Template

Contractor Work Order Template:Scope, Materials, Change Orders, Sign-Off and Minnesota Contract Terms in a Duluth Door Replacement

Contractor work order template with scope, materials, change order and sign-off fields, checked against Minnesota contract law on a Duluth door replacement.

Updated 12 min read

Download .xlsxExcel spreadsheet · 17 KB · Free, no sign-upFill it in online

A contractor work order template is the job sheet a remodeler sends to the site for one day: the signed contract's scope, the materials and their specification, the price basis, any change order written on site with its price and signatures, and the customer's sign-off. The sample further down completes each field for a door replacement in Duluth, Minnesota.

FieldRanger, which makes field service software that runs inside HubSpot, publishes this form with its other free field service templates, with no sign-up in front of it. The page offers the form as a free .xlsx download: a Template sheet with every field and a Sample sheet with the filled work order. In a Word or Google Docs form, each row becomes a labeled box.

Contractor work order fields: scope, materials, change orders and sign-off

Every row below is a field on the form. The office fills the contract rows before the visit. The assigned carpenter fills the site rows, and the customer signs the change order and the completion block.

Contractor work order template fields by section, with the person responsible and the expected entry
SectionFieldFilled byWhat goes in it
HeaderContractor and licenseOfficeBusiness name, address, phone, and the license statement and number where the state requires one
HeaderWork order numberOfficeThe next number in the company's work order series, repeated on the invoice
HeaderContract referenceOfficeProposal or contract number and the date the customer signed it
HeaderCustomer and propertyOfficeOwner's name, property address and the contact for the day
HeaderAccess and site rulesOfficeEntry, parking, pets, work hours, protected areas and where debris goes
HeaderPermit and inspectionOfficePermit number and any inspection the work must stop for, or the scope decision that none applies
ScopeScope summaryOfficeThe work as the contract describes it, step by step, in the contract's words
ScopeExclusionsOfficeWork the contract leaves out, written so the carpenter can refuse it on site
ScopeMaterials and specificationOfficeEach material by size, type, brand or model where the contract names one, with quantity
ScopePrice basisOfficeFixed price, or the hourly rate and material markup that a time-and-materials job bills from
VisitAssigned carpenterOfficeThe person responsible for the day's work
VisitDate and arrival windowOfficeThe day booked and the window promised to the customer
VisitArrival and departureCarpenterTimes on and off site
SiteConditions foundCarpenterWhat opening the work revealed that the contract did not anticipate, with photo numbers
SiteWork performedCarpenterEach scope step marked done, with any deviation explained
SiteMaterials usedCarpenterWhat was installed, in what quantity, and where it came from
Change orderChange order number and descriptionCarpenter, officeThe added or removed work, its materials and the reason for it
Change orderPrice and schedule changeOfficeThe amount added or credited, the revised contract price and any change to the finish time
Change orderSignatures and copyCustomer, contractorBoth signatures with date and time, and how the customer's copy was delivered
CompletionOpen itemsCarpenterPunch items left and who owns each
CompletionCleanup and disposalCarpenterDebris removed or left, and the old materials hauled away
CompletionCustomer sign-offCustomerName in capitals, signature, date and time, accepting the work order and every change order on it
CompletionContractor signatureCarpenterName and signature of the person who did the work

A work order template for service calls carries equipment, readings and a fault in the customer's words. The contractor version carries the contract instead: what was sold, what it excludes, what it costs and what changed. The price basis row decides how a change order is priced, so it is filled before anyone opens a wall.

Minnesota contract terms that reach the work order

Minnesota sets out what a residential contractor's paperwork must say, and three statutes land on the work order. Section 326B.809 requires that "all agreements including proposals, estimates, bids, quotations, contracts, purchase orders, and change orders" between a licensee and a customer be in writing, with three contents (Minn. Stat. 326B.809, 2026 Minnesota Statutes). The same section requires written performance guidelines before the agreement, signatures and dates from both parties, and a signed copy for the customer at no charge.

Minnesota requirements and the work order field that carries each (2026 Minnesota Statutes, checked November 2026)
RequirementSourceWork order field
"A detailed summary of the services to be performed"326B.809(a)(1)Scope summary, and the description line of each change order
"A description of the specific materials to be used or a list of standard features to be included"326B.809(a)(2)Materials and specification
"The total contract price or a description of the basis on which the price will be calculated"326B.809(a)(3)Price basis, and the price line of each change order
Written performance guidelines given before the agreement and included or incorporated by reference326B.809(b)Contract reference
"All agreements shall be signed and dated by the licensee and customer"326B.809(b)Change order signatures
A signed and dated copy to the customer, at no charge, when signed326B.809(c)Change order copy delivered
Contracts must "state that the person is licensed and must state the license number"[326B.87, subd. 3](https://www.revisor.mn.gov/statutes/cite/326B.87)Contractor and license
Pre-lien notice in the written contract, in at least 10-point bold type[514.011, subd. 1](https://www.revisor.mn.gov/statutes/cite/514.011)Contract reference

The work order is not on the statute's list of agreements. A change order is, and a change order written on the work order brings all three contents and both signatures with it. The pre-lien notice belongs in the contract, and a contractor who fails to give it loses the lien remedy of chapter 514 for that job; the work order records only which document carried it.

