General Contractor Invoice Template:Draw Request, Retainage, Change Order Markup and Utah Lien Waivers
General contractor invoice template for a progress draw: schedule of values, retainage, change orders with markup and Utah lien waivers, filled for Ogden.
A general contractor invoice template is the bill a general contractor sends the owner at each draw: the contract sum, approved change orders, a schedule of values with work completed to date, retainage withheld, earlier payments, the amount due and the lien waivers that go with the payment. The example fills every field for draw 4 on a commercial building.
The field list is one of the free field service templates kept by FieldRanger, the general contractor software that runs inside HubSpot. The construction invoice template sets out the pay application line by line. This page adds what the general contractor carries around it: markup on change orders, the subcontractor waivers collected before payment, and retainage under a state cap.
General contractor invoice fields: draw, schedule of values, retainage and waivers
| Part | Field | What goes in it |
|---|---|---|
| Header | General contractor | Business name, address, telephone and state contractor license number |
| Header | Owner and lender | The owner billed and, on a financed project, the construction lender that funds the draw |
| Header | Project | Project name, site address and parcel or legal description |
| Header | Contract | Contract type, number, date and the retainage rate it sets |
| Header | Draw number and period | The draw's sequence number and the dates of work it covers |
| Header | Invoice date and due date | The date submitted and the payment date the contract sets |
| Summary | Original contract sum | The price in the signed contract |
| Summary | Approved change orders | The net of executed change orders, additions less deductions |
| Summary | Contract sum to date | Original contract sum plus approved change orders |
| Summary | Completed and stored to date | The total of the schedule of values, including materials stored on site |
| Summary | Retainage | The rate and the amount withheld on everything completed and stored to date |
| Summary | Earned less retainage | Completed and stored to date, less retainage |
| Summary | Previous draws | The amounts certified on earlier draws |
| Summary | Amount due this draw | Earned less retainage, less previous draws |
| Summary | Balance to finish | Contract sum to date less earned less retainage, so retainage still owed is included |
| Schedule of values | Line items | Each portion of the work with its scheduled value, previous billing, this period, stored materials, total, percent and balance |
| Change orders | Change order log | Number, description, cost, markup, amount, the date each was signed, and pending changes listed without an amount billed |
| Waivers | Lien waiver log | Each claimant, the form signed, the payment period and the payment amount |
| Sign-off | Certification | The general contractor's signature, and the owner's or lender's approval where the contract requires it |
Filled general contractor invoice: draw 4 on an equipment showroom and shop in Ogden, Utah
The project is a 7,200 square foot pre-engineered metal building: a 1,800 square foot showroom and office and a 5,400 square foot service shop, built for an equipment dealer on a stipulated-sum contract. The business, owner, lender and figures are illustrative. The retainage and waiver entries follow the Utah Code sections cited below.
| Field | Example entry |
|---|---|
| General contractor | Example Builders Inc., 300 Example Avenue, Ogden, UT 84401 · 801-555-0172 · contractor license 0000000-5501 (example) |
| Owner and lender | Example Equipment Holdings LLC · construction loan with Example Bank, draw inspection required |
| Project | Showroom and service shop, 4400 Example Drive, Ogden, UT 84405 · parcel 00-000-0000 (example) |
| Contract | Stipulated sum, contract EB-26-014, dated May 4, 2026 · retainage 5% |
| Draw number and period | Draw 4 · October 1 to October 31, 2026 |
| Invoice date and due date | November 5, 2026 · due 15 days after the lender's inspection, under the contract |
| Certification | Signed by the general contractor's project manager; approved by the owner and the lender's inspector |
| Line | Description | Scheduled value | Previous | This period | Stored | Total to date | % | Balance |
|---|---|---|---|---|---|---|---|---|
| 1 | General conditions | $96,000 | $38,400 | $12,000 | $0 | $50,400 | 53% | $45,600 |
| 2 | Site work and utilities | $142,000 | $142,000 | $0 | $0 | $142,000 | 100% | $0 |
| 3 | Concrete footings and slab | $168,000 | $151,200 | $16,800 | $0 | $168,000 | 100% | $0 |
