Excavation Estimating Software:Excavation and Site Work Estimates in FieldRanger and HubSpot
Excavation estimating software on HubSpot: unit-price bids by cubic yard and machine hour, shrink factors, trench safety and locate lines in FieldRanger.
Excavation estimating software prices earthwork from its quantities: bank cubic yards dug, compacted yards placed, loads hauled, linear feet of protected trench and the machine hours behind each line. FieldRanger holds that estimate on the HubSpot deal or in FieldRanger, then logs the hours, loads and materials the crew spends.
In excavation software, estimating is the step between takeoff and bidding. Takeoff measures the quantities from plans or a site survey. Estimating prices those quantities with machine, labor, haul and disposal costs. Bidding packages the prices into the form the owner asked for, whether a lump sum, a schedule of unit prices or hourly rates. FieldRanger does the second step and the record after it; the takeoff comes from a separate product or a tape and a level on site.
Unit-price bids and machine-hour rates
Excavation work is sold in two structures. A unit-price bid names a price per unit of work, such as a bank cubic yard excavated, a linear foot of trench or a compacted yard of fill, and the owner pays for the measured quantity. A machine-hour bid, also called time and equipment, names a rate for each machine with its operator, and the owner pays for the hours worked. Unit prices put the production risk on the contractor; hourly rates put it on the owner.
Both structures rest on the cost of a machine hour. FEMA publishes hourly equipment rates in its 2025 Schedule of Equipment Rates, which applies to disasters declared on or after July 1, 2025; it lists a Caterpillar 320 GC excavator at $107.93 an hour, a Bobcat S76 skid steer at $45.23, a 47-inch vibratory drum compactor at $39.01 and a 12-cubic-yard dump truck at $120.74 (FEMA, 2025 Schedule of Equipment Rates, September 2025). Labor comes from the operator's wage. BLS puts the May 2025 median at $28.78 an hour for operating engineers and other construction equipment operators, $28.19 for heavy and tractor-trailer truck drivers and $22.66 for construction laborers (BLS, Occupational Employment and Wages, May 2025, released May 15, 2026).
An excavator hour with its operator therefore costs $136.71 at those rates before overhead and profit. Divided by a production rate in bank cubic yards per hour, the same figure becomes a unit price. The production rate is the contractor's own number, taken from past jobs with the same machine, soil and depth, and it is where a unit-price bid carries its risk.
Bank, loose and compacted yards: swell and shrink factors
One cubic yard of soil has three volumes. A bank cubic yard is the soil as it lies before digging. A loose yard is the same soil in the truck, larger because digging breaks it up. A compacted yard is the soil after it is placed and rolled in a fill. An excavation estimate that mixes the three on one line prices the wrong quantity.
State highway manuals convert between them with compaction factors. The Wyoming Department of Transportation's design manual states that a soil-type material with a 20 percent shrink gives a compaction factor of 1.2, applied as "Fill Volume × 1.2 = Cut Volume". A rock-type material with a 10 percent swell gives a factor of 0.9, applied as "Fill Volume × 0.9 = Cut Volume". The same section warns that a project with several sliver cuts and fills "could require a compaction factor of 1.5± verses a laboratory determined factor of 1.2±" (WYDOT Road Design Manual, Section 3-03 Earthwork Design.pdf), August 2011). The factors themselves come from the soils report for the site.
The factor sets the haul lines. A pad that needs 300 compacted yards of soil fill needs 360 bank yards cut at a factor of 1.2, so the borrow line is priced on 360. A trench whose spoil returns as compacted backfill leaves only the bank yards the backfill does not consume for the haul-off line.
Trench safety and the Texas pay item
Trench protection is a line of its own, and in Texas the statute says so for public work. On a project for a political subdivision "in which trench excavation will exceed a depth of five feet", the bid documents and the contract must include a reference to the OSHA trench safety standards in effect during construction, any special shoring requirements, any geotechnical information the owner obtained, and "a separate pay item for trench excavation safety protection". That pay item "must be based on the linear feet of trench excavated", and special shoring is paid on "the square feet of shoring used" (Tex. Health & Safety Code §756.023, amended effective September 1, 1999).