Filled contractor work order: rear entry door replacement in Duluth, Minnesota

The job replaces a rear entry door at a 1920s house in one day. The business, the customer, the prices and the decay found under the threshold are samples; the statutory rows follow the table above.

Filled contractor work order, header and scope (sample business, customer and prices)
FieldSample entry
Contractor and licenseExample North Shore Remodeling LLC, 2200 Example Street, Duluth, MN 55812 · 218-555-0144 · Licensed by the Minnesota Department of Labor and Industry, license 000000 (example)
Work order numberWO-2026-0731
Contract referenceProposal P-2026-118, signed October 28, 2026 · performance guidelines incorporated by reference · pre-lien notice in section 8 of the proposal
Customer and propertyErik and Lena Halvorsen, 1418 Example Avenue East, Duluth, MN 55812 · Erik Halvorsen home all day, 218-555-0190
Access and site rulesSide gate; dog kept upstairs; drop cloths from the door to the kitchen; dumpster not permitted, debris to the trailer
Permit and inspectionDecided at proposal stage and noted in P-2026-118
Scope summary1. Remove the existing 36 x 80 in. wood door, frame and threshold · 2. Install a sill pan · 3. Set, shim and fasten the new prehung unit · 4. Flash the exterior with self-adhered tape and seal · 5. Foam the gap and install interior casing · 6. Adjust the strike and weatherstrip · 7. Haul away the old unit
ExclusionsPainting or staining; storm door; any framing repair below or beside the rough opening, which is priced by change order
Materials and specificationPrehung fiberglass entry door, 36 x 80 in., 4-9/16 in. jamb, left-hand inswing, 1 · sill pan, 1 · 4 in. self-adhered flashing tape, 1 roll · low-expansion window and door foam, 2 cans · exterior sealant, 1 tube · primed casing, 2 pieces · fasteners
Price basisFixed price $1,797: materials $772, labor $980, disposal $45 · change orders at $95 per hour plus materials at cost
Assigned carpenterSam Okafor, lead carpenter
Date and arrival windowNovember 10, 2026 · 7:30 to 8:00 AM
Filled contractor work order, site record and change order (sample times and prices)
FieldSample entry
Arrival and departure7:40 AM to 5:55 PM
Conditions foundAt 9:10 AM, with the threshold out: sill plate soft for 38 in. under the opening; rim joist face decayed about 1/2 in. deep across the same length · photos P3 to P5
Change order number and descriptionCO-1: cut out 40 in. of decayed sill plate and rim joist face; install a pressure-treated 2x6 sill section and a sistered 2x8 rim section; patch the subfloor 6 x 40 in. with 3/4 in. plywood · materials: PT 2x6 8 ft, PT 2x8 8 ft, half sheet of 3/4 in. plywood, structural screws, construction adhesive · reason: decay hidden under the threshold, outside the scope
Price and schedule changeLabor 3.0 h at $95 = $285 · materials at cost $88 · CO-1 total $373 · revised contract price $2,170 · finish moved from 3:00 PM to 6:00 PM, same day
Signatures and copyErik Halvorsen, November 10, 2026, 9:42 AM · Sam Okafor for the contractor, 9:44 AM · signed copy emailed to the customer at 9:45 AM, no charge
Work performedSteps 1 to 7 done; CO-1 done before step 2 · sill pan set on the new sill section
Materials usedAll contract materials installed · CO-1 lumber and plywood from the shop rack; screws and adhesive from van stock
Open itemsInterior casing left primed for the owner to paint, per the exclusions
Cleanup and disposalOld door, frame and cut-out lumber to the trailer; floor vacuumed
Customer sign-offErik Halvorsen, 5:50 PM: "Work complete as described in WO-2026-0731 and CO-1"
Contractor signatureSam Okafor, 5:52 PM

Anyone can redo the change order arithmetic. Three hours at $95 is $285; $285 plus $88 in materials is $373; $1,797 plus $373 is the $2,170 that goes to the invoice. The signature time matters as much as the sum: CO-1 was signed at 9:42 AM, and the sill pan, step 2, went in after it. A change order signed after the work is done records a dispute rather than preventing one.

Change orders priced from the contract's own basis

The price basis row exists so that a change order on site is arithmetic rather than a negotiation. The Halvorsen proposal set $95 per hour and materials at cost for changes, so the carpenter could price CO-1 in the driveway and the customer could check it before signing.