| 4 | Metal building, supply and erection | $312,000 | $249,600 | $62,400 | $0 | $312,000 | 100% | $0 |
| 5 | Overhead doors | $48,000 | $0 | $0 | $33,600 | $33,600 | 70% | $14,400 |
| 6 | Plumbing | $74,000 | $22,200 | $22,200 | $0 | $44,400 | 60% | $29,600 |
| 7 | HVAC | $88,000 | $17,600 | $35,200 | $0 | $52,800 | 60% | $35,200 |
| 8 | Electrical | $121,000 | $36,300 | $36,300 | $0 | $72,600 | 60% | $48,400 |
| 9 | Office finishes | $84,000 | $0 | $16,800 | $0 | $16,800 | 20% | $67,200 |
| 10 | Paving and striping | $53,000 | $0 | $0 | $0 | $0 | 0% | $53,000 |
| CO-1 | Rock excavation at the north footings | $10,340 | $10,340 | $0 | $0 | $10,340 | 100% | $0 |
| CO-2 | Added 14 x 16 ft overhead door, east wall | $12,980 | $0 | $5,192 | $0 | $5,192 | 40% | $7,788 |
| Totals | $1,209,320 | $667,640 | $206,892 | $33,600 | $908,132 | 75% | $301,188 |
| Line | Amount |
|---|---|
| Original contract sum | $1,186,000.00 |
| Approved change orders | $23,320.00 |
| Contract sum to date | $1,209,320.00 |
| Completed and stored to date | $908,132.00 |
| Retainage, 5% of completed and stored | $45,406.60 |
| Earned less retainage | $862,725.40 |
| Less previous draws | $634,258.00 |
| Amount due this draw | $228,467.40 |
| Balance to finish, including retainage | $346,594.60 |
| Change order | Description | Cost | Markup, 10% | Amount | Status |
|---|---|---|---|---|---|
| CO-1 | Rock excavation and disposal at the north footing line | $9,400.00 | $940.00 | $10,340.00 | Signed August 12, 2026; billed on draw 3 |
| CO-2 | Added overhead door: framed opening, door and operator | $11,800.00 | $1,180.00 | $12,980.00 | Signed October 6, 2026; 40% billed on draw 4 |
| CO-3 | Epoxy floor coating in the showroom, requested by the owner | $8,600.00 | $860.00 | $9,460.00 | Pending; not billed |
| Claimant | Form | Payment period | Payment amount |
|---|---|---|---|
| Example Builders Inc., general contractor | Utah Conditional Waiver and Release Upon Progress Payment | October 1 to 31, 2026 | $228,467.40 |
| Metal building erector | Same form, from its own payment | October 1 to 31, 2026 | $56,430.00 |
| Concrete subcontractor | Same form | October 1 to 31, 2026 | $15,180.00 |
| Plumbing subcontractor | Same form | October 1 to 31, 2026 | $20,045.00 |
| HVAC subcontractor | Same form | October 1 to 31, 2026 | $31,825.00 |
| Electrical subcontractor | Same form | October 1 to 31, 2026 | $32,785.00 |
The arithmetic closes both ways. This period plus stored materials is $240,492.00, and 95 percent of it is the $228,467.40 due. Draws 1 to 3 billed $667,640.00, certified at 95 percent as $634,258.00.
Utah retention limits in the draw 4 summary
Utah caps retention at 5 percent. Under Utah Code section 13-8-5, retention withheld from any payment may not exceed 5 percent of that payment. The total withheld may not exceed 5 percent of the total construction price (Utah Code 13-8-5, effective February 27, 2023, checked November 2026). The section covers contracts entered into on or after July 1, 1999, from the owner down through each tier of subcontractor. Its definition of a construction contract is written for nonresidential commercial or industrial projects; a mixed project is covered only for its nonresidential share of floor area. A version amended in the 2026 General Session takes effect January 1, 2027 and keeps both limits (Utah Code 13-8-5, effective January 1, 2027).
Draw 4 sits inside both limits. The $45,406.60 withheld is 5 percent of the work completed and stored, and 3.75 percent of the $1,209,320.00 contract sum to date.
The same section governs the money once it is withheld. The owner places it in an interest-bearing account, accounted for separately and held in trust for the contractors who earned it. It is released, with interest, within 45 days of the later of the owner's receipt of the contractor's billing statement and the certificate of occupancy or final acceptance. Occupancy permitted without a certificate, and the contractor's acceptance of final pay quantities, are also triggers. That billing statement must include documentation of lien releases or waivers. The general contractor pays each subcontractor its share within 10 days of receiving it. Retention knowingly and wrongfully withheld carries a charge of 2 percent per month.
Utah lien waiver forms attached to the draw
Utah writes the waiver forms into statute. A waiver of lien rights is enforceable only if it is signed and the claimant receives the payment it names, and a progress waiver reaches only that payment. A waiver given for a check that fails to clear is void (Utah Code 38-1a-802, checked November 2026). A waiver qualifies when it is in substantially the statutory form for its circumstance.