The unit follows the work. A trench box is set and moved along the run, so its cost accrues per foot advanced: the box rental for the days on site plus the machine and crew time spent setting and pulling it, divided by the linear feet excavated. Private work carries the same cost whether or not the owner's form names it, and an estimate that buries it in the cubic-yard price cannot show the owner what the protection costs. The protective system required for each depth is set by OSHA's excavation standard, 29 CFR 1926.652, which the trench checklist on the job then records.
Utility locates as estimate lines
The locate is free; the work around it is not. Texas requires an excavator to notify the one-call notification center "not earlier than the 14th day before the date the excavation is to begin or later than the 48th hour before", excluding Saturdays, Sundays and legal holidays (Tex. Util. Code §251.151, added effective September 1, 1999). The City of Grand Prairie states that Texas 811 "does not charge for locating any utility lines", and also that neither 811 nor the city "can mark buried lines that belong to a property owner"; it directs owners to a commercial line-locating firm or a licensed plumber for those (City of Grand Prairie, call before you dig, checked November 12, 2026).
That gives the estimate three locate lines. The private locate is a subcontractor's quote. Potholing to expose a crossing is priced by the hour: FEMA lists a hydro-excavation vacuum truck at $99.66 an hour. Re-notice is a contingency: under the 14-day wording, a dig date that slips past the window needs a new notice and a new wait. In FieldRanger the ticket number goes on the job's checklist and the dig date goes on the calendar inside the statutory window; FieldRanger has no connection to Texas 811, so the office files each ticket.
A costed trench bid from published rates
The sample prices a 240-foot storm drain trench, 3 feet wide and 6 feet deep, for a Texas municipal utility district. The dimensions, the machine hours and the 40 yards taken by pipe and bedding are sample inputs. The equipment rates are FEMA's 2025 schedule, the wages are BLS medians for May 2025, and the compaction factor is WYDOT's 1.2 for soil.
| Bid line | Quantity | Basis | Direct cost | Unit cost |
|---|---|---|---|---|
| Trench excavation | 160 bank yd³ (240 × 3 × 6 ÷ 27) | Excavator 14 h × ($107.93 + $28.78) | $1,913.94 | $11.96 per bank yd³ |
| Backfill and compaction | 120 compacted yd³ (160 less 40 for pipe and bedding) | Skid steer and operator 8 h × ($45.23 + $28.78); roller and laborer 8 h × ($39.01 + $22.66) | $1,085.44 | $9.05 per compacted yd³ |
| Spoil haul-off | 16 bank yd³ (160 less 120 × 1.2) | Dump truck and driver 3 h × ($120.74 + $28.19) | $446.79 | $27.92 per bank yd³, before the receiving site's fee |
| Potholing at crossings | Lump sum | Vacuum truck and operator 4 h × ($99.66 + $28.78) | $513.76 | Lump sum |
| Trench excavation safety protection | 240 linear feet | Box rental and setting time, from the contractor's rental quote | Quote | Per linear foot, as §756.023 requires |
| One-call ticket | 1 | Texas 811 | $0.00 | No charge |
The four priced lines total $3,959.93 in direct cost before the trench box, the pipe and bedding material, overhead and profit. The table shows where the price is fragile. The haul-off line rests on the compaction factor: at the 1.5 WYDOT gives for sliver work, 120 compacted yards would consume 180 bank yards, more than the trench produced, and the line would change from haul-off to import. The excavation line rests on the 14 hours, which come from the contractor's own production history.
From bid to job in HubSpot and FieldRanger
- The utility district's request arrives as a HubSpot deal on the district's company record, with its engineer as a contact.
- Quantities come from the plans through a takeoff product; site photos of the route, the crossings and the access attach to the record.
- The estimate is built from the HubSpot deal or contact record without leaving HubSpot, or in FieldRanger, where it stays tied to the deal, with each pay item as its own line.
- PandaDoc sends the proposal for signature, and the won deal becomes a job with its context carried over.
- The office files the locate, and the dispatcher dates the dig inside the notice window.
- The excavator, the skid steer and the trench box are booked on the equipment availability calendar and checked out by QR code at the yard.
- Operators clock in with their location recorded, the competent person completes the trench checklist each morning, and bedding stone is logged as material, with scale tickets photographed onto the work order.