Three things decide whether a change order holds up later. It names the work in enough detail that a stranger could tell what was added. It names the materials, because Minnesota requires that of every agreement, change orders included. It carries both signatures with a date, and the customer keeps a copy. A verbal approval at the door, written up afterwards, meets none of those at the moment the work was done.

A change order can also take work out. A credit for an excluded item, or for a material the customer supplies, is written the same way with a negative amount, and the revised contract price falls.

Contractor work order instructions from signed contract to final signature

  1. Copy the license statement, contract reference, customer and access rows from the signed proposal, and confirm the pre-lien notice and performance guidelines went with it.
  2. Copy the scope summary, exclusions, materials and price basis word for word from the proposal, so the carpenter works from the contract and not from memory.
  3. Assign the carpenter, set the date and window, and check that every listed material is on the van or at the shop.
  4. On site, the carpenter records arrival, then photographs and describes any condition the contract did not anticipate before touching it.
  5. Write a change order for any added or removed work: description, materials, price from the contract's basis, the revised contract price and the new finish time.
  6. Collect both signatures with the time, give the customer a copy, and only then start the changed work.
  7. Mark each scope step done, record materials used and their source, and note open items and cleanup.
  8. Collect the customer's sign-off and the carpenter's signature, then check that the revised price equals the contract price plus every change order, and that each change order was signed before its work began.

Estimate, contract, work order and change order on one remodel

Four documents follow a remodeling job. The estimate prices the work for a decision. The signed contract or proposal turns the estimate into an agreement, with the performance guidelines and the lien notice. The work order takes that agreement to the site for one day. The change order amends the agreement when the site disagrees with the plan, and the invoice bills the contract price plus every change order.

The same structure serves repeat work differently. A maintenance work order template is generated from a schedule against an asset, so it carries a task list and a trigger rather than a contract and its exclusions.

Work order software for remodeling contractors

A paper work order and change order reach the office when the carpenter does, and the revised contract price waits there until someone retypes it into the invoice.

In FieldRanger, an estimate is built from the HubSpot deal or contact record, or in FieldRanger and tied to the deal, and PandaDoc sends estimates and agreements for signature, a change order included. A won HubSpot deal becomes a job with its context carried over. Digital work orders put the job details, customer information and instructions on the assigned technician's phone; photo documentation attaches before and after photos to the work order, materials tracking logs parts and materials used on each job, the carpenter's van can be its own stock location, and job-level time tracking logs time against the job. A deposit invoice can go out at signing, the balance is invoiced from the completed work order, and invoices and payments sync with QuickBooks. The work order software page sets out how a FieldRanger work order is laid out.

Two limits apply to remodeling. FieldRanger does not do progress billing or retainage, so a draw schedule on a larger job stays in the accounting system. Each day is its own job: a change order that pushed this door into a second day would mean a second work order on the next day's job.

Fill it in here, or download the spreadsheet

The form below is the same template: totals calculate as you type, with the spreadsheet's own formulas, and your entries stay in this browser. Download it filled in, print it or save it as a PDF, or take the blank file.

Frequently asked questions

What should a contractor work order include?

The contractor and license number, the contract reference, the customer and property, access rules, the scope summary, exclusions, materials and their specification, the price basis, the assigned carpenter and schedule, conditions found, work performed, change orders with signatures, open items and the customer's sign-off.

What is the difference between a contractor work order and a change order?

A work order takes the signed scope to the site for the day and records what was done. A change order amends the contract: it names added or removed work, its materials and price, and both parties sign it before the changed work starts.

Does a change order need to be signed in Minnesota?

Yes. Minnesota Statutes 326B.809 lists change orders among the agreements that must be in writing, with a detailed summary, the materials and the price or price basis, signed and dated by the licensee and the customer, with a signed copy to the customer at no charge.

Is there a contractor work order template for Word or PDF?

The page offers a free .xlsx download with no sign-up, not a Word file: a Template sheet with every field and a Sample sheet with the filled work order. Excel or Google Sheets saves it as a PDF; set out as a two-page Word or Google Docs form, it needs one change order block for each change on the job.

Does the license number have to be on a Minnesota contractor's paperwork?

Minnesota Statutes 326B.87 requires license numbers on business cards and contracts, and requires contracts to state that the person is licensed and give the number.

WO-2026-0731 and the $2,170 invoice

The Halvorsen door closed at 5:55 PM with seven scope steps done, one signed change order and a revised price of $2,170 that anyone can rebuild from the page. The decay behind CO-1 is in photos P3 to P5, and the 9:42 AM signature sits ahead of the work it approved. The next job's estimate and invoice forms are in the free field service templates. A FieldRanger account for the same jobs costs a per-technician rate shown on pricing, after a 14-day Start free trial that asks for no card.