Payment Terms for Contractors:Net Days, Due on Receipt, Deposits, Milestone Payments, Late Charges and Virginia's Prompt Payment Statutes

Payment terms for contractors: net days, due on receipt, deposits, milestone payments, late charges and Virginia's prompt payment statutes, with a sample job.

By Published Updated

13 min read

Payment terms for contractors set when and how a customer pays: the due date counted from the invoice (due on receipt, net 15, net 30), any deposit taken before work starts, milestone payments during a longer job, the payment methods accepted, and the charge for paying late. The terms bind when the customer signs them before the work begins.

Terms fail at the joins between the job and the money. A net 30 invoice goes out on a replacement whose equipment the contractor paid for on day one. A deposit is taken with no amount written in the contract. A general contractor holds a subcontractor's payment for weeks and never says why. This page belongs to FieldRanger's invoicing and getting paid guides. It defines the term types, sets out what statutes treat as typical, applies Virginia's prompt payment statutes to private and public work, and prices one residential job and one subcontract under the terms described. A checklist, the software record and a short FAQ follow.

Five terms carry the page. Net terms give the number of calendar days after the invoice date by which payment is due: net 30 means 30 days. Due on receipt means payment is owed when the invoice arrives. A deposit, or down payment, is paid when the contract is signed and before work starts. A milestone payment is due when a named stage is complete, such as equipment set or rough-in inspected. Prompt payment statutes are state and federal laws that fix the latest date an owner, an agency or a general contractor may pay, and the interest owed after it.

Net terms and due on receipt: the due-date clause

The due-date clause answers one question: on which calendar date does the balance become late. Net terms count from the invoice date, so an invoice dated March 3 on net 30 is due April 2. Due on receipt has no grace at all, and it suits work finished and accepted on site, such as a service call paid before the van leaves.

Three drafting details decide whether the clause can be enforced as written:

  1. The start of the count. "Net 30" counts from the invoice date, while "30 days after completion" counts from an event the parties may later dispute. The invoice date is the cleaner anchor.
  2. The calendar date on the invoice. The invoice prints the due date itself, not only the term, so nobody has to count.
  3. The condition of a proper invoice. Public agencies pay only against an invoice that meets their requirements; federal law gives an agency 7 days to return an improper invoice with the reasons (31 U.S.C. § 3903). A purchase-order customer also checks the order number on the invoice, as the invoice vs purchase order guide sets out, and the contents of a proper invoice under the federal, New York and Florida payment clocks are in contractor invoice.

Typical payment terms for contractors by customer and contract type

No single term fits every customer, because the statutes that set the outer limits differ by who pays. The figures below are the legal benchmarks for each payer; a contract may set a shorter period inside them.

Payment benchmarks set by statute, by payer (checked November 13, 2026)
Payer and workBenchmarkSource
Federal agency, ordinary invoice30 days after a proper invoice, where the contract sets no date31 U.S.C. § 3903(a)(1)(B)
Federal agency, construction progress paymentInterest owed if unpaid more than 14 days after the payment request31 U.S.C. § 3903(a)(6)(A)
Virginia locality, goods or servicesThe contract date, or 45 days after receipt or invoice, whichever is laterVa. Code § 2.2-4352
Virginia private owner to general contractorWithin 60 days of the invoice for satisfactorily completed workVa. Code § 11-4.6(B)(1)
Virginia general contractor to subcontractorThe earlier of 60 days after the invoice or 7 days after being paidVa. Code § 11-4.6(B)(2)

Homeowner work falls outside these payer rules, and the contract carries the whole arrangement. Virginia's Board for Contractors makes the payment schedule part of the required contract for residential work, as the next section shows. A service call on a homeowner's existing equipment is the case where due on receipt fits: the work is small, finished in one visit and accepted on site.

Deposits and down payments in residential contracts

A deposit pays for the commitment: ordered equipment, a reserved crew date and material bought for one customer. It is a written amount, stated before work begins, and it is credited against the contract price on the final invoice.

Virginia regulates the wording rather than the size. The Board for Contractors treats as a prohibited act the failure of residential contractors to use a written contract that includes "the amounts and schedule for progress payments, including a specific statement on the amount of the down payment" (18VAC50-22-260, amended effective September 1, 2025). The same list requires the contract to be signed by both parties "prior to commencement of work or acceptance of payments", to disclose cancellation rights, and to state that any change to cost or scope must be in writing and signed. Routine maintenance and service contracts are excluded from that written-contract rule.

Three practical consequences follow for a Virginia residential job:

  • The deposit appears as a dollar figure in the signed contract, not as "a deposit is required".
  • No money is accepted before both signatures are on the contract.
  • A change order that raises the price is signed before the extra work, so the final invoice matches a signed document.

This Virginia rule sets no percentage. Each state writes its own home improvement rules, so a contractor working across a state line reads the statute of each state before reusing one contract.