- The completed work order generates the invoice, the district pays by card through Stripe or on terms, and QuickBooks receives both the invoice and the payment.
Job completions, notes and photos are logged to the HubSpot timeline, and the job status shows on the deal for the district's engineer. General contractors who price a whole building, with sitework as one division among many, are covered on construction estimating software.
Estimated hours and yards against the job record
The bid is tested by the job. FieldRanger records each operator's hours against the job through geo-location time tracking, logs materials used for job costing, and holds the scale and load tickets as photos on the work order. Revenue reports then set each job's revenue against those costs, by customer or by service type, which shows whether trench work for one district earns what pad work for a builder does.
The comparison corrects the next bid. When trench excavation in clay logs more hours than the estimate carried, the production rate on the next clay trench falls and its unit price rises. When pad haul-off keeps exceeding the estimate, the next pad's compaction factor moves toward the field value.
Excavation bidding software, takeoff tools and free options
Excavation bidding software assembles a bid package: the owner's bid form, a unit-price schedule, alternates and sometimes the electronic submission. Takeoff software measures cut, fill and trench quantities from plans or surfaces. FieldRanger does neither. A contractor bidding public work every week from plans is better served by a dedicated bidding product; FieldRanger suits the contractor whose jobs are measured on site and sold through HubSpot.
Free excavation estimating software takes the form of spreadsheets and calculators. The inputs above are free as well: FEMA's equipment schedule, the BLS wage tables and a state DOT's earthwork section can be read by anyone. A spreadsheet, though, keeps no link to the customer, the crew calendar or the hours logged on the job. A FieldRanger trial runs 14 days without a card.
Excavation estimating limits in FieldRanger
- No quantity takeoff from plans, surfaces or drone data.
- No conversion between bank, loose and compacted yards; the estimator applies the factor.
- No unit cost database and no equipment rate feed; rates come from the contractor's own records.
- No bid-form import or electronic bid submission.
- No connection to 811 one-call centers and no hour-meter feed from machines.
- No progress billing against a contract value; each invoice comes from a completed work order, which suits a trench finished in days rather than a site package billed monthly.
Frequently asked questions
What is excavation estimating software?
Software that prices earthwork from its quantities: bank cubic yards excavated, compacted yards placed, loads hauled and linear feet of protected trench, with the machine and labor hours behind each line. FieldRanger holds the estimate on the HubSpot deal or in FieldRanger and logs the hours the crew spends.
What is the difference between excavation estimating software and excavation bidding software?
Estimating software prices the quantities. Bidding software assembles the result into the owner's bid form and submission. FieldRanger covers the estimate and the job after it, not takeoff or bid forms.
How are swell and shrink factors applied in an excavation estimate?
Through a compaction factor between bank and compacted volume. Wyoming DOT's manual gives 1.2 for a soil with a 20 percent shrink, so 300 compacted yards of fill need 360 bank yards cut, and 0.9 for a rock with a 10 percent swell.
How is an excavator hour priced?
As the machine's hourly cost plus its operator. At FEMA's 2025 rate for a Caterpillar 320 GC, $107.93, and the BLS May 2025 median for equipment operators, $28.78, the hour costs $136.71 before overhead and profit.
Is trench safety a separate line item in an excavation bid?
In Texas it must be on public work. Health and Safety Code §756.023 requires a separate pay item for trench excavation safety protection, based on linear feet of trench, on political subdivision projects with trenches deeper than five feet.
Is there free excavation estimating software?
Spreadsheets and calculators cost nothing, and the public inputs, such as FEMA's equipment rates and BLS wages, are free to read. FieldRanger is not free; its trial runs 14 days with no card.
How much does excavation estimating software cost?
FieldRanger is priced per technician, with the plans on the pricing page.
A trench bid stands on four numbers that can be checked later: the bank yards, the compaction factor, the machine hours and the linear feet under a box. FieldRanger sets the estimate on the district's HubSpot deal and the logged hours, tickets and loads on the job beside it, so the next bid starts from the last one's result. Crews, locates and machines on the job are covered under excavation software, whole-building bids under construction estimating software, and pricing lists the per-technician plans and a 14-day Start free trial with no card.