Concrete Estimate Template:Cubic Yards with Waste, Forms, Reinforcement, Finish, Joints and Pump Lines

Concrete estimate template with cubic yards and a waste factor, forms, reinforcement, finish, joints and pump lines, filled for a driveway in Savannah, Georgia.

Updated 11 min read

Download .xlsxExcel spreadsheet · 15 KB · Free, no sign-upFill it in online

A concrete estimate template is the priced scope of a pour: each slab or footing with its dimensions and cubic yards, the waste factor and yards ordered, forms, reinforcement, base, finish, joints, the pump or chute, demolition, the permit, exclusions, the price and the terms. The example prices a driveway replacement with a right-of-way apron in Savannah, Georgia.

The field list is one of the free field service templates kept by FieldRanger, the concrete contractor software that runs inside HubSpot. The concrete estimating software page sets out volume formulas for slabs, footings and walls and how FieldRanger holds the estimate. This page sets out the document the customer signs, with every row filled for one job, and offers it as a free .xlsx download with no sign-up.

Concrete estimate fields from takeoff to terms

Concrete estimate template fields and what goes in each
FieldWhat goes in it
ContractorBusiness name, address, telephone, and the liability insurer and limit
Estimate number, date and expiryA unique number, the issue date and the date the price lapses
Customer and siteName, address, truck access, the right-of-way line, utilities and trees near the work
Pour elementsEach slab, apron, footing or wall with length, width and thickness
VolumeCubic feet and cubic yards of each element, the waste factor, and the yards ordered in the supplier's increment
MixSpecified strength in psi, fiber or air entrainment, color, and the supplier
DemolitionExisting concrete to remove, its area and thickness, and haul-off
BaseMaterial, thickness, compaction standard and area
FormsLinear feet of forms and bulkheads, and the lumber or steel used
ReinforcementFiber, welded wire or rebar with bar size and spacing, dowels and chairs
PlacementChute, line pump, boom pump or buggy, with the reason and the minimum charge
FinishBroom, trowel, stamped or exposed aggregate, and any slope the finish must hold
JointsControl joint layout and depth, saw-cut timing, isolation and construction joints
Curing and protectionCuring method, traffic restrictions, and weather protection
PermitIssuing department, the application's attachments, the fee and the processing time
ExclusionsHidden conditions, rock, buried utilities, irrigation and landscape repair
Price and optionsLine items with the total, and options listed outside it
Terms and acceptanceDeposit, balance due, payment methods, signature and date

Filled concrete estimate: driveway and apron replacement in Savannah, Georgia

The job replaces a cracked 4-inch driveway and its apron. The new driveway runs 40 feet from the garage slab to the back of the sidewalk; the apron crosses the sidewalk and the planting strip to the curb, inside the city right-of-way. The business, customers and prices are illustrative; the apron's thickness, strength, fiber, tint, compaction and permit rows follow the City of Savannah application cited below.