Milestone payments and progress billing compared

A milestone payment is due when a named, checkable event happens: equipment delivered, rough-in inspected, system started. Progress billing invoices a percentage of each line of a schedule of values at the end of each period, less retainage. Federal law treats both as progress payments on construction contracts, naming "milestone payments for completed phases, increments, or segments of any project" in the same clause as monthly percentage-of-completion payments (31 U.S.C. § 3903(a)(6)(A)).

The difference for a field service company is administrative. A milestone schedule has three or four lines, each tied to an event a technician can photograph. A progress billing schedule has many lines, a pay application each month and retainage held until completion; it is set out line by line in the progress billing guide. A replacement job finished in a week suits milestones; a six-month new-construction contract runs on pay applications.

Virginia prompt payment rules for private construction: Code § 11-4.6

Virginia's private-work statute covers more than new building. A "construction contract" includes "the construction, alteration, repair, or maintenance of a building, structure, or appurtenance thereto", and an "owner" is any person or entity other than a public body (Va. Code § 11-4.6, as shown November 13, 2026).

Owner to general contractor. The contract must require the owner to pay "within 60 days of the receipt of an invoice following satisfactory completion of the portion of the work for which the general contractor has invoiced". An owner who withholds any part must give written notice within 45 days of receiving the invoice, "specifically identifying the contractual noncompliance and the dollar amount being withheld". Late payment "shall result in interest penalties consistent with § 2.2-4355".

General contractor to subcontractor. Payment is due within the earlier of 60 days after the subcontractor's invoice or "seven days after receipt of amounts paid by the owner". Withholding needs written notice within 50 days. Payment by the owner "shall not be a condition precedent to payment to any subcontractor", unless the party contracting with the contractor is insolvent or bankrupt, and "any provision in a contract contrary to this section shall be unenforceable". On projects other than single-family homes worth more than $500,000, every lower-tier subcontract carries the same terms.

The interest rate. Section 2.2-4355 sets the rate as the prime rate "as reported daily in the publication entitled The Wall Street Journal" (Va. Code § 2.2-4355). The Federal Reserve's H.15 release showed the bank prime loan rate at 7.00 percent on November 12, 2026 (Federal Reserve, H.15 Selected Interest Rates). That section starts interest "after seven days following the payment date" for state agencies; whether the seven days carry into a private contract through the words "consistent with" is a question for counsel, and the sample below prices both readings.

Virginia prompt payment rules for local government work: Code §§ 2.2-4352 and 2.2-4354

A city, county or school board in Virginia pays by "the date on which payment is due under the terms of the contract" or, where the contract sets no date, "not more than forty-five days after goods or services are received or not more than forty-five days after the invoice is rendered, whichever is later" (Va. Code § 2.2-4352). The agency has 20 days to report any defect that would prevent payment. Unless the contract says otherwise, a late agency pays finance charges assessed by the supplier "that shall not exceed one percent per month".

A contractor on public work also owes its own subcontractors. Section 2.2-4354 requires every state and local contract to make the contractor pay a subcontractor's share, or give written notice of withholding, within seven days of being paid, and to carry the clause "Unless otherwise provided under the terms of this contract, interest shall accrue at the rate of one percent per month" (Va. Code § 2.2-4354). That interest is the contractor's own cost and cannot be billed back to the agency.

Late charges and interest after the due date

A late charge is agreed in the contract; statutory interest applies where the contract is silent or the statute overrides it. The two are calculated differently, and the clause that counts the days matters as much as the rate, as the late payment fee guide shows with a calculation on two invoices. What happens on the customer side once the date passes, and the order of reminders, is in the late payment guide.

For Virginia public work the ceiling is stated: one percent per month on a locality's late payment unless the contract provides otherwise. For Virginia private construction the rate is the prime rate under § 2.2-4355. A contract that sets a higher private late charge is checked against Virginia's usury and contract law by counsel before it is signed.

Payment methods and their processing cost

The terms name the methods accepted, because each one has a different cost to the contractor. Stripe lists 2.9 percent plus 30 cents per successful domestic card transaction online, an extra 0.5 percent for manually entered cards, 2.7 percent plus 5 cents for in-person card payments through Terminal, and 0.8 percent for ACH Direct Debit with a $5.00 cap (Stripe pricing, checked November 13, 2026).

The cap changes the arithmetic on large balances. On a $5,920 final payment, an online card payment costs $171.98 and an ACH debit costs $5.00. Terms can therefore name bank transfer or ACH as the expected method on project balances, with cards accepted for service calls. A card surcharge added to the invoice is checked against state law and the card network's rules before it appears. An HVAC company that also states its accepted methods and financing on its service pages keeps the website and the contract consistent; the pages themselves are covered in seo for HVAC contractors.

Sample terms on a Richmond, Virginia job and a Virginia subcontract

The figures below are sample inputs for a hypothetical heating and cooling company, labelled as such. The rates come from the statutes and the Stripe and Federal Reserve pages cited above.

Residential replacement. A homeowner signs a $14,800 heat pump replacement (sample). The contract states a 10 percent deposit at signing, 50 percent when the equipment is set, and the 40 percent balance due on receipt at start-up (sample terms).