The progress form is the "Utah Conditional Waiver and Release Upon Progress Payment". Its blanks match the invoice header: property name and location, the undersigned's customer, the invoice or payment application number, the payment amount and the payment period. It takes effect once the claimant endorses a check in the payment amount and the check is paid. It does not reach retention, items pending approval, disputed items, or work invoiced after the payment period, so CO-3 and the $45,406.60 of retention stay outside every waiver in the log. At closeout, each claimant signs the "Utah Waiver and Release Upon Final Payment" instead.
The log holds six waivers for one draw: the general contractor's own and one from each subcontractor paid from it. The lender's inspector reads it before releasing funds, since a subcontractor without a waiver keeps its lien rights against the building.
Change order markup and pending changes
A change order enters the contract sum when both parties sign it, and the invoice then bills it like any other line. Its amount is the subcontractor's price plus the general contractor's markup, 10 percent under the example contract: CO-2's $11,800.00 of cost and $1,180.00 of markup make the $12,980.00 line, 40 percent of it billed this period.
A pending change is logged and not billed. CO-3 waits at $9,460.00 with no schedule of values line until the owner signs it. Billed early, it would put an amount on the invoice that the contract does not yet contain.
General contractor invoice instructions for each draw
- Collect each subcontractor's pay application for the period, with its signed conditional waiver for its own payment.
- Enter the original contract sum and each signed change order at cost plus the contract markup; list unsigned changes as pending.
- On each schedule of values line, carry the previous total forward, then enter this period's work and any materials stored on site.
- Total each line and compute its percent and balance.
- Apply the contract retainage rate to the total completed and stored, and check it against the state cap on each payment and on the total price.
- Subtract the previous draws to reach the amount due, then fill the general contractor's own conditional waiver with that amount and period.
- Sign the invoice, attach the waiver log and the waivers, and send it to the owner and the lender.
- Before sending, confirm that the previous column equals the last draw's total, that no line exceeds 100 percent, and that every subcontractor paid on the last draw has a waiver in the log.
Progress billing software and the FieldRanger invoice
FieldRanger does not do progress billing or retainage. It generates the invoice from the completed work order, and invoices and payments sync with QuickBooks. A general contractor billing monthly draws keeps them in construction billing software, or in a spreadsheet laid out like the tables above.
FieldRanger fits the jobs around a general contractor that are billed on completion: warranty calls, service work and small projects. The estimate is built from the HubSpot deal or in FieldRanger and kept tied to the deal, and PandaDoc sends estimates and agreements for signature. A deposit invoice can go out before a small project starts, with the balance invoiced on completion. A won deal becomes a job with its context carried over, and job status shows on the deal record. Time is logged against each job, and revenue reports show job revenue and margin by customer or service type. The contractor invoicing software page sets out the FieldRanger invoice and its limits.
Fill it in here, or download the spreadsheet
The form below is the same template: totals calculate as you type, with the spreadsheet's own formulas, and your entries stay in this browser. Download it filled in, print it or save it as a PDF, or take the blank file.
Frequently asked questions
What should a general contractor invoice include?
The contractor, owner, project and contract; the draw number and period; the original contract sum, approved change orders and contract sum to date; a schedule of values; retainage; previous draws; the amount due; the balance to finish; a change order log; and the lien waivers for the payment.
How is retainage calculated on a general contractor invoice?
Multiply the total completed and stored to date by the contract rate. In the example, 5 percent of $908,132.00 is $45,406.60, which is subtracted before previous draws to reach the amount due.
What is the maximum retainage in Utah?
Under Utah Code 13-8-5, retention may not exceed 5 percent of any payment or 5 percent of the total construction price, on construction contracts entered into on or after July 1, 1999. The owner holds it in an interest-bearing account.
Which lien waiver goes with a progress payment in Utah?
The Utah Conditional Waiver and Release Upon Progress Payment, in substantially the form in Utah Code 38-1a-802. It takes effect once the check for the payment amount is endorsed and paid, and it excludes retention, pending changes and disputed items.
How are change orders billed on a general contractor invoice?
Each signed change order is added to the contract sum at cost plus the contract markup and billed by percent complete on its own schedule of values line. Unsigned changes stay in the log as pending, with nothing billed.
Does FieldRanger do progress billing for general contractors?
No. FieldRanger generates invoices from completed work orders and has no progress billing or retainage, so monthly draws stay in construction billing software or a spreadsheet.
The $45,406.60 held back after draw 4
The Ogden building now carries $45,406.60 of retention in an interest-bearing account and $301,188.00 of work still to bill, led by office finishes and paving. Retention moves last, on a billing statement that carries every claimant's final waiver. The warranty calls that follow handover are the part FieldRanger invoices. Their forms are in the free field service templates hub, and FieldRanger pricing sets the per-technician cost of running them, with Start free trial for 14 days and no card.