Industry
Concrete Contractor Invoicing Software:Flatwork, Foundation Stage and Pump Charges in FieldRanger and HubSpot
Concrete contractor invoicing software on HubSpot: FieldRanger bills each pour and foundation stage from its work order, with the batch tickets as the record.
Concrete contractor invoicing software bills each pour from the work actually placed: the slab or foundation stage, the yards behind it, the pump, and the supplier's extra charges. FieldRanger generates the invoice from the completed work order inside HubSpot, with the batch ticket photos on the same job, and syncs it to QuickBooks.
The trade as a whole, from silica rules to forms and saws, is on concrete contractor software. This page covers the bill: what a concrete invoice charges for and which of three yard counts it uses. It also covers how a ready-mix supplier's charges reach the invoice, and how Minnesota taxes installed and delivered concrete.
Billing units for flatwork and foundations
A concrete invoice charges for the finished work, and the unit of that work depends on the customer. A homeowner buys a driveway. A builder buys a foundation in stages. A general contractor buys yards or square feet at a unit price written into a subcontract.
| Job | Billed by | What the invoice states | Invoiced when |
|---|---|---|---|
| Residential flatwork: driveway, patio, walk | The job, or the square foot at a stated thickness | Area, thickness, finish, control joints, sealing | The pour and finish are complete |
| Garage or shop slab | The square foot, or the job | Area, thickness, reinforcement, vapor barrier | The slab is complete |
| Foundation for a builder | Each stage: footings, walls, slab | The stage and the inspection it passed | Each stage is complete |
| Commercial subcontract | Unit price per cubic yard or square foot, or a lump sum | The quantity the subcontract pays on | The subcontract's billing terms |
| Repair, leveling and sealing | The job, or the hour | Area treated and material used | The repair is complete |
Each row is a job in FieldRanger, and each completed work order generates its own invoice. A driveway is one job and one invoice. A foundation is three or more jobs on the builder's HubSpot company, one per stage, with an invoice as each stage closes.
Delivered yards, placed yards and plan quantity
Three quantities describe the same concrete. Delivered yards are what the batch tickets show leaving the trucks. Placed yards are what ended up in the forms, including any over-excavation. Plan quantity is the volume computed from the drawings or the estimate's dimensions. They differ on every pour, and the contract decides which one the customer pays for.
State highway work shows the plan-quantity method in its plainest form. MnDOT's Bridge Construction Manual quotes Specification 2401: concrete "will be measured, as indicated in the Proposal, by volume or by area, based on the dimensions shown in the Plans." No increase is allowed for concrete used to bring the finished slab to the plan's profile and cross section (MnDOT Bridge Construction Manual, 5-393.304, November 1, 2005). The tickets still matter there. MnDOT's inspector guide lists the ticket's contents, among them the cubic yards, the daily cumulative yards, the batch date and time, and the mix designation (MnDOT Inspector's Job Guide, Ready-Mix Concrete, Producer, checked November 2026).
A residential flatwork price works the same way in practice. The homeowner pays for the driveway quoted, and the extra yards a soft base swallows are the contractor's cost unless the contract says otherwise. A subcontract priced per cubic yard has to name its quantity, delivered or plan, before the first ticket arrives. The allowance between plan yards and ordered yards is priced on concrete estimating software; the invoice is where that allowance either holds or does not.
FieldRanger keeps the evidence for each count on the job. Batch tickets are photographed onto the work order, and delivered yards are logged as materials used. Photos of the forms record the dimensions before the pour. The estimate on the HubSpot deal holds the plan quantity.
Supplier charges: part loads, unloading time, returned concrete and pumps
A ready-mix supplier bills the contractor for more than yards, and each extra charge raises the question of whether the customer pays it. Cemstone, a Minnesota producer, publishes its 2026 terms:
- Loads of 6 1/4 cubic yards and less carry a part load charge.
- Unloading beyond 7 minutes per cubic yard, or beyond the customer-requested truck spacing, is charged at $200 an hour.
- Returned concrete of 2 or more yards carries a $300 disposal fee.
- Orders cancelled or rescheduled with less than 18 standard operating hours' notice may be charged $200 an hour per truck.
- Pump travel time is charged portal to portal, and placements requiring line carry additional charges.
Source: Cemstone, Ready Mixed Concrete Customer Service Guidelines 2026, checked November 2026.
Each charge has a cause on site: a balance load at the end of a pour, a slow discharge into a wheelbarrow line, a pour called off for rain. A contract that passes these charges through says so in the estimate, and the invoice then carries them as their own lines. The ticket photo and the located clock-in times on the job are the record if the customer disputes a standby charge.
Pump charges come in two forms. A pump subcontractor bills the contractor for its truck, with travel portal to portal on Cemstone's terms, and the contractor rebills or absorbs it. A contractor-owned line pump is an equipment record instead: the QR check-out assigns it to the job, and usage history shows which pours it served.
Minnesota sales tax on installed and delivered concrete
Minnesota draws its line between installing concrete and selling it. On a construction contract, the Minnesota Department of Revenue says contractors pay sales and use tax on the cost of all materials, supplies and equipment. Its two instructions follow: "Do not charge sales tax on construction contracts" and "Do not itemize sales tax separately on the invoice" (Minnesota Revenue, General Contractors and Subcontractors, updated June 18, 2024).
Concrete sold without installation is a different transaction. "Ready-mixed concrete sold from a ready-mixed concrete truck, without installation, is taxable," transportation, delivery and other service charges included. No deduction is allowed for those charges, even when they are separately stated (Minnesota Revenue, Ready-Mixed Concrete Contractors, checked November 2026).