Sample residential payment schedule and the processing cost of each method (sample inputs labelled; Stripe rates checked November 13, 2026)
PaymentAmountOnline card, 2.9% + $0.30ACH, 0.8% capped at $5.00In-person card, 2.7% + $0.05
Deposit at signing (sample)$1,480.00$43.22$5.00$40.01
Equipment set (sample)$7,400.00$214.90$5.00$199.85
Balance at start-up (sample)$5,920.00$171.98$5.00$159.89
Total$14,800.00$430.10$15.00$399.75

The schedule puts $8,880 in hand before the start-up visit, which is 60 percent of the contract against equipment already bought. The method clause moves $415.10 between the two ends of the table on one job.

Private subcontract under § 11-4.6. The same company invoices a general contractor $22,400 for ductwork rough-in on a private office fit-out (sample). The general contractor is paid by the owner on day 40 after the invoice (sample), so its deadline is day 47, the earlier of day 60 and seven days after receipt. It pays on day 62 (sample), 15 days late.

At the 7.00 percent prime rate, interest is $22,400 × 7.00% ÷ 365 = $4.30 a day. Fifteen days come to $64.44. If the seven-day allowance in § 2.2-4355 is read into the private contract, eight days are charged, or $34.37. Neither figure is large; the statute's value to the subcontractor is the fixed deadline and the written notice required before any amount is withheld, not the interest.

Payment terms checklist

  1. The due date is stated as a term and as a calendar date on every invoice.
  2. Net terms count from the invoice date, not from completion or acceptance.
  3. The deposit is a dollar figure in the signed contract, taken only after both signatures.
  4. Milestones name events a technician can photograph and date.
  5. Late charges and the interest basis are written in the contract, with the annual figure beside any monthly rate.
  6. Virginia private work: the contract allows 60 days at most and requires written notice within 45 days of any withholding.
  7. Virginia subcontracts: payment within the earlier of 60 days or seven days after the general contractor is paid; no pay-if-paid clause.
  8. Virginia local government work: the contract date or 45 days, finance charges no higher than one percent per month.
  9. Accepted payment methods are listed, with ACH or bank transfer named for large balances.
  10. Verify on the first job under new terms: recompute the due date, the late charge and the processing cost by hand, and compare them with what the invoice and the payment record show.

Estimates, invoices and payment records in FieldRanger

FieldRanger holds the terms where the sale is made. An estimate can be built from the HubSpot deal or contact record without leaving HubSpot, or in FieldRanger and kept tied to the HubSpot deal it belongs to, and estimates and agreements go out for signature through PandaDoc, so the signed payment schedule sits on the customer's record. A won HubSpot deal becomes a job with its context carried over, and the invoice is generated from the completed work order. Payment can be taken in the field through Stripe, invoices and payments sync with QuickBooks, and revenue reports show job revenue and margin by customer or service type.

A deposit invoice can go out before the job, with the balance invoiced on completion, so the deposit term in the contract has its own bill. Recurring work can be charged automatically to a card on file. FieldRanger does not do progress billing or retainage, so a contract paid on monthly pay applications is billed outside it. The path from the last task on site to the bill is on the contractor invoicing software page, the fields of one bill are on the invoice template, and plans are on pricing, where Start free trial runs 14 days with no card.

Frequently asked questions

What are payment terms for contractors?

The written rules for when and how a customer pays: the due date counted from the invoice, any deposit, milestone payments during the job, the accepted payment methods and the charge for paying late. They bind when signed before the work begins.

What are typical payment terms for contractors?

Statutes set the outer limits by payer. Federal agencies pay ordinary invoices 30 days after a proper invoice where the contract sets no date; in Virginia, private owners pay a general contractor within 60 days, localities within 45 days where the contract is silent, and general contractors pay subcontractors within the earlier of 60 days after the invoice or seven days after being paid.

What does net 30 mean on a contractor invoice?

Payment is due 30 calendar days after the invoice date. The invoice prints the resulting calendar date so that neither party has to count.

How much deposit can a contractor take in Virginia?

Virginia's Board for Contractors does not set a percentage in 18VAC50-22-260; it requires the residential contract to state the amount of the down payment and the schedule of progress payments, signed by both parties before any payment is accepted.

Can a general contractor wait to pay a subcontractor until the owner pays?

Not on Virginia construction contracts. Code § 11-4.6 makes owner payment no condition precedent to paying a subcontractor, unless the paying party is insolvent or bankrupt, and makes a contrary contract provision unenforceable.

What interest applies when a Virginia owner pays a contractor late?

Section 11-4.6 applies interest consistent with § 2.2-4355, which uses the prime rate. The Federal Reserve's H.15 release showed the bank prime loan rate at 7.00 percent on November 12, 2026.

On the sample subcontract, 15 days of delay cost the general contractor $64.44 or $34.37 depending on one cross-reference, while the method clause on the homeowner's contract moved $415.10. The terms worth drafting first are the ones that decide which day the money is due and by which rail it arrives.