroll rate, and escalates multi-year work by the annual updates. An employee paid less may sue and, if successful, is awarded treble damages for lost wages and benefits. Records follow the work: contractors submit true and accurate copies of payroll weekly to the awarding authority and keep them for three years after the contract is completed (c. 149, § 27B). Those weekly copies are office hours the bid must also carry.

Subcontractor bids and Massachusetts filed sub-bids

How to bid a job as a subcontractor depends on who receives the number. On private work, the subcontractor prices a trade scope and sends it to the general contractor, who compares it with other quotes before bid day. That bid states what is included and excluded, the drawings and addenda it is based on, and how long the price holds, because a general contractor can only carry a number it understands.

Massachusetts public building work adds a second route. For listed classes of work estimated to exceed $25,000, the awarding authority takes filed sub-bids, and those subcontractors bid to the public body rather than to a general contractor (c. 149, § 44F). The listed classes include roofing and flashing, painting, plumbing, heating, ventilating and air-conditioning, electrical work, masonry and fire protection sprinkler systems. A clause also lets the awarding authority add any other class it deems necessary. Each filed sub-bid carries the 5% deposit under section 44B, and a sub-bid without a required deposit is rejected. Plumbing is one of the listed classes, and its trade lines are set out in how to bid a plumbing job.

Drywall bids: board area, finish level and labor

How to bid a drywall job starts from the wall and ceiling area taken off the drawings, less openings, which sets the board count and the finishing area. The finish level sets the hours. The Gypsum Association's GA-214 defines six levels, from Level 0, with no taping or finishing, to Level 5, which adds a skim coat over the entire surface for smooth walls with non-flat paint (National Gypsum, gypsum board finish levels, August 22, 2022). The same source places Level 4 in appearance areas with smooth walls and flat paint, and Level 2 under tile. A bid that assumes Level 4 where the specification calls for Level 5 omits a full skim coat across every wall.

Labor is priced from the trade's wage. Drywall installers, ceiling tile installers and tapers earned a median of $28.74 an hour in May 2025 (BLS Occupational Outlook Handbook, page modified August 27, 2026), before the loading above. On Massachusetts public building work, drywall is not a named filed sub-bid class, although lathing and plastering and acoustical tile are, so drywall is carried in the general bid unless the awarding authority adds it.

Deck bids: permit, prescriptive guide and footings

How to bid a deck job begins with whether the design is prescriptive or engineered, because that decides the drawing cost. The American Wood Council's DCA 6, based on the 2015 International Residential Code, applies to single-level residential wood decks attached to the house (AWC DCA 6). It excludes decks supporting large concentrated loads such as hot tubs, and decks with snow loads above 40 pounds per square foot. It sets a minimum post size of 6x6 and states that a deck is not used or occupied until final inspection and approval.

A bid on a deck outside that scope, such as a multi-level deck or one carrying a hot tub, needs an engineer's design priced as its own line. The other lines are the permit fee, footings by count and depth, framing lumber and connectors, decking, guards and stairs, and the inspection visits, each of which can hold the crew on site.

Retaining wall bids: height, permit and engineering

How to bid a retaining wall job turns on height, because height decides whether a permit and an engineer are in the price. Eagle Mountain, Utah, shows how one local rule is structured. Walls less than four feet high, including the 30-inch footing depth, need no building permit but must meet zoning requirements. Walls taller than 4 feet need a building permit, the application lists required engineered drawings to be checked with the city's Engineering Division, and no wall may exceed 6 feet from finished grade to the top (Eagle Mountain building department, retaining walls, checked November 12, 2026).

A wall bid therefore carries an allowance for the engineer's design and the permit wherever the height crosses the local trigger. Excavation, base material, block or stone by face area, drainage and backfill are the quantity lines. On a public retaining wall in Massachusetts over $50,000, the section 39M deposit and the prevailing wage schedule apply on top.

Written bids for private commercial work

How to write a bid for a job without an owner's form follows the same logic, with the contractor supplying the structure. A property manager or a general contractor reads a written bid against the request, so the bid answers the request in its order.

  1. Restate the scope as the request describes it, with the drawings, specifications and addenda the price is based on.
  2. List the price by line, with unit prices and quantities where the work repeats.
  3. State exclusions, allowances and the assumptions behind any quantity.
  4. Give the price validity period and the payment terms.
  5. Attach the certificate of insurance and any license the work requires.
  6. Sign and date the bid, and confirm the delivery method and deadline in writing.