Filled concrete estimate, site, mix, joints and terms (example business, illustrative entries)
FieldExample entry
ContractorExample Concrete LLC, 800 Example Road, Savannah, GA 31405 · 912-555-0138 · liability insurer and limit (example)
Estimate number, date and expiryCN-2026-0512 · November 12, 2026 · valid until December 31, 2026
Customer and siteJordan and Rae Whitfield, 418 Sample Street, Savannah, GA 31404 · trucks stage on the street · water meter box 4 ft east of the apron edge, outside the driveway · street tree in the planting strip west of the apron
Pour elementsDriveway, private property: 16 x 40 ft, 4 in · apron, right-of-way: 16 x 12 ft, 6 in, including the 4 ft sidewalk crossing
MixDriveway: 4,000 psi with synthetic fiber · apron: 5,000 psi, fiber-reinforced, tinted to the city's specification · same supplier, two loads
BaseGraded aggregate base, 4 in, under both pours · right-of-way portion compacted to 100% of ASTM D698
ReinforcementSynthetic fiber in both mixes, added at the plant · no welded wire
PlacementApron by truck chute from the street · driveway by line pump: the far end is 52 ft from the curb, beyond chute reach
FinishMedium broom across the slope · sidewalk crossing held to a 4 ft path at no more than 2% cross-slope
JointsDriveway: center joint and transverse joints at 10 ft, panels 8 x 10 ft, sawn 1 in deep · apron: center joint, and a joint at the front edge of the sidewalk, sawn 1.5 in deep · saw cutting 4 to 12 hours after finishing · isolation joints at the garage slab and the curb · formed construction joint at the right-of-way line between the two pours
Curing and protectionCuring compound sprayed after finishing · no vehicles for 7 days, the contractor's term · pour rescheduled for rain
PermitCity of Savannah Traffic Engineering driveway permit · sketch of location and dimensions attached · filed four working days before work begins
ExclusionsIrrigation repair; sod replacement in the planting strip; root cutting beyond the street tree work the city allows
Terms and acceptance30% deposit to book the pour · balance on completion · check or bank transfer · signatures and date
Filled concrete estimate, volumes and yards ordered
ElementDimensionsCubic feetCubic yardsWith 8% wasteOrdered
Driveway16 x 40 ft x 4 in213.37.908.539.0 yd³
Apron16 x 12 ft x 6 in96.03.563.844.0 yd³
Total309.311.4612.3713.0 yd³
Filled concrete estimate, line items (illustrative prices)
LineQuantityUnit priceLine total
Demolition and haul-off, existing 4 in driveway and apron832 sq ft$2.25$1,872.00
Graded aggregate base, 4 in, compacted832 sq ft$1.10$915.20
Forms and bulkhead, set and stripped120 lf$3.50$420.00
Concrete, driveway, 4,000 psi with fiber9.0 yd³$165.00$1,485.00
Concrete, apron, 5,000 psi, fiber, tinted4.0 yd³$205.00$820.00
Supplier short-load charge, apron load1$150.00$150.00
Line pump, driveway pour, minimum charge1$650.00$650.00
Place, broom finish and cure832 sq ft$2.60$2,163.20
Isolation joints, garage slab and curb32 lf$4.00$128.00
Saw-cut control joints116 lf$1.50$174.00
Driveway permit, City of Savannah, at cost1$75.00$75.00
Total$8,852.40
Option, outside the total: penetrating sealer after the concrete has cured832 sq ft$0.60add $499.20

Cubic yards, waste factor and the two loads

A cubic yard is 27 cubic feet, so each element's volume is length times width times thickness in feet, divided by 27. The driveway holds 16 by 40 feet at a third of a foot, 213.3 cubic feet or 7.90 cubic yards, and the apron 16 by 12 feet at half a foot, 96 cubic feet or 3.56 cubic yards.

The waste factor covers the gap between the forms and the ticket. NRMCA notes that ready mixed concrete is sold by the volume of fresh concrete as discharged from the truck. It recommends an allowance of 4 to 10 percent over plan dimensions for waste, over-excavation and other contingencies, and advises against short loads to complete a placement (NRMCA, CIP 8, Discrepancies in Yield, revised 2016). The example uses 8 percent and rounds each load up to the next half yard.

The apron's tint and strength make it a separate mix, so the job takes two loads and the smaller one carries the supplier's short-load charge. Pouring the driveway at the apron's specification would put all 13 yards on one mix. Whether that removes the short-load charge depends on the supplier's minimum load, and it adds the higher mix price to 9 yards, so the estimate prices the two-mix version.

Savannah right-of-way rows: thickness, strength, fiber and the ADA path

The apron rows come from the city's application. Savannah's Traffic Engineering Department sets the residential standard at 6 inches thick, 5,000 psi and fiber-reinforced, from 12 to 24 feet wide. Base material in the right-of-way is compacted to 100 percent of ASTM D698 under the city's Technical Provisions (City of Savannah, Driveway Permit Application, revised December 30, 2008, checked November 2026). Where the sidewalk crosses the driveway, a 4-foot ADA path with no more than 2 percent cross-slope is required, and the adjacent sidewalk and curb slopes may be no steeper than 12:1. Concrete in the right-of-way is tinted to city specifications, and maintenance is the property owner's responsibility.

The same sheet sets site rows the estimator checks before pricing. The garage door sits at least 25 feet from the back of the sidewalk. The driveway keeps 20 feet from adjacent driveways, 3 feet from the property line or at-grade utilities, and 5 feet from the projection of any above-ground utility. Water and sewer lines are located outside the driveway, and trees in the right-of-way are protected under the city's tree ordinance. The application fee shown is $75 for a residential permit, by certified check or money order, with four working days for processing and a sketch of the location and dimensions attached. The form is dated 2008, so the fee is confirmed when the application is filed and billed at cost.

Control joints, isolation joints and saw-cut timing

The joint row follows NRMCA's guidance for slabs on grade. Maximum joint spacing is 24 to 36 times the slab thickness, about 10 feet for a 4-inch slab, and no more than 15 feet in any case. Panels are square or nearly so, with length no more than 1.5 times width. Contraction joints are cut to at least a quarter of the slab thickness and never less than 1 inch, and conventional saw cuts are made 4 to 12 hours after finishing. Isolation joints separate the slab from walls and footings and from walks and curbs at a driveway's junctions (NRMCA, CIP 6, Joints in Concrete Slabs on Grade, 2014).