For a Minnesota flatwork contractor, the two rules produce two kinds of document. The supplier's bill to the contractor carries tax on the concrete and its delivery charges, because the supplier sells without installing. The contractor's invoice for a placed driveway carries no sales tax line, because the driveway is a construction contract. The tax already paid sits inside the contractor's cost. A load sold to a homeowner who places it without the contractor's crew is a retail sale, taxed on the full price including delivery.
FieldRanger does not decide which charges are taxable. The state's rules decide, the company's accountant applies them, and QuickBooks, which receives FieldRanger's invoices and payments, holds the tax settings.
Foundation stages as separate invoices
Builders pay foundations by stage, and FieldRanger bills them the same way. Footings, walls and slab are separate jobs on the builder's HubSpot company, and each day of work is its own job. When a stage's work order is completed, it generates that stage's invoice. A job status change can trigger a HubSpot workflow, such as a task for the office to send the footing invoice to the builder's payables contact.
FieldRanger does not do progress billing. It has no schedule of values, no percent-complete draws and no retainage held to the end of the contract. A deposit invoice can go out at signing, with the balance invoiced on completion.
A driveway invoice from ticket to QuickBooks
The driveway measures 16 by 48 feet at 5 inches thick: 768 square feet and 11.85 cubic yards in the forms. The contractor orders 12.5 yards. The first truck brings 10 yards and the second a 2.5-yard balance load, which falls under Cemstone's part load threshold. The first truck's 10 yards allow 70 minutes of unloading at 7 minutes a yard. A slow discharge takes 95 minutes, and the 25 minutes over cost $83.33 at $200 an hour.
| Line | Quantity | On the homeowner's invoice | Record on the FieldRanger job |
|---|---|---|---|
| Driveway, 5-inch, broom finish, saw-cut joints | 768 square feet | Yes, at the quoted price | Estimate on the HubSpot deal; form photos |
| Concrete delivered | 12.5 cubic yards on 2 tickets | No; inside the quoted price | Batch ticket photos; yards logged as materials |
| Part load charge on the second truck | 1 | Only if the contract passes it through | Ticket 2, 2.5 cubic yards |
| Excess unloading time | 25 minutes, $83.33 | Only if the contract passes it through | Ticket times; located clock-ins |
| Sales tax | None | No line, under Minnesota's construction contract rule | Tax paid on the supplier's bill |
The invoice is generated from the completed work order. The homeowner can pay in the field through Stripe, and the invoice and payment sync to QuickBooks. The completion, the photos and the notes reach the HubSpot timeline, where the estimator who sold the driveway sees the job closed.
Payment records and revenue by job type
Revenue reports show job revenue and margin by customer or service type. Flatwork, foundations and repairs then sit side by side on what each earns. HubSpot reports follow revenue from the first lead to the completed job. A builder account's foundations can be traced to the deal that opened it. Job status shows on each HubSpot deal, which tells a salesperson whether the stage just quoted has been poured and billed.
Knowify and AIA pay applications
Subcontract billing on AIA forms is a separate product category. Knowify's AIA billing page states that it can "Generate accurate G702/G703 pay apps in minutes" and build schedules of values automatically. It tracks retainage by phase and takes completed work in dollars or percentages. Approved change orders go into the correct billing period, and pay app and retainage information syncs with QuickBooks Online (Knowify, AIA billing, checked November 2026).
Knowify is the better fit for a concrete subcontractor that bills general contractors on pay applications with retainage. FieldRanger fits a contractor whose work closes pour by pour and stage by stage, with each invoice generated from a completed work order on the customer's HubSpot record. The general invoicing mechanics are on contractor invoicing software.
Concrete billing outside FieldRanger
- No progress billing, schedule of values or retainage.
- No AIA G702 and G703 pay applications.
- No sales tax determination; the accountant and QuickBooks apply the state's rules.
Frequently asked questions
What is concrete contractor invoicing software?
Software that bills concrete work from what was placed: flatwork jobs, foundation stages, pump time and supplier pass-through charges. FieldRanger generates each invoice from the completed work order inside HubSpot and syncs it to QuickBooks.
Do concrete contractors bill for yards delivered or yards placed?
The contract decides. Residential flatwork is priced by the job or the square foot, so extra delivered yards are the contractor's cost; MnDOT pays highway concrete on plan dimensions; a subcontract priced per cubic yard names its quantity in advance.
Do concrete contractors charge sales tax in Minnesota?
Not on a construction contract. Minnesota Revenue says contractors pay tax on their materials and must not charge or itemize sales tax on construction contracts. Ready-mixed concrete sold from a truck without installation is taxable, delivery charges included.
How are concrete pump charges invoiced?
A pump subcontractor bills the contractor, with travel time portal to portal on Cemstone's 2026 terms, and the contractor rebills or absorbs it under the contract. A contractor-owned pump is tracked in FieldRanger as equipment checked out to each job.
Can FieldRanger do progress billing for foundation work?
No. Each foundation stage is its own job with its own invoice from the completed work order; schedules of values, percent-complete draws and retainage are not built.
How much does concrete contractor invoicing software cost?
FieldRanger is priced per technician on the pricing page. The trial runs for 14 days and asks for no card.
The 16-by-48 driveway closes with two batch tickets, 25 minutes of standby and no sales tax line. Each of those facts has a photo or a timestamp on the FieldRanger job. Pricing the pour comes first, on concrete estimating software; the trade is on concrete contractor software. Pricing lists the plans, and Start free trial runs 14 days with no card.