How to make a bid for a job that will be compared with others is a question of comparability: the same lines, in the owner's order, with nothing left for the reader to infer. The blank layout for a priced document is the quote template.

Public bid checklist from invitation to award

  1. Register on the owner's bid system, such as COMMBUYS in Massachusetts, and download every document and addendum.
  2. Identify the statute and tier: services under c. 30B, public works under c. 30, § 39M, or building work under c. 149.
  3. Read the bid form line by line and list each quantity as actual or estimated.
  4. Confirm whether a bid deposit is required, its amount, and arrange the bond with the surety before bid week.
  5. Check for a prevailing wage schedule and price each classification at or above it.
  6. Price multi-year unit prices on the average cost of the term unless the invitation provides for adjustment.
  7. Test the hourly lines at half the estimated quantity.
  8. Submit written questions before the deadline, and acknowledge every addendum on the form.
  9. Check each extension, sign the form and deliver it sealed before the stated time.
  10. Verify after the opening: compare the recorded bid amounts with the bid as submitted, and record each competitor's price for the next solicitation.

Estimates and won bids on HubSpot records

FieldRanger keeps the bid and the work on the same HubSpot records. An estimate can be built from the HubSpot deal or contact record without leaving HubSpot, or built in FieldRanger and kept tied to the deal it belongs to. PandaDoc sends estimates and agreements for signature. When the deal is won, it becomes a job with its context carried over, and recurring job templates hold a maintenance contract's quarterly visits so each one repeats without being booked again. FieldRanger builds each technician's route for the day automatically, and technicians clock in and out with time logged against each job. Those hours are the record to compare with the 642 bid hours. The invoice is generated from the completed work order, and revenue reports show job revenue and margin by customer or service type, so a fixed unit price can be checked against its actual margin in each contract year. Progress billing and retainage are not built in FieldRanger. The estimating software page describes the estimate in detail.

Frequently asked questions

How to bid a job?

Read the invitation for bids, price every line of the owner's bid form from loaded labor, travel, overhead and margin, attach any required bid deposit, price public work at or above the prevailing wage schedule, acknowledge every addendum and deliver the signed, sealed bid before the deadline.

How to bid on a job for a city or town?

Register on the public bid system, such as COMMBUYS in Massachusetts, find the statute that governs the purchase, and answer the bid form exactly. In Massachusetts, services over $50,000 are bought by sealed invitation for bids, and the award goes to the lowest responsible and responsive bidder.

How to write a bid for a job?

Restate the scope with the documents the price relies on, list prices by line with quantities, state exclusions and assumptions, give the validity period and payment terms, attach insurance and license certificates, then sign and date it.

How to make a bid for a job that runs for several years?

Price the whole term. A Massachusetts unit price stays the same for the contract unless the solicitation provides for adjustment, so the bid uses the average cost of the term, not the first year's cost.

How to bid a job as a subcontractor?

Price the trade scope from the drawings and addenda, state inclusions, exclusions and how long the price holds, and send it to the general contractor before bid day. On Massachusetts public building work over $25,000 in listed trades, the subcontractor files a sub-bid with the awarding authority instead.

How to bid a drywall job?

Take off wall and ceiling area less openings, count boards, price the finish level the specification names, and price labor from the trade wage loaded for taxes and benefits. Level 5 adds a skim coat over the whole surface, so it carries more hours than Level 4.

How to bid a deck job?

Confirm whether the deck fits a prescriptive guide such as AWC DCA 6 or needs an engineer, then price the permit, footings, framing and connectors, decking, guards, stairs and inspection visits as separate lines.

How to bid a retaining wall job?

Check the local height trigger for a permit and engineering, price the design and permit where the wall crosses it, then price excavation, base, block by face area, drainage and backfill.

How much is a bid deposit on a Massachusetts public job?

Five percent of the value of the bid for public works over $50,000 under chapter 30, section 39M, and for general bids and sub-bids on building work under chapter 149, section 44B. It may be a bid bond, cash or a certified, treasurer's or cashier's check.

In the sample, a unit visit bid at $104.36 on first-year cost still pays $104.36 in year three, when its margin has fallen to 4.4%; the level price of $107.56 holds 7.3% in the same year. The pricing and quoting guides cover the trade methods behind each line; plans, and Start free trial for 14 days without a card, are on pricing.