Applied to the example, the 16-foot driveway takes a center joint, making two 8-foot lanes, and transverse joints at 10, 20 and 30 feet: twelve panels of 8 by 10 feet, each 1.25 times as long as it is wide. The 6-inch apron allows up to 15 feet, so its center joint and the joint at the front of the sidewalk are enough, cut 1.5 inches deep. That is 116 linear feet of saw cutting. The two pours meet at a formed construction joint on the right-of-way line, which adds the 16-foot bulkhead to the 104 feet of side forms.

Concrete estimate instructions from site visit to signature

  1. Measure each pour element, mark the right-of-way line, and photograph the existing slab, the curb, the meter box and any trees.
  2. Compute cubic feet and cubic yards for each element, apply the waste factor, and round up to the supplier's ordering increment.
  3. Set the mix for each element from the city's standard or the engineer's specification, and price each load.
  4. Decide how each pour is placed, and price the pump and any short-load charge that follows.
  5. Lay out the joints from the slab thickness and panel shape, and count the forms, saw cuts and isolation joints.
  6. Price demolition, base, placement and finish by area, and add the permit at cost.
  7. Before sending, check that the yards ordered exceed the volume by the waste factor, that every right-of-way row meets the city's standard, and that the lines add up to the total.

Concrete estimate, construction estimate and the general estimate

A concrete contractor's estimate prices one trade in its own units: yards, square feet of finish and linear feet of joints. A construction estimate template prices a building across trades, with concrete as one line among many. The general estimate template suits a single small job with a few lines and no volume table.

Estimating software and the signed concrete estimate

In FieldRanger, the estimate is built from the HubSpot deal or contact record without leaving HubSpot, or built in FieldRanger and kept tied to the deal, and PandaDoc sends it for signature. The won deal becomes a job with its context carried over, and the dispatcher drags the pour onto the calendar as one job carrying the whole placing crew.

The saw, screeds and power trowel are checked out by QR code, and the equipment availability calendar keeps two crews from booking the same saw. A job-specific checklist holds the pour's conditions: permit approved, base compacted, forms checked, joints sawn within the window. Photos of the base, the forms and the finished slab attach to the work order and sync to the customer's HubSpot record. Clocked time is logged against the job, the invoice is generated from the completed work order, and revenue reports show margin by service type. The estimating software page describes the estimate on the deal.

The yards come from the arithmetic above, and the ticket from the supplier.

Fill it in here, or download the spreadsheet

The form below is the same template: totals calculate as you type, with the spreadsheet's own formulas, and your entries stay in this browser. Download it filled in, print it or save it as a PDF, or take the blank file.

Frequently asked questions

What should a concrete estimate include?

The site, each pour element with dimensions, cubic yards with the waste factor and yards ordered, the mix, demolition, base, forms, reinforcement, placement method, finish, joints, curing, the permit, exclusions, the price and the terms.

How are cubic yards calculated for a driveway?

Multiply length by width by thickness in feet and divide by 27. A 16 by 40 foot driveway at 4 inches holds 213.3 cubic feet, or 7.90 cubic yards.

How much extra concrete should be ordered?

NRMCA recommends an allowance of 4 to 10 percent over plan dimensions for waste, over-excavation and other contingencies. The example orders 8 percent over and rounds up to the next half yard.

How far apart should control joints be in a concrete driveway?

NRMCA's guidance sets maximum spacing at 24 to 36 times the slab thickness, about 10 feet for a 4-inch slab and no more than 15 feet, with panels no longer than 1.5 times their width.

What does Savannah require for a residential driveway apron?

The city's driveway permit application calls for 6-inch, 5,000 psi, fiber-reinforced concrete, 12 to 24 feet wide, base compacted to 100 percent of ASTM D698, a 4-foot ADA path at no more than 2 percent cross-slope, and tinted concrete in the right-of-way.

When does a concrete estimate need a pump line?

When the truck's chute cannot reach the forms. In the example, the far end of the driveway sits 52 feet from the curb, so the driveway pour is priced with a line pump and the apron by chute.

Pour day for estimate CN-2026-0512

The Whitfields' job turns into two trucks on one morning: 4 yards of tinted apron mix by chute, then 9 yards of driveway mix through the line pump, with the saw on site before the first finish is dry. The pour's invoice has its own form in the free field service templates hub. FieldRanger is priced per technician on pricing, and Start free trial lasts 14 days with no card.